Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1740 (New) |
190551-Construction of Dual Carriageway from Chamkani to Badaber, Peshawar. |
Peshawar PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 17000 | 0 | 70 | 70 | 70 | 35 | 35 | 0 |
December - 2020 |
PC-II AA issued on 18-08-2020. |
No Image | |
1740 (New) |
190551-Construction of Dual Carriageway from Chamkani to Badaber, Peshawar. |
Peshawar PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 17000 | 0 | 70 | 70 | 70 | 35 | 35 | 0 |
December - 2020 |
PC-II AA issued on 18-08-2020. |
No Image | |
1740 (New) |
190551-Construction of Dual Carriageway from Chamkani to Badaber, Peshawar. |
Peshawar PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 17000 | 0 | 70 | 70 | 35 | 2.5 | 2.5 | 0 | - |
- October - 2020 |
PC-II has been approved with the condition that the work would not be started till the finalization of alligment of DIK Motorway. |
No Image |
1740 (New) |
190551-Construction of Dual Carriageway from Chamkani to Badaber, Peshawar. |
Peshawar PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 17000 | 0 | 70 | 70 | 0 | 0 | 0 | 0 | - |
- September - 2020 |
PC-II has been approved with the condition that the work would not be started till the finalization of alligment of DIK Motorway. |
No Image |
1740 (New) |
190551-Construction of Dual Carriageway from Chamkani to Badaber, Peshawar. |
Peshawar PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 17000 | 0 | 70 | 70 | 0 | 0 | 0 | 0 |
- August - 2020 |
PC-II has been approved with the condition that the work would not be started till the finalization of alligment of DIK Motorway. |
No Image | |
1740 (New) |
190551-Construction of Dual Carriageway from Chamkani to Badaber, Peshawar. |
Peshawar PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 17000 | 0 | 70 | 0 | 0 | 0 | 0 | 0 | - |
- July - 2020 |
PC-II has been approved with the condition that the work would not be started till the finalization of alligment of DIK Motorway. |
No Image |
1740 (New) |
190551-Construction of Dual Carriageway from Chamkani to Badaber, Peshawar. |
Peshawar PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 17000 | 0 | 70 | 70 | 70 | 35 | 35 | 0 |
May - 2021 |
PC-II AA issued on 18-08-2020. |
No Image | |
1740 (New) |
190551-Construction of Dual Carriageway from Chamkani to Badaber, Peshawar. |
Peshawar PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 17000 | 0 | 70 | 70 | 70 | 35 | 35 | 0 |
April - 2021 |
PC-II AA issued on 18-08-2020. |
No Image | |
1740 (New) |
190551-Construction of Dual Carriageway from Chamkani to Badaber, Peshawar. |
Peshawar PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 17000 | 0 | 70 | 70 | 70 | 35 | 35 | 0 |
March - 2021 |
PC-II AA issued on 18-08-2020. |
No Image | |
1740 (New) |
190551-Construction of Dual Carriageway from Chamkani to Badaber, Peshawar. |
Peshawar PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 17000 | 0 | 70 | 70 | 70 | 35 | 35 | 0 |
February - 2021 |
PC-II AA issued on 18-08-2020. |
No Image | |
1740 (New) |
190551-Construction of Dual Carriageway from Chamkani to Badaber, Peshawar. |
Peshawar PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 17000 | 0 | 70 | 70 | 70 | 35 | 35 | 0 |
January - 2021 |
PC-II AA issued on 18-08-2020. |
No Image | |
Pages : 1 |