Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2021, February - 2021, March - 2021, April - 2021, May - 2021, July - 2020, August - 2020, September - 2020, October - 2020, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1775
(OG)
191739-140337-Construction of BT Road from Shahoor to Toormandi Phase II (6 Kms) in SWA. (Umbrella) [MA]
South Waziristan
HW
30-11--1 30-11--1 - 30-11--1 - 104.089 87.457 8.27 8.27 8.27 2.483 89.94 8.362 92% 86%
December - 2020
Length = 06-Km E/W, S/B,B/C & Structure work in progress. Completion : June-2021.
No Image
1775
(OG)
191739-140337-Construction of BT Road from Shahoor to Toormandi Phase II (6 Kms) in SWA. (Umbrella) [MA]
South Waziristan
HW
30-11--1 30-11--1 - 30-11--1 - 104.089 87.457 8.27 8.27 8.27 2.483 89.94 8.362 92% 86%
December - 2020
Length = 06-Km E/W, S/B,B/C & Structure work in progress. Completion : June-2021.
No Image
1775
(OG)
191739-140337-Construction of BT Road from Shahoor to Toormandi Phase II (6 Kms) in SWA. (Umbrella) [MA]
South Waziristan
HW
30-11--1 30-11--1 - 30-11--1 - 104.089 87.457 8.27 8.27 8.27 2.483 89.94 8.362 92% 86%
October - 2020
Length = 06-Km E/W, S/B,B/C & Structure work in progress. Completion : June-2021.
No Image
1775
(OG)
191739-140337-Construction of BT Road from Shahoor to Toormandi Phase II (6 Kms) in SWA. (Umbrella) [MA]
South Waziristan
HW
30-11--1 30-11--1 - 30-11--1 - 104.089 87.457 8.27 8.27 8.27 0.464 87.921 8.362 92% 84%
September - 2020
Length = 06-Km E/W, S/B,B/C & Structure work in progress. Completion : June-2021.
No Image
1775
(OG)
191739-140337-Construction of BT Road from Shahoor to Toormandi Phase II (6 Kms) in SWA. (Umbrella) [MA]
South Waziristan
HW
30-11--1 30-11--1 - 30-11--1 - 104.089 87.457 8.27 8.27 8.27 0.5 87.957 8.362 92% 85%
August - 2020
Length = 06-Km E/W, S/B,B/C & Structure work in progress. Completion : June-2021.
No Image
1775
(OG)
191739-140337-Construction of BT Road from Shahoor to Toormandi Phase II (6 Kms) in SWA. (Umbrella) [MA]
South Waziristan
HW
30-11--1 30-11--1 - 30-11--1 - 104.089 87.457 8.27 2.439 2.439 2.483 89.94 8.362 92% 86%
May - 2021
Length = 06-Km E/W, S/B,B/C & Structure work in progress. Completion : June-2021.
No Image
1775
(OG)
191739-140337-Construction of BT Road from Shahoor to Toormandi Phase II (6 Kms) in SWA. (Umbrella) [MA]
South Waziristan
HW
30-11--1 30-11--1 - 30-11--1 - 104.089 87.457 8.27 8.27 8.27 2.483 89.94 8.362 92% 86%
April - 2021
Length = 06-Km E/W, S/B,B/C & Structure work in progress. Completion : June-2021.
No Image
1775
(OG)
191739-140337-Construction of BT Road from Shahoor to Toormandi Phase II (6 Kms) in SWA. (Umbrella) [MA]
South Waziristan
HW
30-11--1 30-11--1 - 30-11--1 - 104.089 87.457 8.27 8.27 8.27 2.483 89.94 8.362 92% 86%
March - 2021
Length = 06-Km E/W, S/B,B/C & Structure work in progress. Completion : June-2021.
No Image
1775
(OG)
191739-140337-Construction of BT Road from Shahoor to Toormandi Phase II (6 Kms) in SWA. (Umbrella) [MA]
South Waziristan
HW
30-11--1 30-11--1 - 30-11--1 - 104.089 87.457 8.27 8.27 8.27 2.483 89.94 8.362 92% 86%
February - 2021
Length = 06-Km E/W, S/B,B/C & Structure work in progress. Completion : June-2021.
No Image
1775
(OG)
191739-140337-Construction of BT Road from Shahoor to Toormandi Phase II (6 Kms) in SWA. (Umbrella) [MA]
South Waziristan
HW
30-11--1 30-11--1 - 30-11--1 - 104.089 87.457 8.27 8.27 8.27 2.483 89.94 8.362 92% 86%
January - 2021
Length = 06-Km E/W, S/B,B/C & Structure work in progress. Completion : June-2021.
No Image
1775
(OG)
191739-140337-Construction of BT Road from Shahoor to Toormandi Phase II (6 Kms) in SWA. (Umbrella) [MA]
South Wazirstan
30-11--1 30-11--1 - 30-11--1 - 112.358 104.088 8.27 0 0 0 104.088 0
July - 2020
No Image
Pages : 1