Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2021, February - 2021, March - 2021, April - 2021, May - 2021, July - 2020, August - 2020, September - 2020, October - 2020, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1719
(OG)
180622-Feasibility studies of Oughday (Takhta Band) to Kabal Bridge & Ningolai to Allah Abad Bridge, Swat.
Swat
PKHA
30-11--1 30-11--1 - 30-11--1 - 12.4 8.823 3.577 3.577 3.577 0 8.823 0 100% 71%
December - 2020
Overlapping with Swat Expressway Phase II. Scheme. Completion : June-2021.
No Image
Swat
1719
(OG)
180622-Feasibility studies of Oughday (Takhta Band) to Kabal Bridge & Ningolai to Allah Abad Bridge, Swat.
Swat
PKHA
30-11--1 30-11--1 - 30-11--1 - 12.4 8.823 3.577 3.577 3.577 0 8.823 0 100% 71%
December - 2020
Overlapping with Swat Expressway Phase II. Scheme. Completion : June-2021.
No Image
Swat
1719
(OG)
180622-Feasibility studies of Oughday (Takhta Band) to Kabal Bridge & Ningolai to Allah Abad Bridge, Swat.
Swat
PKHA
30-11--1 30-11--1 - 30-11--1 - 12.4 8.823 3.577 3.577 3.577 3.577 12.4 0 100% 100%
October - 2020
Overlapping with Swat Expressway Phase II. Scheme. Completion : June-2021.
No Image
Swat
1719
(OG)
180622-Feasibility studies of Oughday (Takhta Band) to Kabal Bridge & Ningolai to Allah Abad Bridge, Swat.
Swat
PKHA
30-11--1 30-11--1 - 30-11--1 - 12.4 8.823 3.577 3.577 3.577 3.577 12.4 0 100% 100%
September - 2020
Overlapping with Swat Expressway Phase II. Scheme. Completion : June-2021.
No Image
Swat
1719
(OG)
180622-Feasibility studies of Oughday (Takhta Band) to Kabal Bridge & Ningolai to Allah Abad Bridge, Swat.
Swat
PKHA
30-11--1 30-11--1 - 30-11--1 - 12.4 8.823 3.577 3.577 3.577 3.577 12.4 0 100% 100%
August - 2020
Overlapping with Swat Expressway Phase II. Scheme. Completion : June-2021.
No Image
Swat
1719
(OG)
180622-Feasibility studies of Oughday (Takhta Band) to Kabal Bridge & Ningolai to Allah Abad Bridge, Swat.
Swat
PKHA
30-11--1 30-11--1 - 30-11--1 - 12.4 8.823 3.577 0 3.577 0 8.823 0 100% 71%
July - 2020
Overlapping with Swat Expressway Phase II. Scheme
No Image
Swat
1719
(OG)
180622-Feasibility studies of Oughday (Takhta Band) to Kabal Bridge & Ningolai to Allah Abad Bridge, Swat.
Swat
PKHA
30-11--1 30-11--1 - 30-11--1 - 12.4 8.823 3.577 3.577 3.577 0 8.823 0 100% 71%
May - 2021
work stopped due to motorway phase II. Overlapping with Swat Expressway Phase II. Scheme. Completion : June-2021.
No Image
 Swat
1719
(OG)
180622-Feasibility studies of Oughday (Takhta Band) to Kabal Bridge & Ningolai to Allah Abad Bridge, Swat.
Swat
PKHA
30-11--1 30-11--1 - 30-11--1 - 12.4 8.823 3.577 3.577 3.577 0 8.823 0 100% 71%
April - 2021
work stopped due to motorway phase II. Overlapping with Swat Expressway Phase II. Scheme. Completion : June-2021.
No Image
 Swat
1719
(OG)
180622-Feasibility studies of Oughday (Takhta Band) to Kabal Bridge & Ningolai to Allah Abad Bridge, Swat.
Swat
PKHA
30-11--1 30-11--1 - 30-11--1 - 12.4 8.823 3.577 3.577 3.577 0 8.823 0 100% 71%
March - 2021
work stopped due to motorway phase II. Overlapping with Swat Expressway Phase II. Scheme. Completion : June-2021.
No Image
 Swat
1719
(OG)
180622-Feasibility studies of Oughday (Takhta Band) to Kabal Bridge & Ningolai to Allah Abad Bridge, Swat.
Swat
PKHA
30-11--1 30-11--1 - 30-11--1 - 12.4 8.823 3.577 3.577 3.577 0 8.823 0 100% 71%
February - 2021
work stopped due to motorway phase II. Overlapping with Swat Expressway Phase II. Scheme. Completion : June-2021.
No Image
 Swat
1719
(OG)
180622-Feasibility studies of Oughday (Takhta Band) to Kabal Bridge & Ningolai to Allah Abad Bridge, Swat.
Swat
PKHA
30-11--1 30-11--1 - 30-11--1 - 12.4 8.823 3.577 3.577 3.577 0 8.823 0 100% 71%
January - 2021
work stopped due to motorway phase II. Overlapping with Swat Expressway Phase II. Scheme. Completion : June-2021.
No Image
 Swat
Pages : 1