Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2021, February - 2021, March - 2021, April - 2021, May - 2021, July - 2020, August - 2020, September - 2020, October - 2020, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1739
(OG)
190560-Construction of BT road from Balakot on Malam Jabba-Manglawar road to Shangla Top (6km)
Provincial
PKHA
30-11--1 30-11--1 - 30-11--1 - 898.98 50 50 50 50 0 50 798.98 11% 6%
December - 2020
Tender process has been completed
No Image
1739
(OG)
190560-Construction of BT road from Balakot on Malam Jabba-Manglawar road to Shangla Top (6km)
Provincial
PKHA
30-11--1 30-11--1 - 30-11--1 - 898.98 50 50 50 50 0 50 798.98 11% 6%
December - 2020
Tender process has been completed
No Image
1739
(OG)
190560-Construction of BT road from Balakot on Malam Jabba-Manglawar road to Shangla Top (6km)
Provincial
PKHA
30-11--1 30-11--1 - 30-11--1 - 898.98 50 50 50 25 8.333 58.333 798.98 11% 6%
October - 2020
Tender process has been completed
No Image
1739
(OG)
190560-Construction of BT road from Balakot on Malam Jabba-Manglawar road to Shangla Top (6km)
Provincial
PKHA
30-11--1 30-11--1 - 30-11--1 - 898.98 50 50 50 8.333 8.333 58.333 798.98 11% 6%
September - 2020
Tender process has been completed
No Image
1739
(OG)
190560-Construction of BT road from Balakot on Malam Jabba-Manglawar road to Shangla Top (6km)
Provincial
PKHA
30-11--1 30-11--1 - 30-11--1 - 898.98 50 50 50 8.333 8.333 58.333 798.98 11% 6%
August - 2020
Tender process has been completed
No Image
1739
(OG)
190560-Construction of BT road from Balakot on Malam Jabba-Manglawar road to Shangla Top (6km)
Provincial
PKHA
30-11--1 30-11--1 - 30-11--1 - 898.98 50 50 0 8.333 0 50 798.98 11% 6%
July - 2020
Work has been tendered.
No Image
1739
(OG)
190560-Construction of BT road from Balakot on Malam Jabba-Manglawar road to Shangla Top (6km)
Provincial
PKHA
30-11--1 30-11--1 - 30-11--1 - 898.98 50 50 0 0 0 50 798.98 11% 6%
May - 2021
work stopped
No Image
1739
(OG)
190560-Construction of BT road from Balakot on Malam Jabba-Manglawar road to Shangla Top (6km)
Provincial
PKHA
30-11--1 30-11--1 - 30-11--1 - 898.98 50 50 0 0 0 50 798.98 11% 6%
April - 2021
work stopped
No Image
1739
(OG)
190560-Construction of BT road from Balakot on Malam Jabba-Manglawar road to Shangla Top (6km)
Provincial
PKHA
30-11--1 30-11--1 - 30-11--1 - 898.98 50 50 50 50 0 50 798.98 11% 6%
March - 2021
work stopped
No Image
1739
(OG)
190560-Construction of BT road from Balakot on Malam Jabba-Manglawar road to Shangla Top (6km)
Provincial
PKHA
30-11--1 30-11--1 - 30-11--1 - 898.98 50 50 50 50 0 50 798.98 11% 6%
February - 2021
work stopped
No Image
1739
(OG)
190560-Construction of BT road from Balakot on Malam Jabba-Manglawar road to Shangla Top (6km)
Provincial
PKHA
30-11--1 30-11--1 - 30-11--1 - 898.98 50 50 50 50 0 50 798.98 11% 6%
January - 2021
work stopped
No Image
Pages : 1