1720 (OG) |
190510-Construction of Oughday (Takhta Band) to Kabal Bridge & Ningolai to Allah Abad Bridge, Swat. |
Swat PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 4303.024 | 0 | 80 | 80 | 80 | 0 | 0 | 4223.024 | 2% |
- December - 2020 |
Bridges are overlapping the proposed aligment of swat Express-way.The issue has been discussed with Chief Minister KP and it was decided to keep hold the bridge till finalization of Express-way Phase-II |
No Image |
1720 (OG) |
190510-Construction of Oughday (Takhta Band) to Kabal Bridge & Ningolai to Allah Abad Bridge, Swat. |
Swat PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 4303.024 | 0 | 80 | 80 | 80 | 0 | 0 | 4223.024 | 2% |
- December - 2020 |
Bridges are overlapping the proposed aligment of swat Express-way.The issue has been discussed with Chief Minister KP and it was decided to keep hold the bridge till finalization of Express-way Phase-II |
No Image |
1720 (OG) |
190510-Construction of Oughday (Takhta Band) to Kabal Bridge & Ningolai to Allah Abad Bridge, Swat. |
Swat PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 4303.024 | 0 | 80 | 80 | 60 | 11.429 | 11.429 | 4223.024 | 2% |
0% October - 2020 |
Bridges are overlapping the proposed aligment of swat Express-way.The issue has been discussed with Chief Minister KP and it was decided to keep hold the bridge till finalization of Express-way Phase-II |
No Image |
1720 (OG) |
190510-Construction of Oughday (Takhta Band) to Kabal Bridge & Ningolai to Allah Abad Bridge, Swat. |
Swat PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 4303.024 | 0 | 80 | 80 | 11.429 | 11.429 | 11.429 | 4223.024 | 2% |
0% September - 2020 |
Bridges are overlapping the proposed aligment of swat Express-way.The issue has been discussed with Chief Minister KP and it was decided to keep hold the bridge till finalization of Express-way Phase-II |
No Image |
1720 (OG) |
190510-Construction of Oughday (Takhta Band) to Kabal Bridge & Ningolai to Allah Abad Bridge, Swat. |
Swat PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 4303.024 | 0 | 80 | 80 | 11.429 | 11.429 | 11.429 | 4223.024 | 2% |
0% August - 2020 |
Bridges are overlapping the proposed aligment of swat Express-way.The issue has been discussed with Chief Minister KP and it was decided to keep hold the bridge till finalization of Express-way Phase-II |
No Image |
1720 (OG) |
190510-Construction of Oughday (Takhta Band) to Kabal Bridge & Ningolai to Allah Abad Bridge, Swat. |
Swat PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 4303.024 | 0 | 80 | 0 | 11.429 | 0 | 0 | 4223.024 | 2% |
- July - 2020 |
Approved. Pre-qualification has been invited. |
No Image |
1720 (OG) |
190510-Construction of Oughday (Takhta Band) to Kabal Bridge & Ningolai to Allah Abad Bridge, Swat. |
Swat PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 4303.024 | 0 | 80 | 0 | 0 | 0 | 0 | 0 |
May - 2021 |
work stopped due to motorway phase II.
Bridges are overlapping the proposed aligment of swat Express-way.The issue has been discussed with Chief Minister KP and it was decided to keep hold the bridge till finalization of Express-way Phase-II |
No Image | |
Bridge | |||||||||||||||||||
1720 (OG) |
190510-Construction of Oughday (Takhta Band) to Kabal Bridge & Ningolai to Allah Abad Bridge, Swat. |
Swat PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 4303.024 | 0 | 80 | 0 | 0 | 0 | 0 | 0 |
April - 2021 |
work stopped due to motorway phase II.
Bridges are overlapping the proposed aligment of swat Express-way.The issue has been discussed with Chief Minister KP and it was decided to keep hold the bridge till finalization of Express-way Phase-II |
No Image | |
Bridge | |||||||||||||||||||
1720 (OG) |
190510-Construction of Oughday (Takhta Band) to Kabal Bridge & Ningolai to Allah Abad Bridge, Swat. |
Swat PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 4303.024 | 0 | 80 | 0 | 0 | 0 | 0 | 0 |
March - 2021 |
work stopped due to motorway phase II.
Bridges are overlapping the proposed aligment of swat Express-way.The issue has been discussed with Chief Minister KP and it was decided to keep hold the bridge till finalization of Express-way Phase-II |
No Image | |
Bridge | |||||||||||||||||||
1720 (OG) |
190510-Construction of Oughday (Takhta Band) to Kabal Bridge & Ningolai to Allah Abad Bridge, Swat. |
Swat PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 4303.024 | 0 | 80 | 0 | 0 | 0 | 0 | 0 |
February - 2021 |
work stopped due to motorway phase II.
Bridges are overlapping the proposed aligment of swat Express-way.The issue has been discussed with Chief Minister KP and it was decided to keep hold the bridge till finalization of Express-way Phase-II |
No Image | |
Bridge | |||||||||||||||||||
1720 (OG) |
190510-Construction of Oughday (Takhta Band) to Kabal Bridge & Ningolai to Allah Abad Bridge, Swat. |
Swat PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 4303.024 | 0 | 80 | 80 | 80 | 0 | 0 | 0 |
January - 2021 |
work stopped due to motorway phase II.
Bridges are overlapping the proposed aligment of swat Express-way.The issue has been discussed with Chief Minister KP and it was decided to keep hold the bridge till finalization of Express-way Phase-II |
No Image | |