Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2021, February - 2021, March - 2021, April - 2021, May - 2021, July - 2020, August - 2020, September - 2020, October - 2020, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1723
(OG)
140623-Construction of road from Balambat Timergara to Kalpani Maidan Link road District Dir Lower.
Dir Lower
PKHA
30-11--1 30-11--1 - 30-11--1 - 689.999 382.725 40 40 40 30 412.725 267.274 61% 60%
December - 2020
Substantially completed. Shifting of Electric pole in progress.
No Image
Package-1.?. 3.5-KM
Package-2.?. 3.5-KM
Package-3.?. 3.0-KM
1723
(OG)
140623-Construction of road from Balambat Timergara to Kalpani Maidan Link road District Dir Lower.
Dir Lower
PKHA
30-11--1 30-11--1 - 30-11--1 - 689.999 382.725 40 40 40 30 412.725 267.274 61% 60%
December - 2020
Substantially completed. Shifting of Electric pole in progress.
No Image
Package-1.?. 3.5-KM
Package-2.?. 3.5-KM
Package-3.?. 3.0-KM
1723
(OG)
140623-Construction of road from Balambat Timergara to Kalpani Maidan Link road District Dir Lower.
Dir Lower
PKHA
30-11--1 30-11--1 - 30-11--1 - 689.999 382.725 40 40 30 10 392.725 267.274 61% 57%
October - 2020
Substantially completed. Shifting of Electric pole in progress.
No Image
Package-1
Package-2
1723
(OG)
140623-Construction of road from Balambat Timergara to Kalpani Maidan Link road District Dir Lower.
Dir Lower
PKHA
30-11--1 30-11--1 - 30-11--1 - 689.999 382.725 40 40 10 10 392.725 267.274 61% 57%
September - 2020
Substantially completed. Shifting of Electric pole in progress.
No Image
Package-1
Package-2
1723
(OG)
140623-Construction of road from Balambat Timergara to Kalpani Maidan Link road District Dir Lower.
Dir Lower
PKHA
30-11--1 30-11--1 - 30-11--1 - 689.999 382.725 40 40 10 10 392.725 267.274 61% 57%
August - 2020
Substantially completed. Shifting of Electric pole in progress.
No Image
Package-1
Package-2
1723
(OG)
140623-Construction of road from Balambat Timergara to Kalpani Maidan Link road District Dir Lower.
Dir Lower
PKHA
30-11--1 30-11--1 - 30-11--1 - 689.999 382.725 40 0 10 0 382.725 267.274 61% 55%
July - 2020
Substantially completed. Shifting of Electric pole
No Image
Package-1
Package-2
1723
(OG)
140623-Construction of road from Balambat Timergara to Kalpani Maidan Link road District Dir Lower.
Dir Lower
PKHA
30-11--1 30-11--1 - 30-11--1 - 689.999 382.725 40 40 40 40 422.725 267.274 61% 61%
May - 2021
Substantially completed. Shifting of Electric pole in progress.
No Image
Package-1.?. 3.5-KM
Package-2.?. 3.5-KM
Package-3.?. 3.0-KM
1723
(OG)
140623-Construction of road from Balambat Timergara to Kalpani Maidan Link road District Dir Lower.
Dir Lower
PKHA
30-11--1 30-11--1 - 30-11--1 - 689.999 382.725 40 40 40 40 422.725 267.274 61% 61%
April - 2021
Substantially completed. Shifting of Electric pole in progress.
No Image
Package-1.?. 3.5-KM
Package-2.?. 3.5-KM
Package-3.?. 3.0-KM
1723
(OG)
140623-Construction of road from Balambat Timergara to Kalpani Maidan Link road District Dir Lower.
Dir Lower
PKHA
30-11--1 30-11--1 - 30-11--1 - 689.999 382.725 40 40 40 30 412.725 267.274 61% 60%
March - 2021
Substantially completed. Shifting of Electric pole in progress.
No Image
Package-1.?. 3.5-KM
Package-2.?. 3.5-KM
Package-3.?. 3.0-KM
1723
(OG)
140623-Construction of road from Balambat Timergara to Kalpani Maidan Link road District Dir Lower.
Dir Lower
PKHA
30-11--1 30-11--1 - 30-11--1 - 689.999 382.725 40 40 40 30 412.725 267.274 61% 60%
February - 2021
Substantially completed. Shifting of Electric pole in progress.
No Image
Package-1.?. 3.5-KM
Package-2.?. 3.5-KM
Package-3.?. 3.0-KM
1723
(OG)
140623-Construction of road from Balambat Timergara to Kalpani Maidan Link road District Dir Lower.
Dir Lower
PKHA
30-11--1 30-11--1 - 30-11--1 - 689.999 382.725 40 40 40 30 412.725 267.274 61% 60%
January - 2021
Substantially completed. Shifting of Electric pole in progress.
No Image
Package-1.?. 3.5-KM
Package-2.?. 3.5-KM
Package-3.?. 3.0-KM
Pages : 1