Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2021, February - 2021, March - 2021, April - 2021, May - 2021, July - 2020, August - 2020, September - 2020, October - 2020, December - 2020,

Showing Page Number : 1 of 3

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1754
(OG)
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG)
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 81.5 15.479798 1 1 1 1 16.479798 65.02 20% 20%
October - 2020
Earth work completed. Drain work in progress. Demand Rs. 30 M
No Image
1) Rehabilitation of Civil Station roads (16
1754
(OG)
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG)
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 81.5 0 1 1 1 1 1 80.5 1% 1%
September - 2020
Earth work completed. Drain work in progress. Demand Rs. 30 M
No Image
1) Rehabilitation of Civil Station roads (16
1754
(OG)
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG)
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 81.5 0 1 1 1 1 1 80.5 1% 1%
August - 2020
Earth work completed. Drain work in progress. Demand Rs. 30 M
No Image
1) Rehabilitation of Civil Station roads (16
1754
(OG)
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG)
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 81.5 0 0 0 0 0 0 81.5 - -
July - 2020
Earth work completed. Drain work in progress.
No Image
1) Rehabilitation of Civil Station roads (16
1754
(OG)
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG)
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 81.5 15.479798 13 13 13 13 28.479798 53.02 35% 35%
March - 2021
22 units Earth work completed. Drain work in progress. Demand Rs. 30 M
No Image
  1. Rehabilitation of Civil Station Roads (16-KM) (PK-39)
  2. Rehabilitation of PCC roads in U/C Kakul (5-KM) (PK-39)
  3. Abbottabad Thandiai Road / Bridge work (25-KM) (PK-39)
  4. Rehabilitation of Dhodial Road / Bridge (3-KM) (PK-39)
  5. Rehabilitation of Malkot link Road (6.5 KM) (PK-36) .?.?.?.. TS 16.948
  6. Rehabilitation of Qalandarabad to Tarnawai road (10-KM) (PK-38)
  7. Todo Maira Road (7-KM) (PK-38)
  8. Rehabilitation of Lodhi Abad to Bandi Dhundan road (5-KM) (PK-38)
  9. Baghdara road (3-KM) (PK-          )
  10. Rehabilitation of Kokal Barseen road (12-KM) (PK-37)
  11. Rehabilitation of Samaiser road (2-KM) (PK-39)
  12. Rehabilitation of Manna Karimabad road (3-KM) (PK-39)
  13. Rehabilitation of Loon Pattian road (2-KM) (PK-36)
  14. Rehabilitation of Takia Hall to Pind Gali Beer road via Khanda Khoo (30-KM) (PK-        )
  15. Rehabilitation of Forest Barrier to Shah Di Gali road (8-KM). (PK-38)
  16. Rehabilitation of Rajoya road (5-KM) (PK-37)
  17. Chanmari Tajwal road (5.50 KM)     (PK-37)
  18. Maira Roomal road (3-KM) (PK-       )
  19. Neloi Sandan road (1-KM) (PK-37)
  20. Toheedabad Passala road (4-KM)  (PK-37)
  21. Lora Swargali road (29-KM) (PK-36) .?.?.?.. TS 1.814
  22. Ratti Gali Lower Barrian road (3-KM) (PK-37)
 
1754
(OG)
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG)
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 81.5 15.479798 13 13 13 13 28.479798 53.02 35% 35%
February - 2021
22 units Earth work completed. Drain work in progress. Demand Rs. 30 M
No Image
  1. Rehabilitation of Civil Station Roads (16-KM) (PK-39)
  2. Rehabilitation of PCC roads in U/C Kakul (5-KM) (PK-39)
  3. Abbottabad Thandiai Road / Bridge work (25-KM) (PK-39)
  4. Rehabilitation of Dhodial Road / Bridge (3-KM) (PK-39)
  5. Rehabilitation of Malkot link Road (6.5 KM) (PK-36) .?.?.?.. TS 16.948
  6. Rehabilitation of Qalandarabad to Tarnawai road (10-KM) (PK-38)
  7. Todo Maira Road (7-KM) (PK-38)
  8. Rehabilitation of Lodhi Abad to Bandi Dhundan road (5-KM) (PK-38)
  9. Baghdara road (3-KM) (PK-          )
  10. Rehabilitation of Kokal Barseen road (12-KM) (PK-37)
  11. Rehabilitation of Samaiser road (2-KM) (PK-39)
  12. Rehabilitation of Manna Karimabad road (3-KM) (PK-39)
  13. Rehabilitation of Loon Pattian road (2-KM) (PK-36)
  14. Rehabilitation of Takia Hall to Pind Gali Beer road via Khanda Khoo (30-KM) (PK-        )
  15. Rehabilitation of Forest Barrier to Shah Di Gali road (8-KM). (PK-38)
  16. Rehabilitation of Rajoya road (5-KM) (PK-37)
  17. Chanmari Tajwal road (5.50 KM)     (PK-37)
  18. Maira Roomal road (3-KM) (PK-       )
  19. Neloi Sandan road (1-KM) (PK-37)
  20. Toheedabad Passala road (4-KM)  (PK-37)
  21. Lora Swargali road (29-KM) (PK-36) .?.?.?.. TS 1.814
  22. Ratti Gali Lower Barrian road (3-KM) (PK-37)
 
1754
(OG)
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG)
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 81.5 15.479798 13 13 13 13 28.479798 53.02 35% 35%
January - 2021
22 units Earth work completed. Drain work in progress. Demand Rs. 30 M
No Image
1) Rehabilitation of Civil Station roads (16
1754
(OG)
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG)
Abbottabad
HW
30-11--1 30-11--1 - 30-11--1 - 81.5 15.479798 13 13 13 13 28.479798 53.02 35% 35%
May - 2021
22 units Earth work completed. Drain work in progress. Demand Rs. 10 M
No Image
  1. Rehabilitation of Civil Station Roads (16-KM) (PK-39)
  2. Rehabilitation of PCC roads in U/C Kakul (5-KM) (PK-39)
  3. Abbottabad Thandiai Road / Bridge work (25-KM) (PK-39)
  4. Rehabilitation of Dhodial Road / Bridge (3-KM) (PK-39)
  5. Rehabilitation of Malkot link Road (6.5 KM) (PK-36) .?.?.?.. TS 16.948
  6. Rehabilitation of Qalandarabad to Tarnawai road (10-KM) (PK-38)
  7. Todo Maira Road (7-KM) (PK-38)
  8. Rehabilitation of Lodhi Abad to Bandi Dhundan road (5-KM) (PK-38)
  9. Baghdara road (3-KM) (PK-          )
  10. Rehabilitation of Kokal Barseen road (12-KM) (PK-37)
  11. Rehabilitation of Samaiser road (2-KM) (PK-39)
  12. Rehabilitation of Manna Karimabad road (3-KM) (PK-39)
  13. Rehabilitation of Loon Pattian road (2-KM) (PK-36)
  14. Rehabilitation of Takia Hall to Pind Gali Beer road via Khanda Khoo (30-KM) (PK-        )
  15. Rehabilitation of Forest Barrier to Shah Di Gali road (8-KM). (PK-38)
  16. Rehabilitation of Rajoya road (5-KM) (PK-37)
  17. Chanmari Tajwal road (5.50 KM)     (PK-37)
  18. Maira Roomal road (3-KM) (PK-       )
  19. Neloi Sandan road (1-KM) (PK-37)
  20. Toheedabad Passala road (4-KM)  (PK-37)
  21. Lora Swargali road (29-KM) (PK-36) .?.?.?.. TS 1.814
  22. Ratti Gali Lower Barrian road (3-KM) (PK-37)
 
1754
(OG)
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG)
Abbottabad
HW
30-11--1 30-11--1 - 30-11--1 - 81.5 15.479798 13 13 13 13 28.479798 53.02 35% 35%
April - 2021
22 units Earth work completed. Drain work in progress. Demand Rs. 10 M
No Image
  1. Rehabilitation of Civil Station Roads (16-KM) (PK-39)
  2. Rehabilitation of PCC roads in U/C Kakul (5-KM) (PK-39)
  3. Abbottabad Thandiai Road / Bridge work (25-KM) (PK-39)
  4. Rehabilitation of Dhodial Road / Bridge (3-KM) (PK-39)
  5. Rehabilitation of Malkot link Road (6.5 KM) (PK-36) .?.?.?.. TS 16.948
  6. Rehabilitation of Qalandarabad to Tarnawai road (10-KM) (PK-38)
  7. Todo Maira Road (7-KM) (PK-38)
  8. Rehabilitation of Lodhi Abad to Bandi Dhundan road (5-KM) (PK-38)
  9. Baghdara road (3-KM) (PK-          )
  10. Rehabilitation of Kokal Barseen road (12-KM) (PK-37)
  11. Rehabilitation of Samaiser road (2-KM) (PK-39)
  12. Rehabilitation of Manna Karimabad road (3-KM) (PK-39)
  13. Rehabilitation of Loon Pattian road (2-KM) (PK-36)
  14. Rehabilitation of Takia Hall to Pind Gali Beer road via Khanda Khoo (30-KM) (PK-        )
  15. Rehabilitation of Forest Barrier to Shah Di Gali road (8-KM). (PK-38)
  16. Rehabilitation of Rajoya road (5-KM) (PK-37)
  17. Chanmari Tajwal road (5.50 KM)     (PK-37)
  18. Maira Roomal road (3-KM) (PK-       )
  19. Neloi Sandan road (1-KM) (PK-37)
  20. Toheedabad Passala road (4-KM)  (PK-37)
  21. Lora Swargali road (29-KM) (PK-36) .?.?.?.. TS 1.814
  22. Ratti Gali Lower Barrian road (3-KM) (PK-37)
 
1754
(OG)
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG)
Battagram
30-11--1 30-11--1 - 30-11--1 - 50 0 1.5 1.5 1.5 1.5 1.5 48.5 3% 3%
October - 2020
Work in progress (3 units). Demand Rs. 30 M
No Image
1) Sujbiar Kandow road (9 Km)
2
1754
(OG)
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG)
Battagram
30-11--1 30-11--1 - 30-11--1 - 50 0 1.5 1.5 1.5 0 0 48.5 3% -
September - 2020
Work in progress (3 units). Demand Rs. 30 M
No Image
1) Sujbiar Kandow road (9 Km)
2
1754
(OG)
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG)
Battagram
30-11--1 30-11--1 - 30-11--1 - 50 0 1.5 1.5 1.5 0 0 48.5 3% -
August - 2020
Work in progress (3 units). Demand Rs. 30 M
No Image
1) Sujbiar Kandow road (9 Km)
2
1754
(OG)
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG)
Battagram
30-11--1 30-11--1 - 30-11--1 - 50 0 0 0 0 0 0 50 - -
July - 2020
Work in progress (3 units).
No Image
1) Sujbiar Kandow road (9 Km)
2
1754
(OG)
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG)
Battagram
30-11--1 30-11--1 - 30-11--1 - 50 16.8 3 3 3 2.5 19.3 30.2 40% 39%
May - 2021
Work in progress 1 65% work completed 2 65% work completed 3 50% work completed Demand Rs. 10 M
No Image
1 Sujbiar Kandow road (9 Km)
2 Battagram Shamlai Hill Road (17 KM)
3 Kuzabanda Chattarplain Road (25 KM)
1754
(OG)
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG)
Battagram
30-11--1 30-11--1 - 30-11--1 - 50 16.8 3 3 3 2.5 19.3 30.2 40% 39%
April - 2021
Work in progress 1 65% work completed 2 65% work completed 3 50% work completed Demand Rs. 10 M
No Image
1 Sujbiar Kandow road (9 Km)
2 Battagram Shamlai Hill Road (17 KM)
3 Kuzabanda Chattarplain Road (25 KM)
1754
(OG)
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG)
Battagram
30-11--1 30-11--1 - 30-11--1 - 50 16.8 3 3 3 2.5 19.3 30.2 40% 39%
March - 2021
Work in progress 1 65% work completed 2 65% work completed 3 50% work completed
No Image
1 Sujbiar Kandow road (9 Km)
2 Battagram Shamlai Hill Road (17 KM)
3 Kuzabanda Chattarplain Road (25 KM)
1754
(OG)
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG)
Battagram
30-11--1 30-11--1 - 30-11--1 - 50 16.8 3 3 3 2.5 19.3 30.2 40% 39%
February - 2021
Work in progress 1 65% work completed 2 65% work completed 3 50% work completed
No Image
1 Sujbiar Kandow road (9 Km)
2 Battagram Shamlai Hill Road (17 KM)
3 Kuzabanda Chattarplain Road (25 KM)
1754
(OG)
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG)
Battagram
30-11--1 30-11--1 - 30-11--1 - 50 0 3 3 3 1 1 47 6% 2%
January - 2021
Work in progress (3 units). Demand Rs. 30 M
No Image
1) Sujbiar Kandow road (9 Km)
2
1754
(OG)
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG)
Chitral Upper
30-11--1 30-11--1 - 30-11--1 - 65.51 32.588 1 1 1 1 33.588 31.922 51% 51%
October - 2020
RCC bridge: 8/12 girders launched, Rs 15.00 million is required to keep continue tempo of work.
No Image
Construction of RCC Bridge at Kosht (55 m), U
1754
(OG)
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG)
Chitral Upper
30-11--1 30-11--1 - 30-11--1 - 65.51 32.588 1 1 1 1 33.588 31.922 51% 51%
September - 2020
RCC bridge: 8/12 girders launched, Rs 15.00 million is required to keep continue tempo of work.
No Image
Construction of RCC Bridge at Kosht (55 m), U
1754
(OG)
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG)
Chitral Upper
30-11--1 30-11--1 - 30-11--1 - 65.51 32.588 1 1 1 0 32.588 31.922 51% 50%
August - 2020
RCC bridge: 24/24 piles, 2/3 pile cap, 2/3 pier sh.. Work in progress, Rs 15.00 million is required to keep continue tempo of work.
No Image
Construction of RCC Bridge at Kosht (55 m), U
1754
(OG)
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG)
Chitral Upper
30-11--1 30-11--1 - 30-11--1 - 65.51 0 0 0 0 0 0 65.51 - -
July - 2020
RCC bridge: 24/24 piles, 2/3 pile cap, 2/3 pier sh
No Image
Construction of RCC Bridge at Kosht (55 m), U
1754
(OG)
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG)
Chitral Upper
30-11--1 30-11--1 - 30-11--1 - 65.51 32.588 3 3 3 1 33.588 29.922 54% 51%
May - 2021
RCC bridge: 8/12 girders launched, Rs 15.00 million is required to keep continue tempo of work.
No Image
Construction of RCC Bridge at Kosht (55 m),
1754
(OG)
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG)
Chitral Upper
30-11--1 30-11--1 - 30-11--1 - 65.51 32.588 3 3 3 1 33.588 29.922 54% 51%
April - 2021
RCC bridge: 8/12 girders launched, Rs 15.00 million is required to keep continue tempo of work.
No Image
Construction of RCC Bridge at Kosht (55 m),
1754
(OG)
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG)
Chitral Upper
30-11--1 30-11--1 - 30-11--1 - 65.51 32.588 3 3 3 1 33.588 29.922 54% 51%
March - 2021
RCC bridge: 8/12 girders launched, Rs 15.00 million is required to keep continue tempo of work.
No Image
Construction of RCC Bridge at Kosht (55 m),
1754
(OG)
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG)
Chitral Upper
30-11--1 30-11--1 - 30-11--1 - 65.51 32.588 3 3 3 1 33.588 29.922 54% 51%
February - 2021
RCC bridge: 8/12 girders launched, Rs 15.00 million is required to keep continue tempo of work.
No Image
Construction of RCC Bridge at Kosht (55 m),
1754
(OG)
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG)
Chitral Upper
30-11--1 30-11--1 - 30-11--1 - 65.51 32.588 3 3 3 1 33.588 29.922 54% 51%
January - 2021
RCC bridge: 8/12 girders launched, Rs 15.00 million is required to keep continue tempo of work.
No Image
Construction of RCC Bridge at Kosht (55 m), U
1754
(OG)
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG)
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 114.161 0 1 1 1 1 1 113.161 1% 1%
October - 2020
Test file in progress. Demand Rs. 50 M
No Image
1) Restoration/reconstruction of Shalfalam Br
1754
(OG)
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG)
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 114.161 0 1 1 1 0 0 113.161 1% -
September - 2020
Test file in progress. Demand Rs. 50 M
No Image
1) Restoration/reconstruction of Shalfalam Br
1754
(OG)
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG)
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 114.161 0 1 1 1 0 0 113.161 1% -
August - 2020
Test file in progress. Demand Rs. 50 M
No Image
1) Restoration/reconstruction of Shalfalam Br
1754
(OG)
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG)
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 114.161 0 0 0 0 0 0 114.161 - -
July - 2020
Test file in progress. Demand Rs. 50 M
No Image
1) Restoration/reconstruction of Shalfalam Br
1754
(OG)
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG)
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 114.161 8.928 4 4 4 4 12.928 101.233 11% 11%
March - 2021
Test file in progress. Demand Rs. 50 M
No Image
1) Restoration/reconstruction of Shalfalam Bridge on River Panjokora Dir Lower
2 Spectra Engineerig Consultant
3 Khall Kozkalay Road
1754
(OG)
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG)
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 114.161 8.928 4 4 4 4 12.928 101.233 11% 11%
February - 2021
Test file in progress. Demand Rs. 50 M
No Image
1) Restoration/reconstruction of Shalfalam Bridge on River Panjokora Dir Lower
2 Spectra Engineerig Consultant
3 Khall Kozkalay Road
1754
(OG)
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG)
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 114.161 0 4 4 4 4 4 110.161 4% 4%
January - 2021
Test file in progress. Demand Rs. 50 M
No Image
1) Restoration/reconstruction of Shalfalam Bridge on River Panjokora Dir Lower
2 Spectra Engineerig Consultant
3 Khall Kozkalay Road
1754
(OG)
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG)
Dir Lower
HW
30-11--1 30-11--1 - 30-11--1 - 114.161 8.928 4 4 4 4 12.928 101.233 11% 11%
May - 2021
02 Units all in progress Test file in progress. Demand Rs. 50 M
No Image
1) Restoration/reconstruction of Shalfalam Bridge on River Panjokora Dir Lower
2) Khall Kozkalay Road
1754
(OG)
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG)
Dir Lower
HW
30-11--1 30-11--1 - 30-11--1 - 114.161 8.928 4 4 4 4 12.928 101.233 11% 11%
April - 2021
02 Units all in progress Test file in progress. Demand Rs. 50 M
No Image
1) Restoration/reconstruction of Shalfalam Bridge on River Panjokora Dir Lower
2) Khall Kozkalay Road
1754
(OG)
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG)
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 80.103 0 1 1 1 1 1 79.103 1% 1%
October - 2020
3 units - all in progress. Demand Rs. 20 M
No Image
1) Khall Kozkaly road PK-93
2)
1754
(OG)
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG)
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 80.103 0 1 1 1 1 1 79.103 1% 1%
September - 2020
3 units - all in progress. Demand Rs. 20 M
No Image
1) Khall Kozkaly road PK-93
2)
1754
(OG)
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG)
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 80.103 0 1 1 1 0 0 79.103 1% -
August - 2020
3 units - all in progress. Demand Rs. 20 M
No Image
1) Khall Kozkaly road PK-93
2)
1754
(OG)
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG)
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 80.103 0 0 0 0 0 0 80.103 - -
July - 2020
3 units - all in progress. Demand Rs. 60 M
No Image
1) Khall Kozkaly road PK-93
2)
1754
(OG)
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG)
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 80.103 0 2 2 2 2 2 78.103 2% 2%
May - 2021
3 units - all in progress. Demand Rs. 20 M
No Image
1) Khall Kozkaly road PK-93
2)
1754
(OG)
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG)
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 80.103 0 2 2 2 2 2 78.103 2% 2%
April - 2021
3 units - all in progress. Demand Rs. 20 M
No Image
1) Khall Kozkaly road PK-93
2)
1754
(OG)
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG)
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 80.103 0 2 2 2 2 2 78.103 2% 2%
March - 2021
3 units - all in progress. Demand Rs. 20 M
No Image
1) Khall Kozkaly road PK-93
2)
1754
(OG)
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG)
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 80.103 0 2 2 2 2 2 78.103 2% 2%
February - 2021
3 units - all in progress. Demand Rs. 20 M
No Image
1) Khall Kozkaly road PK-93
2)
1754
(OG)
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG)
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 80.103 0 2 2 2 2 2 78.103 2% 2%
January - 2021
3 units - all in progress. Demand Rs. 20 M
No Image
1) Khall Kozkaly road PK-93
2)
1754
(OG)
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG)
Hangu
30-11--1 30-11--1 - 30-11--1 - 45 0 0 0 0 0 0 45 - -
October - 2020
Work order issued. Over-lapping with other ADP scehme. Revised DCE submitted for Rs. 835.357 M to SOR.
No Image
1) Construction & Rehabilitation of concr
1754
(OG)
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG)
Hangu
30-11--1 30-11--1 - 30-11--1 - 45 0 0 0 0 0 0 45 - -
September - 2020
Work order issued. Over-lapping with other ADP scehme. Revised DCE submitted for Rs. 835.357 M to SOR
No Image
1) Construction & Rehabilitation of concr
1754
(OG)
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG)
Hangu
30-11--1 30-11--1 - 30-11--1 - 45 0 0 0 0 0 0 45 - -
August - 2020
Work order issued. Over-lapping with other ADP scehme. Revised DCE submitted for Rs. 835.357 M to SOR
No Image
1) Construction & Rehabilitation of concr
1754
(OG)
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG)
Hangu
30-11--1 30-11--1 - 30-11--1 - 45 0 0 0 0 0 0 45 - -
July - 2020
Work order issued. Over-lapping with 1229 scope.
No Image
1) Construction & Rehabilitation of concr
1754
(OG)
160498-Provision for Rehabilitaiton of flood/torrential Affected Roads & Bridges. (SDG)
Hangu
30-11--1 30-11--1 - 30-11--1 - 45 30 0 0 0 0 30 15 - 67%
May - 2021
Work order issued. Over-lapping with other ADP scehme. Revised DCE submitted for Rs. 835.357 M to SOR.
No Image
1. Construction & Rehabilitation of concrete Road at Dallan Main Noor Khel Road...
2. Rehab: of Dallan Mazreen Road
3. Rehab; of Dallan Lahori Banda Road..
Pages : 1 2 3