Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2021, February - 2021, March - 2021, April - 2021, May - 2021, July - 2020, August - 2020, September - 2020, October - 2020, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1768
(OG)
200127-Construction of 05Kms BTR Ramzan Abad Ustrana Darazanda Sub Division
D.I.Khan
HW
30-11--1 30-11--1 - 30-11--1 - 123.388 7.471 20.14 20.14 20.14 20.14 27.611 95.777 22% 22%
May - 2021
Length 5 km - E.W and Structure Work in progeress
No Image
1768
(OG)
200127-Construction of 05Kms BTR Ramzan Abad Ustrana Darazanda Sub Division
D.I.Khan
HW
30-11--1 30-11--1 - 30-11--1 - 123.388 7.471 20.14 20.14 20.14 20.14 27.611 95.777 22% 22%
April - 2021
Length 5 km - E.W and Structure Work in progeress
No Image
1768
(OG)
200127-Construction of 05Kms BTR Ramzan Abad Ustrana Darazanda Sub Division
FR DI Khan
30-11--1 30-11--1 - 30-11--1 - 123.388 7.471 20.14 9.727 9.727 9.727 17.198 95.777 22% 14%
December - 2020
Work in progress.
No Image
1768
(OG)
200127-Construction of 05Kms BTR Ramzan Abad Ustrana Darazanda Sub Division
FR DI Khan
30-11--1 30-11--1 - 30-11--1 - 123.388 7.471 20.14 9.727 9.727 9.727 17.198 95.777 22% 14%
December - 2020
Work in progress.
No Image
1768
(OG)
200127-Construction of 05Kms BTR Ramzan Abad Ustrana Darazanda Sub Division
FR DI Khan
30-11--1 30-11--1 - 30-11--1 - 123.388 7.471 20.14 20.14 5 5 12.471 95.777 22% 10%
October - 2020
Work in progress.
No Image
1768
(OG)
200127-Construction of 05Kms BTR Ramzan Abad Ustrana Darazanda Sub Division
FR DI Khan
30-11--1 30-11--1 - 30-11--1 - 123.388 7.471 20.14 20.14 5 4.19 11.661 95.777 22% 9%
September - 2020
Work in progress.
No Image
1768
(OG)
200127-Construction of 05Kms BTR Ramzan Abad Ustrana Darazanda Sub Division
FR DI Khan
30-11--1 30-11--1 - 30-11--1 - 123.388 7.471 20.14 20.14 0 0 7.471 95.777 22% 6%
August - 2020
Work in progress.
No Image
1768
(OG)
200127-Construction of 05Kms BTR Ramzan Abad Ustrana Darazanda Sub Division
FR DI Khan
30-11--1 30-11--1 - 30-11--1 - 123.388 0 20.14 0 0 0 0 0 -
July - 2020
No Image
1768
(OG)
200127-Construction of 05Kms BTR Ramzan Abad Ustrana Darazanda Sub Division
FR DI Khan
30-11--1 30-11--1 - 30-11--1 - 123.388 7.471 20.14 20.14 20.14 20.14 27.611 95.777 22% 22%
March - 2021
Work in progress.
No Image
1768
(OG)
200127-Construction of 05Kms BTR Ramzan Abad Ustrana Darazanda Sub Division
FR DI Khan
30-11--1 30-11--1 - 30-11--1 - 123.388 7.471 20.14 20.14 20.14 20.14 27.611 95.777 22% 22%
February - 2021
Work in progress.
No Image
1768
(OG)
200127-Construction of 05Kms BTR Ramzan Abad Ustrana Darazanda Sub Division
FR DI Khan
30-11--1 30-11--1 - 30-11--1 - 123.388 7.471 20.14 9.727 9.727 9.727 17.198 95.777 22% 14%
January - 2021
Work in progress.
No Image