Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2021, February - 2021, March - 2021, April - 2021, May - 2021, July - 2020, August - 2020, September - 2020, October - 2020, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1714
(OG)
150287-Improvement of Takht-e-Bhai Rajjar Road from Ghani Khan road to Saro Shah (14 km), District Charsadda.
Charsadda
PKHA
30-11--1 30-11--1 - 30-11--1 - 1498.019 491.425 50 50 50 25 516.425 956.594 36% 34%
December - 2020
03- Packages Package -I (5Km) completed. Package-II& III in progress. Demand - Rs 1218 M.
No Image
Package-1? 5-KM... (Ghani Khan Road to Munaf Kali)
Package-2? 5-KM... (Munaf Kali to Ahmadabad)
Package-3? 4.025 -KM... (Ahmadabad to Saro Shah Bridge)
1714
(OG)
150287-Improvement of Takht-e-Bhai Rajjar Road from Ghani Khan road to Saro Shah (14 km), District Charsadda.
Charsadda
PKHA
30-11--1 30-11--1 - 30-11--1 - 1498.019 491.425 50 50 50 25 516.425 956.594 36% 34%
December - 2020
03- Packages Package -I (5Km) completed. Package-II& III in progress. Demand - Rs 1218 M.
No Image
Package-1? 5-KM... (Ghani Khan Road to Munaf Kali)
Package-2? 5-KM... (Munaf Kali to Ahmadabad)
Package-3? 4.025 -KM... (Ahmadabad to Saro Shah Bridge)
1714
(OG)
150287-Improvement of Takht-e-Bhai Rajjar Road from Ghani Khan road to Saro Shah (14 km), District Charsadda.
Charsadda
PKHA
30-11--1 30-11--1 - 30-11--1 - 1498.019 491.425 50 50 25 12 503.425 956.594 36% 34%
October - 2020
03- Packages Package -I (5Km) completed. Package-II& III in progress.
No Image
Package-1 (Ghani Khan Road to Munaf Kali)
Package-2 (Munaf Kali to Ahmadabad)
Package-3 (Ahmadabad to Saro Shah Bridge)
1714
(OG)
150287-Improvement of Takht-e-Bhai Rajjar Road from Ghani Khan road to Saro Shah (14 km), District Charsadda.
Charsadda
PKHA
30-11--1 30-11--1 - 30-11--1 - 1498.019 491.425 50 50 12 12 503.425 956.594 36% 34%
September - 2020
03- Packages Package -I (5Km) completed. Package-II& III in progress.
No Image
Package-1 (Ghani Khan Road to Munaf Kali)
Package-2 (Munaf Kali to Ahmadabad)
Package-3 (Ahmadabad to Saro Shah Bridge)
1714
(OG)
150287-Improvement of Takht-e-Bhai Rajjar Road from Ghani Khan road to Saro Shah (14 km), District Charsadda.
Charsadda
PKHA
30-11--1 30-11--1 - 30-11--1 - 1498.019 491.425 50 50 12.5 12.5 503.925 956.594 36% 34%
August - 2020
03- Packages Package -I (5Km) completed. Package-II& III in progress.
No Image
Package-1 (Ghani Khan Road to Munaf Kali)
Package-2 (Munaf Kali to Ahmadabad)
Package-3 (Ahmadabad to Saro Shah Bridge)
1714
(OG)
150287-Improvement of Takht-e-Bhai Rajjar Road from Ghani Khan road to Saro Shah (14 km), District Charsadda.
Charsadda
PKHA
30-11--1 30-11--1 - 30-11--1 - 1498.019 491.425 50 0 12.5 0 491.425 956.594 36% 33%
July - 2020
Work in progress on 2 Nos culverts. Trees and stum
No Image
Package-1 (Ghani Khan Road to Munaf Kali)
1714
(OG)
150287-Improvement of Takht-e-Bhai Rajjar Road from Ghani Khan road to Saro Shah (14 km), District Charsadda.
Charsadda
PKHA
30-11--1 30-11--1 - 30-11--1 - 1498.019 491.425 50 75 75 75 566.425 956.594 36% 38%
May - 2021
03- Packages Package -I (5Km) completed. Package-II& III in progress. Demand - Rs 1218 M.
No Image
Package-1? 5-KM... (Ghani Khan Road to Munaf Kali)
Package-2? 5-KM... (Munaf Kali to Ahmadabad)
Package-3? 4.025 -KM... (Ahmadabad to Saro Shah Bridge)
1714
(OG)
150287-Improvement of Takht-e-Bhai Rajjar Road from Ghani Khan road to Saro Shah (14 km), District Charsadda.
Charsadda
PKHA
30-11--1 30-11--1 - 30-11--1 - 1498.019 491.425 50 75 75 75 566.425 956.594 36% 38%
April - 2021
03- Packages Package -I (5Km) completed. Package-II& III in progress. Demand - Rs 1218 M.
No Image
Package-1? 5-KM... (Ghani Khan Road to Munaf Kali)
Package-2? 5-KM... (Munaf Kali to Ahmadabad)
Package-3? 4.025 -KM... (Ahmadabad to Saro Shah Bridge)
1714
(OG)
150287-Improvement of Takht-e-Bhai Rajjar Road from Ghani Khan road to Saro Shah (14 km), District Charsadda.
Charsadda
PKHA
30-11--1 30-11--1 - 30-11--1 - 1498.019 491.425 50 50 50 25 516.425 956.594 36% 34%
March - 2021
03- Packages Package -I (5Km) completed. Package-II& III in progress. Demand - Rs 1218 M.
No Image
Package-1? 5-KM... (Ghani Khan Road to Munaf Kali)
Package-2? 5-KM... (Munaf Kali to Ahmadabad)
Package-3? 4.025 -KM... (Ahmadabad to Saro Shah Bridge)
1714
(OG)
150287-Improvement of Takht-e-Bhai Rajjar Road from Ghani Khan road to Saro Shah (14 km), District Charsadda.
Charsadda
PKHA
30-11--1 30-11--1 - 30-11--1 - 1498.019 491.425 50 50 50 25 516.425 956.594 36% 34%
February - 2021
03- Packages Package -I (5Km) completed. Package-II& III in progress. Demand - Rs 1218 M.
No Image
Package-1? 5-KM... (Ghani Khan Road to Munaf Kali)
Package-2? 5-KM... (Munaf Kali to Ahmadabad)
Package-3? 4.025 -KM... (Ahmadabad to Saro Shah Bridge)
1714
(OG)
150287-Improvement of Takht-e-Bhai Rajjar Road from Ghani Khan road to Saro Shah (14 km), District Charsadda.
Charsadda
PKHA
30-11--1 30-11--1 - 30-11--1 - 1498.019 491.425 50 50 50 25 516.425 956.594 36% 34%
January - 2021
03- Packages Package -I (5Km) completed. Package-II& III in progress. Demand - Rs 1218 M.
No Image
Package-1? 5-KM... (Ghani Khan Road to Munaf Kali)
Package-2? 5-KM... (Munaf Kali to Ahmadabad)
Package-3? 4.025 -KM... (Ahmadabad to Saro Shah Bridge)
Pages : 1