Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1735 (OG) |
140878-Improvement & Widening of Nizampur - Kohat road (64 Kms), District Nowshera & Kohat |
Provincial PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2796.766 | 1705.505 | 75 | 75 | 75 | 37.5 | 1743.005 | 1016.261 | 64% |
62% December - 2020 |
Pack-1 (7.3 Km) -
Bridge is completed with 03- Expansion joints.
Pack-II bridge is completed with expantion joints.
Package -IV Bridge is completed except 02 Nos expansion joints
Package-5 Bridge is completed except except 03 Nos expansion joints & approaches slabs. Sub base, WBM, WC of Pack-1,2&3 completed & remaining in progress. |
No Image |
Package-1 (Village Kayai to Nizampur Bazar) 7.3 KM
Package-2 (Nizampur Bazar to Village Piran) 11.05 KM
Package-3 (Village Piran to Toray Stanay) 8.46 KM
Package-4 (Toray Stanay to Zamir Gul Dam) 8.67 KM
Package-5 (Zamir Gul Dam to Jabbar) 10 KM
Package-6 (Jabbar to Kohat Pindi Road) 12.94 KM | |||||||||||||||||||
1735 (OG) |
140878-Improvement & Widening of Nizampur - Kohat road (64 Kms), District Nowshera & Kohat |
Provincial PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2796.766 | 1705.505 | 75 | 75 | 75 | 37.5 | 1743.005 | 1016.261 | 64% |
62% December - 2020 |
Pack-1 (7.3 Km) -
Bridge is completed with 03- Expansion joints.
Pack-II bridge is completed with expantion joints.
Package -IV Bridge is completed except 02 Nos expansion joints
Package-5 Bridge is completed except except 03 Nos expansion joints & approaches slabs. Sub base, WBM, WC of Pack-1,2&3 completed & remaining in progress. |
No Image |
Package-1 (Village Kayai to Nizampur Bazar) 7.3 KM
Package-2 (Nizampur Bazar to Village Piran) 11.05 KM
Package-3 (Village Piran to Toray Stanay) 8.46 KM
Package-4 (Toray Stanay to Zamir Gul Dam) 8.67 KM
Package-5 (Zamir Gul Dam to Jabbar) 10 KM
Package-6 (Jabbar to Kohat Pindi Road) 12.94 KM | |||||||||||||||||||
1735 (OG) |
140878-Improvement & Widening of Nizampur - Kohat road (64 Kms), District Nowshera & Kohat |
Provincial PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2796.766 | 1705.505 | 75 | 75 | 37.5 | 18.75 | 1724.255 | 1016.261 | 64% |
62% October - 2020 |
Pack-1 (7.3 Km) -
Bridge is completed with 03- Expansion joints.
Pack-II bridge is completed with expantion joints.
Package -IV Bridge is completed except 02 Nos expansion joints
Package-5 Bridge is completed except except 03 Nos expansion joints & approaches slabs. Sub base, WBM, WC of Pack-1,2&3 completed & remaining in progress. |
No Image |
1735 (OG) |
140878-Improvement & Widening of Nizampur - Kohat road (64 Kms), District Nowshera & Kohat |
Provincial PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2796.766 | 1705.505 | 75 | 75 | 18.75 | 18.75 | 1724.255 | 1016.261 | 64% |
62% September - 2020 |
Pack-1 (7.3 Km) -
Bridge is completed with 03- Expansion joints.
Pack-II bridge is completed with expantion joints.
Package -IV Bridge is completed except 02 Nos expansion joints
Package-5 Bridge is completed except except 03 Nos expansion joints & approaches slabs. Sub base, WBM, WC of Pack-1,2&3 completed & remaining in progress. |
No Image |
1735 (OG) |
140878-Improvement & Widening of Nizampur - Kohat road (64 Kms), District Nowshera & Kohat |
Provincial PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2796.766 | 1705.505 | 75 | 75 | 18.75 | 18.75 | 1724.255 | 1016.261 | 64% |
62% August - 2020 |
Pack-1 (7.3 Km) -
Bridge is completed with 03- Expansion joints.
Pack-II bridge is completed with expantion joints.
Package -IV Bridge is completed except 02 Nos expansion joints
Package-5 Bridge is completed except except 03 Nos expansion joints & approaches slabs. Sub base, WBM, WC of Pack-1,2&3 completed & remaining in progress. |
No Image |
1735 (OG) |
140878-Improvement & Widening of Nizampur - Kohat road (64 Kms), District Nowshera & Kohat |
Provincial PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2796.766 | 1705.505 | 75 | 0 | 18.75 | 0 | 1705.505 | 1016.261 | 64% |
61% July - 2020 |
Pack-1 (7.3 Km) - sub base, WBM, WC completed. Pac |
No Image |
1735 (OG) |
140878-Improvement & Widening of Nizampur - Kohat road (64 Kms), District Nowshera & Kohat |
Provincial PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2796.766 | 1705.505 | 75 | 75 | 75 | 75 | 1780.505 | 1016.261 | 64% |
64% May - 2021 |
Pack-1 (7.3 Km) -
Bridge is completed with 03- Expansion joints.
Pack-II bridge is completed with expantion joints.
Package -IV Bridge is completed except 02 Nos expansion joints
Package-5 Bridge is completed except except 03 Nos expansion joints & approaches slabs. Sub base, WBM, WC of Pack-1,2&3 completed & remaining in progress. |
No Image |
Package-1 (Village Kayai to Nizampur Bazar) 7.3 KM
Package-2 (Nizampur Bazar to Village Piran) 11.05 KM
Package-3 (Village Piran to Toray Stanay) 8.46 KM
Package-4 (Toray Stanay to Zamir Gul Dam) 8.67 KM
Package-5 (Zamir Gul Dam to Jabbar) 10 KM
Package-6 (Jabbar to Kohat Pindi Road) 12.94 KM | |||||||||||||||||||
1735 (OG) |
140878-Improvement & Widening of Nizampur - Kohat road (64 Kms), District Nowshera & Kohat |
Provincial PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2796.766 | 1705.505 | 75 | 75 | 75 | 75 | 1780.505 | 1016.261 | 64% |
64% April - 2021 |
Pack-1 (7.3 Km) -
Bridge is completed with 03- Expansion joints.
Pack-II bridge is completed with expantion joints.
Package -IV Bridge is completed except 02 Nos expansion joints
Package-5 Bridge is completed except except 03 Nos expansion joints & approaches slabs. Sub base, WBM, WC of Pack-1,2&3 completed & remaining in progress. |
No Image |
Package-1 (Village Kayai to Nizampur Bazar) 7.3 KM
Package-2 (Nizampur Bazar to Village Piran) 11.05 KM
Package-3 (Village Piran to Toray Stanay) 8.46 KM
Package-4 (Toray Stanay to Zamir Gul Dam) 8.67 KM
Package-5 (Zamir Gul Dam to Jabbar) 10 KM
Package-6 (Jabbar to Kohat Pindi Road) 12.94 KM | |||||||||||||||||||
1735 (OG) |
140878-Improvement & Widening of Nizampur - Kohat road (64 Kms), District Nowshera & Kohat |
Provincial PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2796.766 | 1705.505 | 75 | 75 | 75 | 37.5 | 1743.005 | 1016.261 | 64% |
62% March - 2021 |
Pack-1 (7.3 Km) -
Bridge is completed with 03- Expansion joints.
Pack-II bridge is completed with expantion joints.
Package -IV Bridge is completed except 02 Nos expansion joints
Package-5 Bridge is completed except except 03 Nos expansion joints & approaches slabs. Sub base, WBM, WC of Pack-1,2&3 completed & remaining in progress. |
No Image |
Package-1 (Village Kayai to Nizampur Bazar) 7.3 KM
Package-2 (Nizampur Bazar to Village Piran) 11.05 KM
Package-3 (Village Piran to Toray Stanay) 8.46 KM
Package-4 (Toray Stanay to Zamir Gul Dam) 8.67 KM
Package-5 (Zamir Gul Dam to Jabbar) 10 KM
Package-6 (Jabbar to Kohat Pindi Road) 12.94 KM | |||||||||||||||||||
1735 (OG) |
140878-Improvement & Widening of Nizampur - Kohat road (64 Kms), District Nowshera & Kohat |
Provincial PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2796.766 | 1705.505 | 75 | 75 | 75 | 37.5 | 1743.005 | 1016.261 | 64% |
62% February - 2021 |
Pack-1 (7.3 Km) -
Bridge is completed with 03- Expansion joints.
Pack-II bridge is completed with expantion joints.
Package -IV Bridge is completed except 02 Nos expansion joints
Package-5 Bridge is completed except except 03 Nos expansion joints & approaches slabs. Sub base, WBM, WC of Pack-1,2&3 completed & remaining in progress. |
No Image |
Package-1 (Village Kayai to Nizampur Bazar) 7.3 KM
Package-2 (Nizampur Bazar to Village Piran) 11.05 KM
Package-3 (Village Piran to Toray Stanay) 8.46 KM
Package-4 (Toray Stanay to Zamir Gul Dam) 8.67 KM
Package-5 (Zamir Gul Dam to Jabbar) 10 KM
Package-6 (Jabbar to Kohat Pindi Road) 12.94 KM | |||||||||||||||||||
1735 (OG) |
140878-Improvement & Widening of Nizampur - Kohat road (64 Kms), District Nowshera & Kohat |
Provincial PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2796.766 | 1705.505 | 75 | 75 | 75 | 37.5 | 1743.005 | 1016.261 | 64% |
62% January - 2021 |
Pack-1 (7.3 Km) -
Bridge is completed with 03- Expansion joints.
Pack-II bridge is completed with expantion joints.
Package -IV Bridge is completed except 02 Nos expansion joints
Package-5 Bridge is completed except except 03 Nos expansion joints & approaches slabs. Sub base, WBM, WC of Pack-1,2&3 completed & remaining in progress. |
No Image |
Package-1 (Village Kayai to Nizampur Bazar) 7.3 KM
Package-2 (Nizampur Bazar to Village Piran) 11.05 KM
Package-3 (Village Piran to Toray Stanay) 8.46 KM
Package-4 (Toray Stanay to Zamir Gul Dam) 8.67 KM
Package-5 (Zamir Gul Dam to Jabbar) 10 KM
Package-6 (Jabbar to Kohat Pindi Road) 12.94 KM | |||||||||||||||||||