Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1719 (OG) |
180622-Feasibility studies of Oughday (Takhta Band) to Kabal Bridge & Ningolai to Allah Abad Bridge, Swat. |
Swat PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 12.4 | 8.823 | 3.577 | 3.577 | 3.577 | 0 | 8.823 | 0 | 100% |
71% December - 2020 |
Overlapping with Swat Expressway Phase II. Scheme.
Completion : June-2021. |
No Image |
Swat | |||||||||||||||||||
1719 (OG) |
180622-Feasibility studies of Oughday (Takhta Band) to Kabal Bridge & Ningolai to Allah Abad Bridge, Swat. |
Swat PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 12.4 | 8.823 | 3.577 | 3.577 | 3.577 | 0 | 8.823 | 0 | 100% |
71% December - 2020 |
Overlapping with Swat Expressway Phase II. Scheme.
Completion : June-2021. |
No Image |
Swat | |||||||||||||||||||
1719 (OG) |
180622-Feasibility studies of Oughday (Takhta Band) to Kabal Bridge & Ningolai to Allah Abad Bridge, Swat. |
Swat PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 12.4 | 8.823 | 3.577 | 3.577 | 3.577 | 3.577 | 12.4 | 0 | 100% |
100% October - 2020 |
Overlapping with Swat Expressway Phase II. Scheme.
Completion : June-2021. |
No Image |
Swat | |||||||||||||||||||
1719 (OG) |
180622-Feasibility studies of Oughday (Takhta Band) to Kabal Bridge & Ningolai to Allah Abad Bridge, Swat. |
Swat PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 12.4 | 8.823 | 3.577 | 3.577 | 3.577 | 3.577 | 12.4 | 0 | 100% |
100% September - 2020 |
Overlapping with Swat Expressway Phase II. Scheme.
Completion : June-2021. |
No Image |
Swat | |||||||||||||||||||
1719 (OG) |
180622-Feasibility studies of Oughday (Takhta Band) to Kabal Bridge & Ningolai to Allah Abad Bridge, Swat. |
Swat PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 12.4 | 8.823 | 3.577 | 3.577 | 3.577 | 3.577 | 12.4 | 0 | 100% |
100% August - 2020 |
Overlapping with Swat Expressway Phase II. Scheme.
Completion : June-2021. |
No Image |
Swat | |||||||||||||||||||
1719 (OG) |
180622-Feasibility studies of Oughday (Takhta Band) to Kabal Bridge & Ningolai to Allah Abad Bridge, Swat. |
Swat PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 12.4 | 8.823 | 3.577 | 0 | 3.577 | 0 | 8.823 | 0 | 100% |
71% July - 2020 |
Overlapping with Swat Expressway Phase II. Scheme |
No Image |
Swat | |||||||||||||||||||
1719 (OG) |
180622-Feasibility studies of Oughday (Takhta Band) to Kabal Bridge & Ningolai to Allah Abad Bridge, Swat. |
Swat PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 12.4 | 8.823 | 3.577 | 3.577 | 3.577 | 0 | 8.823 | 0 | 100% |
71% May - 2021 |
work stopped due to motorway phase II.
Overlapping with Swat Expressway Phase II. Scheme.
Completion : June-2021. |
No Image |
Swat | |||||||||||||||||||
1719 (OG) |
180622-Feasibility studies of Oughday (Takhta Band) to Kabal Bridge & Ningolai to Allah Abad Bridge, Swat. |
Swat PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 12.4 | 8.823 | 3.577 | 3.577 | 3.577 | 0 | 8.823 | 0 | 100% |
71% April - 2021 |
work stopped due to motorway phase II.
Overlapping with Swat Expressway Phase II. Scheme.
Completion : June-2021. |
No Image |
Swat | |||||||||||||||||||
1719 (OG) |
180622-Feasibility studies of Oughday (Takhta Band) to Kabal Bridge & Ningolai to Allah Abad Bridge, Swat. |
Swat PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 12.4 | 8.823 | 3.577 | 3.577 | 3.577 | 0 | 8.823 | 0 | 100% |
71% March - 2021 |
work stopped due to motorway phase II.
Overlapping with Swat Expressway Phase II. Scheme.
Completion : June-2021. |
No Image |
Swat | |||||||||||||||||||
1719 (OG) |
180622-Feasibility studies of Oughday (Takhta Band) to Kabal Bridge & Ningolai to Allah Abad Bridge, Swat. |
Swat PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 12.4 | 8.823 | 3.577 | 3.577 | 3.577 | 0 | 8.823 | 0 | 100% |
71% February - 2021 |
work stopped due to motorway phase II.
Overlapping with Swat Expressway Phase II. Scheme.
Completion : June-2021. |
No Image |
Swat | |||||||||||||||||||
1719 (OG) |
180622-Feasibility studies of Oughday (Takhta Band) to Kabal Bridge & Ningolai to Allah Abad Bridge, Swat. |
Swat PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 12.4 | 8.823 | 3.577 | 3.577 | 3.577 | 0 | 8.823 | 0 | 100% |
71% January - 2021 |
work stopped due to motorway phase II.
Overlapping with Swat Expressway Phase II. Scheme.
Completion : June-2021. |
No Image |
Swat | |||||||||||||||||||
Pages : 1 |