Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1732
(OG)
20675-F/S and Design of Projects of Various Roads.
Provincial
PKHA
30-11--1 30-11--1 - 30-11--1 - 630 263.496 25 25 25 15.25 278.746 341.504 46% 44%
December - 2020
Approved
No Image
1732
(OG)
20675-F/S and Design of Projects of Various Roads.
Provincial
PKHA
30-11--1 30-11--1 - 30-11--1 - 630 263.496 25 25 25 15.25 278.746 341.504 46% 44%
December - 2020
Approved
No Image
1732
(OG)
20675-F/S and Design of Projects of Various Roads.
Provincial
PKHA
30-11--1 30-11--1 - 30-11--1 - 821.658 263.496 25 25 15 6.5 269.996 533.162 35% 33%
October - 2020
Pc-II approved for Rs.3.750 for (Distt: Buner). Pc-II approved for Rs. 6.00 M for (Distt: Lakki). Pc-II approved for Rs.25.00 M for (Dir Motorway). (feasilbility study and design of 305 Km provincial roads.
No Image
1732
(OG)
20675-F/S and Design of Projects of Various Roads.
Provincial
PKHA
30-11--1 30-11--1 - 30-11--1 - 821.658 263.496 25 25 6.5 6.5 269.996 533.162 35% 33%
September - 2020
Pc-II approved for Rs.3.750 for (Distt: Buner). Pc-II approved for Rs. 6.00 M for (Distt: Lakki). Pc-II approved for Rs.25.00 M for (Dir Motorway). (feasilbility study and design of 305 Km provincial roads.
No Image
1732
(OG)
20675-F/S and Design of Projects of Various Roads.
Provincial
PKHA
30-11--1 30-11--1 - 30-11--1 - 821.658 263.496 25 25 6.25 6.25 269.746 533.162 35% 33%
August - 2020
feasilbility study and design of 305 Km provincial roads.
No Image
1732
(OG)
20675-F/S and Design of Projects of Various Roads.
Provincial
PKHA
30-11--1 30-11--1 - 30-11--1 - 821.658 263.496 25 0 6.25 0 263.496 533.162 35% 32%
July - 2020
Conusltancy services for feasilbility study and de
No Image
1732
(OG)
20675-F/S and Design of Projects of Various Roads.
Provincial
PKHA
30-11--1 30-11--1 - 30-11--1 - 630 278.496 25 25 25 25 303.496 326.504 48% 48%
May - 2021
PC-II for Rs.30 m approved on 16/03/2021. Work start
No Image
1732
(OG)
20675-F/S and Design of Projects of Various Roads.
Provincial
PKHA
30-11--1 30-11--1 - 30-11--1 - 630 278.496 25 25 25 25 303.496 326.504 48% 48%
April - 2021
PC-II for Rs.30 m approved on 16/03/2021. Work start
No Image
1732
(OG)
20675-F/S and Design of Projects of Various Roads.
Provincial
PKHA
30-11--1 30-11--1 - 30-11--1 - 630 278.496 25 25 25 15.25 293.746 326.504 48% 47%
March - 2021
PC-II for Rs.30 m approved on 16/03/2021. Work start
No Image
1732
(OG)
20675-F/S and Design of Projects of Various Roads.
Provincial
PKHA
30-11--1 30-11--1 - 30-11--1 - 630 278.496 25 25 25 15.25 293.746 326.504 48% 47%
February - 2021
work start
No Image
1732
(OG)
20675-F/S and Design of Projects of Various Roads.
Provincial
PKHA
30-11--1 30-11--1 - 30-11--1 - 630 278.496 25 25 25 15.25 293.746 326.504 48% 47%
January - 2021
work start
No Image