Progressive Review for the month(s) of : January - 2021, February - 2021, March - 2021, April - 2021, May - 2021, July - 2020, August - 2020, September - 2020, October - 2020, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1728
(OG)
140877-Construction of Haripur Bypass Road (23-KM).
Haripur
PKHA
30-11--1 30-11--1 - 30-11--1 - 4982.992 3269.313 100 100 100 75 3344.313 1613.679 68% 67%
December - 2020
Length 23 Km - (07-Packages) sub base, sub grade, ABC, AWC, in progress. Demand - Rs 2386.047 M.
No Image
Package-1 Chungi No.11 Khanpur Road (5.250- KM)
Package-2 Panian to Chorh Village (5.250- KM)
Package-3 Chorch Village to Mankaray/Morha Mamdu (5.90 - KM)
Package-4 Mankaray/Morha Mamdu to Garh Village (4.20 - KM)
Package-5 Garh Village to Changi Bandi (3.83 - KM)
Package-6 03 Nos Birdges
Package-7 03 Nos Flyover
1728
(OG)
140877-Construction of Haripur Bypass Road (23-KM).
Haripur
PKHA
30-11--1 30-11--1 - 30-11--1 - 4982.992 3269.313 100 100 100 75 3344.313 1613.679 68% 67%
December - 2020
Length 23 Km - (07-Packages) sub base, sub grade, ABC, AWC, in progress. Demand - Rs 2386.047 M.
No Image
Package-1 Chungi No.11 Khanpur Road (5.250- KM)
Package-2 Panian to Chorh Village (5.250- KM)
Package-3 Chorch Village to Mankaray/Morha Mamdu (5.90 - KM)
Package-4 Mankaray/Morha Mamdu to Garh Village (4.20 - KM)
Package-5 Garh Village to Changi Bandi (3.83 - KM)
Package-6 03 Nos Birdges
Package-7 03 Nos Flyover
1728
(OG)
140877-Construction of Haripur Bypass Road (23-KM).
Haripur
PKHA
30-11--1 30-11--1 - 30-11--1 - 4982.992 3269.313 100 100 75 25 3294.313 1613.679 68% 66%
October - 2020
Length 23 Km - (07-Packages) sub base, sub grade, ABC, AWC, in progress.
No Image
1728
(OG)
140877-Construction of Haripur Bypass Road (23-KM).
Haripur
PKHA
30-11--1 30-11--1 - 30-11--1 - 4982.992 3269.313 100 100 25 25 3294.313 1613.679 68% 66%
September - 2020
Length 23 Km - (07-Packages) sub base, sub grade, ABC, AWC, in progress.
No Image
1728
(OG)
140877-Construction of Haripur Bypass Road (23-KM).
Haripur
PKHA
30-11--1 30-11--1 - 30-11--1 - 4982.992 3269.313 100 100 25 25 3294.313 1613.679 68% 66%
August - 2020
Length 23 Km - (07-Packages) sub base, sub grade, ABC, AWC, in progress.
No Image
1728
(OG)
140877-Construction of Haripur Bypass Road (23-KM).
Haripur
PKHA
30-11--1 30-11--1 - 30-11--1 - 4982.992 3269.313 100 0 25 0 3269.313 1613.679 68% 66%
July - 2020
Length 23 Km - Pack-1 (5.25 Km) sub base, sub gra
No Image
1728
(OG)
140877-Construction of Haripur Bypass Road (23-KM).
Haripur
PKHA
30-11--1 30-11--1 - 30-11--1 - 4982.922 3269.313 100 198 198 198 3467.313 1613.609 68% 70%
May - 2021
Length 23 Km - (07-Packages) sub base, sub grade, ABC, AWC, in progress. Demand - Rs 2386.047 M.
No Image
Package-1 Chungi No.11 Khanpur Road (5.250- KM)
Package-2 Panian to Chorh Village (5.250- KM)
Package-3 Chorch Village to Mankaray/Morha Mamdu (5.90 - KM)
Package-4 Mankaray/Morha Mamdu to Garh Village (4.20 - KM)
Package-5 Garh Village to Changi Bandi (3.83 - KM)
Package-6 03 Nos Birdges
Package-7 03 Nos Flyover
1728
(OG)
140877-Construction of Haripur Bypass Road (23-KM).
Haripur
PKHA
30-11--1 30-11--1 - 30-11--1 - 4982.922 3269.313 100 198 198 198 3467.313 1613.609 68% 70%
April - 2021
Length 23 Km - (07-Packages) sub base, sub grade, ABC, AWC, in progress. Demand - Rs 2386.047 M.
No Image
Package-1 Chungi No.11 Khanpur Road (5.250- KM)
Package-2 Panian to Chorh Village (5.250- KM)
Package-3 Chorch Village to Mankaray/Morha Mamdu (5.90 - KM)
Package-4 Mankaray/Morha Mamdu to Garh Village (4.20 - KM)
Package-5 Garh Village to Changi Bandi (3.83 - KM)
Package-6 03 Nos Birdges
Package-7 03 Nos Flyover
1728
(OG)
140877-Construction of Haripur Bypass Road (23-KM).
Haripur
PKHA
30-11--1 30-11--1 - 30-11--1 - 4982.922 3269.313 100 100 100 75 3344.313 1613.609 68% 67%
March - 2021
Length 23 Km - (07-Packages) sub base, sub grade, ABC, AWC, in progress. Demand - Rs 2386.047 M.
No Image
Package-1 Chungi No.11 Khanpur Road (5.250- KM)
Package-2 Panian to Chorh Village (5.250- KM)
Package-3 Chorch Village to Mankaray/Morha Mamdu (5.90 - KM)
Package-4 Mankaray/Morha Mamdu to Garh Village (4.20 - KM)
Package-5 Garh Village to Changi Bandi (3.83 - KM)
Package-6 03 Nos Birdges
Package-7 03 Nos Flyover
1728
(OG)
140877-Construction of Haripur Bypass Road (23-KM).
Haripur
PKHA
30-11--1 30-11--1 - 30-11--1 - 4982.922 3269.313 100 100 100 75 3344.313 1613.609 68% 67%
February - 2021
Length 23 Km - (07-Packages) sub base, sub grade, ABC, AWC, in progress. Demand - Rs 2386.047 M.
No Image
Package-1 Chungi No.11 Khanpur Road (5.250- KM)
Package-2 Panian to Chorh Village (5.250- KM)
Package-3 Chorch Village to Mankaray/Morha Mamdu (5.90 - KM)
Package-4 Mankaray/Morha Mamdu to Garh Village (4.20 - KM)
Package-5 Garh Village to Changi Bandi (3.83 - KM)
Package-6 03 Nos Birdges
Package-7 03 Nos Flyover
1728
(OG)
140877-Construction of Haripur Bypass Road (23-KM).
Haripur
PKHA
30-11--1 30-11--1 - 30-11--1 - 4982.922 3269.313 100 100 100 75 3344.313 1613.609 68% 67%
January - 2021
Length 23 Km - (07-Packages) sub base, sub grade, ABC, AWC, in progress. Demand - Rs 2386.047 M.
No Image
Package-1 Chungi No.11 Khanpur Road (5.250- KM)
Package-2 Panian to Chorh Village (5.250- KM)
Package-3 Chorch Village to Mankaray/Morha Mamdu (5.90 - KM)
Package-4 Mankaray/Morha Mamdu to Garh Village (4.20 - KM)
Package-5 Garh Village to Changi Bandi (3.83 - KM)
Package-6 03 Nos Birdges
Package-7 03 Nos Flyover