Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2021, February - 2021, March - 2021, April - 2021, May - 2021, July - 2020, August - 2020, September - 2020, October - 2020, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1704
(New)
200249-Construction of Techinically & Economically Feasible 35 KMs Roads in Bannu Division.
Lakki Marwat
HW
30-11--1 30-11--1 - 30-11--1 - 15.42 0 0 0 0 0 0 15.42 - -
May - 2021
Work order issued
No Image
Const: of road form Gabmilla Adda to nazari Adda and Nazari adda to GT Road Sarai Naurang Amir Jan Bhatta Khast 27-KM in Distt: Lakki Marwat
1704
(New)
200249-Construction of Techinically & Economically Feasible 35 KMs Roads in Bannu Division.
Lakki Marwat
HW
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
April - 2021
Approved in PDWP on 18-11-2020. Minutes yet to arrive. Summary for change of scope (35 Km to 43 Km) and cost enhancement (Rs 400 M to Rs 640 M) to be approved.
No Image
1704
(New)
200249-Construction of Techinically & Economically Feasible 35 KMs Roads in Bannu Division.
Provincial
30-11--1 30-11--1 - 30-11--1 - 400 0 100 100 0 0 0 0 - -
December - 2020
Approved in PDWP on 18-11-2020. Minutes yet to arrive. Summary for change of scope (35 Km to 43 Km) and cost enhancement (Rs 400 M to Rs 640 M) to be approved.
No Image
1704
(New)
200249-Construction of Techinically & Economically Feasible 35 KMs Roads in Bannu Division.
Provincial
30-11--1 30-11--1 - 30-11--1 - 400 0 100 100 0 0 0 0 - -
December - 2020
Approved in PDWP on 18-11-2020. Minutes yet to arrive. Summary for change of scope (35 Km to 43 Km) and cost enhancement (Rs 400 M to Rs 640 M) to be approved.
No Image
1704
(New)
200249-Construction of Techinically & Economically Feasible 35 KMs Roads in Bannu Division.
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 400 0 100 100 0 0 0 0 - -
October - 2020
PC-I/DCE under preparation. Will be submitted by 30/10/2020.
No Image
1704
(New)
200249-Construction of Techinically & Economically Feasible 35 KMs Roads in Bannu Division.
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 400 0 100 100 0 0 0 0 - -
September - 2020
PC-I/DCE under preparation. Will be submitted by 30/10/2020.
No Image
1704
(New)
200249-Construction of Techinically & Economically Feasible 35 KMs Roads in Bannu Division.
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 400 0 100 100 0 0 0 0 - -
August - 2020
No Image
1704
(New)
200249-Construction of Techinically & Economically Feasible 35 KMs Roads in Bannu Division.
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 400 0 100 0 0 0 0 0 -
July - 2020
No Image
1704
(New)
200249-Construction of Techinically & Economically Feasible 35 KMs Roads in Bannu Division.
Provincial
30-11--1 30-11--1 - 30-11--1 - 400 0 100 100 0 0 0 0 - -
May - 2021
No Image
1704
(New)
200249-Construction of Techinically & Economically Feasible 35 KMs Roads in Bannu Division.
Provincial
30-11--1 30-11--1 - 30-11--1 - 400 0 100 100 0 0 0 0 - -
April - 2021
No Image
1704
(New)
200249-Construction of Techinically & Economically Feasible 35 KMs Roads in Bannu Division.
Provincial
30-11--1 30-11--1 - 30-11--1 - 400 0 100 100 0 0 0 0 - -
March - 2021
Approved in PDWP on 18-11-2020. Minutes yet to arrive. Summary for change of scope (35 Km to 43 Km) and cost enhancement (Rs 400 M to Rs 640 M) to be approved.
No Image
1704
(New)
200249-Construction of Techinically & Economically Feasible 35 KMs Roads in Bannu Division.
Provincial
30-11--1 30-11--1 - 30-11--1 - 400 0 100 100 0 0 0 0 - -
February - 2021
Approved in PDWP on 18-11-2020. Minutes yet to arrive. Summary for change of scope (35 Km to 43 Km) and cost enhancement (Rs 400 M to Rs 640 M) to be approved.
No Image
1704
(New)
200249-Construction of Techinically & Economically Feasible 35 KMs Roads in Bannu Division.
Provincial
30-11--1 30-11--1 - 30-11--1 - 400 0 100 100 0 0 0 0 - -
January - 2021
Approved in PDWP on 18-11-2020. Minutes yet to arrive. Summary for change of scope (35 Km to 43 Km) and cost enhancement (Rs 400 M to Rs 640 M) to be approved.
No Image
Pages : 1