Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2021, February - 2021, March - 2021, April - 2021, May - 2021, July - 2020, August - 2020, September - 2020, October - 2020, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1730
(OG)
190341-Widening / Improvement / Rehabilitation of road from Beer to Kalangir on Haripur - Chappar Road Section of Provincial Highway S-12 (17 Km)
Haripur
PKHA
30-11--1 30-11--1 - 30-11--1 - 1274.72 0 10 10 10 7.5 7.5 1264.72 1% 1%
December - 2020
work order issued.
No Image
1730
(OG)
190341-Widening / Improvement / Rehabilitation of road from Beer to Kalangir on Haripur - Chappar Road Section of Provincial Highway S-12 (17 Km)
Haripur
PKHA
30-11--1 30-11--1 - 30-11--1 - 1274.72 0 10 10 10 7.5 7.5 1264.72 1% 1%
December - 2020
work order issued.
No Image
1730
(OG)
190341-Widening / Improvement / Rehabilitation of road from Beer to Kalangir on Haripur - Chappar Road Section of Provincial Highway S-12 (17 Km)
Haripur
PKHA
30-11--1 30-11--1 - 30-11--1 - 1274.72 0 10 10 7.5 1.429 1.429 1264.72 1% 0%
October - 2020
LOA issued to contractor.
No Image
1730
(OG)
190341-Widening / Improvement / Rehabilitation of road from Beer to Kalangir on Haripur - Chappar Road Section of Provincial Highway S-12 (17 Km)
Haripur
PKHA
30-11--1 30-11--1 - 30-11--1 - 1274.72 0 10 10 1.429 1.429 1.429 1264.72 1% 0%
September - 2020
LOA issued to contractor.
No Image
1730
(OG)
190341-Widening / Improvement / Rehabilitation of road from Beer to Kalangir on Haripur - Chappar Road Section of Provincial Highway S-12 (17 Km)
Haripur
PKHA
30-11--1 30-11--1 - 30-11--1 - 1274.72 0 10 10 1.429 1.429 1.429 1264.72 1% 0%
August - 2020
LOA issued to contractor.
No Image
1730
(OG)
190341-Widening / Improvement / Rehabilitation of road from Beer to Kalangir on Haripur - Chappar Road Section of Provincial Highway S-12 (17 Km)
Haripur
PKHA
30-11--1 30-11--1 - 30-11--1 - 1274.72 0 10 0 1.429 0 0 1264.72 1% -
July - 2020
LOA issued to contractor.
No Image
1730
(OG)
190341-Widening / Improvement / Rehabilitation of road from Beer to Kalangir on Haripur - Chappar Road Section of Provincial Highway S-12 (17 Km)
Haripur
PKHA
30-11--1 30-11--1 - 30-11--1 - 1274.72 7.5 10 10 10 10 17.5 1257.22 1% 1%
May - 2021
work started on 1st scheme
No Image
1730
(OG)
190341-Widening / Improvement / Rehabilitation of road from Beer to Kalangir on Haripur - Chappar Road Section of Provincial Highway S-12 (17 Km)
Haripur
PKHA
30-11--1 30-11--1 - 30-11--1 - 1274.72 7.5 10 10 10 10 17.5 1257.22 1% 1%
April - 2021
work started on 1st scheme
No Image
1730
(OG)
190341-Widening / Improvement / Rehabilitation of road from Beer to Kalangir on Haripur - Chappar Road Section of Provincial Highway S-12 (17 Km)
Haripur
PKHA
30-11--1 30-11--1 - 30-11--1 - 1274.72 7.5 10 10 10 7.5 15 1257.22 1% 1%
March - 2021
work started on 1st scheme
No Image
1730
(OG)
190341-Widening / Improvement / Rehabilitation of road from Beer to Kalangir on Haripur - Chappar Road Section of Provincial Highway S-12 (17 Km)
Haripur
PKHA
30-11--1 30-11--1 - 30-11--1 - 1274.72 7.5 10 10 10 7.5 15 1257.22 1% 1%
February - 2021
work started on 1st scheme
No Image
1730
(OG)
190341-Widening / Improvement / Rehabilitation of road from Beer to Kalangir on Haripur - Chappar Road Section of Provincial Highway S-12 (17 Km)
Haripur
PKHA
30-11--1 30-11--1 - 30-11--1 - 1274.72 7.5 10 10 10 7.5 15 1257.22 1% 1%
January - 2021
work started on 1st scheme
No Image
Pages : 1