Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2021, February - 2021, March - 2021, April - 2021, May - 2021, July - 2020, August - 2020, September - 2020, October - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1709
(OG)
140626-Construction of road from Amberi Killa to Daratang phase-II, SH: Km 17 to km 35 District Karak (19 km)
Karak
PKHA
30-11--1 30-11--1 - 30-11--1 - 798.06 501.5 40.575 40.575 20.2875 10.144 511.644 255.985 68% 64%
October - 2020
Length 19.925 Km - subtantially completed.
No Image
1) Package-1 (7 Km)
2) Package-2 (7 Km)
3) Package-3 (5.925 Km)
1709
(OG)
140626-Construction of road from Amberi Killa to Daratang phase-II, SH: Km 17 to km 35 District Karak (19 km)
Karak
PKHA
30-11--1 30-11--1 - 30-11--1 - 798.06 501.5 40.575 40.575 10.144 10.144 511.644 255.985 68% 64%
September - 2020
Length 19.925 Km - subtantially completed.
No Image
1) Package-1 (7 Km)
2) Package-2 (7 Km)
3) Package-3 (5.925 Km)
1709
(OG)
140626-Construction of road from Amberi Killa to Daratang phase-II, SH: Km 17 to km 35 District Karak (19 km)
Karak
PKHA
30-11--1 30-11--1 - 30-11--1 - 798.06 501.5 40.575 40.575 10.144 10.144 511.644 255.985 68% 64%
August - 2020
Length 19.925 Km - subtantially completed.
No Image
1) Package-1 (7 Km)
2) Package-2 (7 Km)
3) Package-3 (5.925 Km)
1709
(OG)
140626-Construction of road from Amberi Killa to Daratang phase-II, SH: Km 17 to km 35 District Karak (19 km)
Karak
PKHA
30-11--1 30-11--1 - 30-11--1 - 798.06 501.5 40.575 0 10.144 0 501.5 255.985 68% 63%
July - 2020
Length 19.925 Km - subtantially completed.
No Image
1) Package-1 (7 Km)
2) Package-
1709
(OG)
140626-Construction of road from Amberi Killa to Daratang phase-II, SH: Km 17 to km 35 District Karak (19 km)
Karak
PKHA
30-11--1 30-11--1 - 30-11--1 - 917.769 501.788 40.575 40.575 40.575 40.575 542.363 375.406 59% 59%
May - 2021
Length 19.925 Km - subtantially completed.
No Image
1. Package-1 (7 Km)? Rs. 250.055 M
2. Package-2 (7 Km)? Rs. 245.726 M
3. Package-3 (5.925 Km)? Rs. 216.722 M
1709
(OG)
140626-Construction of road from Amberi Killa to Daratang phase-II, SH: Km 17 to km 35 District Karak (19 km)
Karak
PKHA
30-11--1 30-11--1 - 30-11--1 - 917.769 501.788 40.575 40.575 40.575 40.575 542.363 375.406 59% 59%
April - 2021
Length 19.925 Km - subtantially completed.
No Image
1. Package-1 (7 Km)? Rs. 250.055 M
2. Package-2 (7 Km)? Rs. 245.726 M
3. Package-3 (5.925 Km)? Rs. 216.722 M
1709
(OG)
140626-Construction of road from Amberi Killa to Daratang phase-II, SH: Km 17 to km 35 District Karak (19 km)
Karak
PKHA
30-11--1 30-11--1 - 30-11--1 - 798.06 501.788 40.575 40.575 40.575 20.288 522.076 255.697 68% 65%
March - 2021
Length 19.925 Km - subtantially completed.
No Image
1. Package-1 (7 Km)? Rs. 250.055 M
2. Package-2 (7 Km)? Rs. 245.726 M
3. Package-3 (5.925 Km)? Rs. 216.722 M
1709
(OG)
140626-Construction of road from Amberi Killa to Daratang phase-II, SH: Km 17 to km 35 District Karak (19 km)
Karak
PKHA
30-11--1 30-11--1 - 30-11--1 - 798.06 501.788 40.575 40.575 40.575 20.288 522.076 255.697 68% 65%
February - 2021
Length 19.925 Km - subtantially completed.
No Image
1. Package-1 (7 Km)? Rs. 250.055 M
2. Package-2 (7 Km)? Rs. 245.726 M
3. Package-3 (5.925 Km)? Rs. 216.722 M
1709
(OG)
140626-Construction of road from Amberi Killa to Daratang phase-II, SH: Km 17 to km 35 District Karak (19 km)
Karak
PKHA
30-11--1 30-11--1 - 30-11--1 - 798.06 501.788 40.575 40.575 40.575 20.288 522.076 255.697 68% 65%
January - 2021
Length 19.925 Km - subtantially completed.
No Image
1. Package-1 (7 Km)? Rs. 250.055 M
2. Package-2 (7 Km)? Rs. 245.726 M
3. Package-3 (5.925 Km)? Rs. 216.722 M
Pages : 1