Progressive Review for the month(s) of : January - 2021, February - 2021, March - 2021, April - 2021, May - 2021, July - 2020, August - 2020, September - 2020, October - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1710
(OG)
140879-Improvement & Rehabilitation of road from Gulshanabad to Janana Mill via Hangu Pattak and Dualization of Old Bannu Road from Janana Mill to Kohat University (Indus Highway Juncation) (17.90-Km) i/c Construction of New Bridge at Jerma, District Koha
Kohat
PKHA
30-11--1 30-11--1 - 30-11--1 - 1403.483 1160.773 90 90 45 22.5 1183.273 152.71 89% 84%
October - 2020
04- Packages. sub base, sub grade, WBM,ABC,AWC, DST, PCC Shoulders Retaining Walls Side drain, Ancillary works completed.
No Image
1) Package-1 (Gulshan Chowk to Hangu Phatak)
2) Package-2 (Hangu Phatak to Saif CNG)
3) Package-3 (Saif CNG to Jerma Bridge Start Point)
4) Package-4 (Jerma Bridge via KUST to Main Indus Highway)
1710
(OG)
140879-Improvement & Rehabilitation of road from Gulshanabad to Janana Mill via Hangu Pattak and Dualization of Old Bannu Road from Janana Mill to Kohat University (Indus Highway Juncation) (17.90-Km) i/c Construction of New Bridge at Jerma, District Koha
Kohat
PKHA
30-11--1 30-11--1 - 30-11--1 - 1403.483 1160.773 90 90 22.5 22.5 1183.273 152.71 89% 84%
September - 2020
04- Packages. sub base, sub grade, WBM,ABC,AWC, DST, PCC Shoulders Retaining Walls Side drain, Ancillary works completed.
No Image
1) Package-1 (Gulshan Chowk to Hangu Phatak)
2) Package-2 (Hangu Phatak to Saif CNG)
3) Package-3 (Saif CNG to Jerma Bridge Start Point)
4) Package-4 (Jerma Bridge via KUST to Main Indus Highway)
1710
(OG)
140879-Improvement & Rehabilitation of road from Gulshanabad to Janana Mill via Hangu Pattak and Dualization of Old Bannu Road from Janana Mill to Kohat University (Indus Highway Juncation) (17.90-Km) i/c Construction of New Bridge at Jerma, District Koha
Kohat
PKHA
30-11--1 30-11--1 - 30-11--1 - 1403.483 1160.773 90 90 22.5 22.5 1183.273 152.71 89% 84%
August - 2020
04- Packages. sub base, sub grade, WBM,ABC,AWC, DST, PCC Shoulders Retaining Walls Side drain, Ancillary works completed.
No Image
1) Package-1 (Gulshan Chowk to Hangu Phatak)
2) Package-2 (Hangu Phatak to Saif CNG)
3) Package-3 (Saif CNG to Jerma Bridge Start Point)
4) Package-4 (Jerma Bridge via KUST to Main Indus Highway)
1710
(OG)
140879-Improvement & Rehabilitation of road from Gulshanabad to Janana Mill via Hangu Pattak and Dualization of Old Bannu Road from Janana Mill to Kohat University (Indus Highway Juncation) (17.90-Km) i/c Construction of New Bridge at Jerma, District Koha
Kohat
PKHA
30-11--1 30-11--1 - 30-11--1 - 1403.483 1160.773 90 0 22.5 0 1160.773 152.71 89% 83%
July - 2020
Pack-1 - sub base, sub grade, NGC, embankment comp
No Image
1) Package-1 (Gulshan Chowk to Hangu Phatak)<
1710
(OG)
140879-Improvement & Rehabilitation of road from Gulshanabad to Janana Mill via Hangu Pattak and Dualization of Old Bannu Road from Janana Mill to Kohat University (Indus Highway Juncation) (17.90-Km) i/c Construction of New Bridge at Jerma, District Koha
Kohat
PKHA
30-11--1 30-11--1 - 30-11--1 - 1403.483 1160.773 90 90 90 45 1205.773 152.71 89% 86%
May - 2021
04- Packages. sub base, sub grade, WBM,ABC,AWC, DST, PCC Shoulders Retaining Walls Side drain, Ancillary works completed.
No Image
1. Package-1 (Gulshan Chowk to Hangu Phatak)? Rs. 176.151 M
2. Package-2 (Hangu Phatak to Saif CNG)? Rs. 232.522 M
3. Package-3 (Saif CNG to Jerma Bridge Start Point)? Rs. 421.965 M
4. Package-4 (Jerma Bridge via KUST to Main Indus Highway)? Rs. 336.901 M
1710
(OG)
140879-Improvement & Rehabilitation of road from Gulshanabad to Janana Mill via Hangu Pattak and Dualization of Old Bannu Road from Janana Mill to Kohat University (Indus Highway Juncation) (17.90-Km) i/c Construction of New Bridge at Jerma, District Koha
Kohat
PKHA
30-11--1 30-11--1 - 30-11--1 - 1403.483 1160.773 90 90 90 45 1205.773 152.71 89% 86%
April - 2021
04- Packages. sub base, sub grade, WBM,ABC,AWC, DST, PCC Shoulders Retaining Walls Side drain, Ancillary works completed.
No Image
1. Package-1 (Gulshan Chowk to Hangu Phatak)? Rs. 176.151 M
2. Package-2 (Hangu Phatak to Saif CNG)? Rs. 232.522 M
3. Package-3 (Saif CNG to Jerma Bridge Start Point)? Rs. 421.965 M
4. Package-4 (Jerma Bridge via KUST to Main Indus Highway)? Rs. 336.901 M
1710
(OG)
140879-Improvement & Rehabilitation of road from Gulshanabad to Janana Mill via Hangu Pattak and Dualization of Old Bannu Road from Janana Mill to Kohat University (Indus Highway Juncation) (17.90-Km) i/c Construction of New Bridge at Jerma, District Koha
Kohat
PKHA
30-11--1 30-11--1 - 30-11--1 - 1403.483 1160.773 90 90 90 45 1205.773 152.71 89% 86%
March - 2021
04- Packages. sub base, sub grade, WBM,ABC,AWC, DST, PCC Shoulders Retaining Walls Side drain, Ancillary works completed.
No Image
1. Package-1 (Gulshan Chowk to Hangu Phatak)? Rs. 176.151 M
2. Package-2 (Hangu Phatak to Saif CNG)? Rs. 232.522 M
3. Package-3 (Saif CNG to Jerma Bridge Start Point)? Rs. 421.965 M
4. Package-4 (Jerma Bridge via KUST to Main Indus Highway)? Rs. 336.901 M
1710
(OG)
140879-Improvement & Rehabilitation of road from Gulshanabad to Janana Mill via Hangu Pattak and Dualization of Old Bannu Road from Janana Mill to Kohat University (Indus Highway Juncation) (17.90-Km) i/c Construction of New Bridge at Jerma, District Koha
Kohat
PKHA
30-11--1 30-11--1 - 30-11--1 - 1403.483 1160.773 90 90 90 45 1205.773 152.71 89% 86%
February - 2021
04- Packages. sub base, sub grade, WBM,ABC,AWC, DST, PCC Shoulders Retaining Walls Side drain, Ancillary works completed.
No Image
1. Package-1 (Gulshan Chowk to Hangu Phatak)? Rs. 176.151 M
2. Package-2 (Hangu Phatak to Saif CNG)? Rs. 232.522 M
3. Package-3 (Saif CNG to Jerma Bridge Start Point)? Rs. 421.965 M
4. Package-4 (Jerma Bridge via KUST to Main Indus Highway)? Rs. 336.901 M
1710
(OG)
140879-Improvement & Rehabilitation of road from Gulshanabad to Janana Mill via Hangu Pattak and Dualization of Old Bannu Road from Janana Mill to Kohat University (Indus Highway Juncation) (17.90-Km) i/c Construction of New Bridge at Jerma, District Koha
Kohat
PKHA
30-11--1 30-11--1 - 30-11--1 - 1403.483 1160.773 90 90 90 45 1205.773 152.71 89% 86%
January - 2021
04- Packages. sub base, sub grade, WBM,ABC,AWC, DST, PCC Shoulders Retaining Walls Side drain, Ancillary works completed.
No Image
1. Package-1 (Gulshan Chowk to Hangu Phatak)? Rs. 176.151 M
2. Package-2 (Hangu Phatak to Saif CNG)? Rs. 232.522 M
3. Package-3 (Saif CNG to Jerma Bridge Start Point)? Rs. 421.965 M
4. Package-4 (Jerma Bridge via KUST to Main Indus Highway)? Rs. 336.901 M