Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1772 (OG) |
191731-140030-Construction of BT Road from Siplatoi to Nano via Aghbarghai Phase II (10 Kms) in SWA. (Umbrella) [MA] |
South Waziristan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100.022 | 69.859 | 34.672 | 34.672 | 17.336 | 2.917 | 72.776 | 0 | 100% |
73% December - 2020 |
Length = 10 Km
E/W, S/B,B/C & Structure work in progress.
Cannot be complted due to revision |
No Image |
1772 (OG) |
191731-140030-Construction of BT Road from Siplatoi to Nano via Aghbarghai Phase II (10 Kms) in SWA. (Umbrella) [MA] |
South Waziristan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100.022 | 69.859 | 34.672 | 34.672 | 17.336 | 2.917 | 72.776 | 0 | 100% |
73% December - 2020 |
Length = 10 Km
E/W, S/B,B/C & Structure work in progress.
Cannot be complted due to revision |
No Image |
1772 (OG) |
191731-140030-Construction of BT Road from Siplatoi to Nano via Aghbarghai Phase II (10 Kms) in SWA. (Umbrella) [MA] |
South Waziristan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100.022 | 69.859 | 34.672 | 34.672 | 17.336 | 2.917 | 72.776 | 0 | 100% |
73% October - 2020 |
Length = 10 Km
E/W, S/B,B/C & Structure work in progress.
Completion : June-2021. |
No Image |
1772 (OG) |
191731-140030-Construction of BT Road from Siplatoi to Nano via Aghbarghai Phase II (10 Kms) in SWA. (Umbrella) [MA] |
South Waziristan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100.022 | 69.859 | 34.672 | 34.672 | 17.336 | 2.917 | 72.776 | 0 | 100% |
73% September - 2020 |
Length = 10 Km
E/W, S/B,B/C & Structure work in progress.
Completion : June-2021. |
No Image |
1772 (OG) |
191731-140030-Construction of BT Road from Siplatoi to Nano via Aghbarghai Phase II (10 Kms) in SWA. (Umbrella) [MA] |
South Waziristan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100.022 | 69.859 | 34.672 | 34.672 | 17.336 | 2.9 | 72.759 | 0 | 100% |
73% August - 2020 |
Length = 10 Km
E/W, S/B,B/C & Structure work in progress.
Completion : June-2021. |
No Image |
1772 (OG) |
191731-140030-Construction of BT Road from Siplatoi to Nano via Aghbarghai Phase II (10 Kms) in SWA. (Umbrella) [MA] |
South Waziristan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100.022 | 69.859 | 34.672 | 31.754 | 31.754 | 2.917 | 72.776 | 0 | 100% |
73% May - 2021 |
Length = 10 Km
E/W, S/B,B/C & Structure work in progress.
Cannot be complted due to revision |
No Image |
1772 (OG) |
191731-140030-Construction of BT Road from Siplatoi to Nano via Aghbarghai Phase II (10 Kms) in SWA. (Umbrella) [MA] |
South Waziristan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100.022 | 69.859 | 34.672 | 17.336 | 17.336 | 2.917 | 72.776 | 0 | 100% |
73% April - 2021 |
Length = 10 Km
E/W, S/B,B/C & Structure work in progress.
Cannot be complted due to revision |
No Image |
1772 (OG) |
191731-140030-Construction of BT Road from Siplatoi to Nano via Aghbarghai Phase II (10 Kms) in SWA. (Umbrella) [MA] |
South Waziristan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100.022 | 69.859 | 34.672 | 17.336 | 17.336 | 2.917 | 72.776 | 0 | 100% |
73% March - 2021 |
Length = 10 Km
E/W, S/B,B/C & Structure work in progress.
Cannot be complted due to revision |
No Image |
1772 (OG) |
191731-140030-Construction of BT Road from Siplatoi to Nano via Aghbarghai Phase II (10 Kms) in SWA. (Umbrella) [MA] |
South Waziristan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100.022 | 69.859 | 34.672 | 17.336 | 17.336 | 2.917 | 72.776 | 0 | 100% |
73% February - 2021 |
Length = 10 Km
E/W, S/B,B/C & Structure work in progress.
Cannot be complted due to revision |
No Image |
1772 (OG) |
191731-140030-Construction of BT Road from Siplatoi to Nano via Aghbarghai Phase II (10 Kms) in SWA. (Umbrella) [MA] |
South Waziristan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100.022 | 69.859 | 34.672 | 17.336 | 17.336 | 2.917 | 72.776 | 0 | 100% |
73% January - 2021 |
Length = 10 Km
E/W, S/B,B/C & Structure work in progress.
Cannot be complted due to revision |
No Image |
1772 (OG) |
191731-140030-Construction of BT Road from Siplatoi to Nano via Aghbarghai Phase II (10 Kms) in SWA. (Umbrella) [MA] |
South Wazirstan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 104.531 | 69.859 | 34.672 | 0 | 0 | 0 | 69.859 | 0 |
July - 2020 |
No Image | ||