Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1693 (New) |
190566-Dualization of road from katlang Bazar Doran Abad chowk (Chungi) Mardan |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 300 | 0 | 20 | 0 | 0 | 0 | 0 | 0 | - |
- July - 2020 |
Consultant appointed. DCE Under Prep.
Will be su |
No Image |
Mardan | |||||||||||||||||||
1693 (New) |
190566-Dualization of road from katlang Bazar Doran Abad chowk (Chungi) Mardan |
Mardan PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 300 | 0 | 20 | 20 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
PC-II approcved for Rs. 5 m .
LOA issued. |
No Image |
Mardan | |||||||||||||||||||
1693 (New) |
190566-Dualization of road from katlang Bazar Doran Abad chowk (Chungi) Mardan |
Mardan PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 300 | 0 | 20 | 20 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
PC-II approcved for Rs. 5 m .
LOA issued. |
No Image |
Mardan | |||||||||||||||||||
1693 (New) |
190566-Dualization of road from katlang Bazar Doran Abad chowk (Chungi) Mardan |
Mardan PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 300 | 0 | 20 | 20 | 0 | 0 | 0 | 0 | - |
- October - 2020 |
PC-II approcved for Rs. 5 m .
RFP called on 22/10/20. |
No Image |
Mardan | |||||||||||||||||||
1693 (New) |
190566-Dualization of road from katlang Bazar Doran Abad chowk (Chungi) Mardan |
Mardan PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 300 | 0 | 20 | 20 | 0 | 0 | 0 | 0 | - |
- September - 2020 |
PC-II approcved for Rs. 5 m .
RFP called on 22/10/20. |
No Image |
Mardan | |||||||||||||||||||
1693 (New) |
190566-Dualization of road from katlang Bazar Doran Abad chowk (Chungi) Mardan |
Mardan PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 300 | 0 | 20 | 20 | 0 | 0 | 0 | 0 | - |
- August - 2020 |
Consultant appointed. DCE Under Preparation. |
No Image |
Mardan | |||||||||||||||||||
1693 (New) |
190566-Dualization of road from katlang Bazar Doran Abad chowk (Chungi) Mardan |
Mardan PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 300 | 0 | 20 | 20 | 0 | 0 | 0 | 0 | - |
- May - 2021 |
PC-II approcved for Rs. 5 m.
Creative consultant LOA issued. |
No Image |
Mardan | |||||||||||||||||||
1693 (New) |
190566-Dualization of road from katlang Bazar Doran Abad chowk (Chungi) Mardan |
Mardan PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 300 | 0 | 20 | 20 | 0 | 0 | 0 | 0 | - |
- April - 2021 |
PC-II approcved for Rs. 5 m.
Creative consultant LOA issued. |
No Image |
Mardan | |||||||||||||||||||
1693 (New) |
190566-Dualization of road from katlang Bazar Doran Abad chowk (Chungi) Mardan |
Mardan PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 300 | 0 | 20 | 20 | 0 | 0 | 0 | 0 | - |
- March - 2021 |
PC-II approcved for Rs. 5 m.
Creative consultant LOA issued. |
No Image |
Mardan | |||||||||||||||||||
1693 (New) |
190566-Dualization of road from katlang Bazar Doran Abad chowk (Chungi) Mardan |
Mardan PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 300 | 0 | 20 | 20 | 0 | 0 | 0 | 0 | - |
- February - 2021 |
PC-II approcved for Rs. 5 m.
Creative consultant LOA issued. |
No Image |
Mardan | |||||||||||||||||||
1693 (New) |
190566-Dualization of road from katlang Bazar Doran Abad chowk (Chungi) Mardan |
Mardan PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 300 | 0 | 20 | 20 | 0 | 0 | 0 | 0 | - |
- January - 2021 |
PC-II approcved for Rs. 5 m.
Creative consultant LOA issued. |
No Image |
Mardan | |||||||||||||||||||
Pages : 1 |