Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2021, February - 2021, March - 2021, April - 2021, May - 2021, July - 2020, August - 2020, September - 2020, October - 2020, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1785
(OG)
191765-170303-Construction of BT Roads in Sarwakai Sub Division, SWA. [MA]
South Waziristan
HW
30-11--1 30-11--1 - 30-11--1 - 351.326 76.499 129.424 129.424 45.376 38.993 115.492 145.403 59% 33%
December - 2020
E/Work,S/B, B/C & Structure work in progress.
No Image
1785
(OG)
191765-170303-Construction of BT Roads in Sarwakai Sub Division, SWA. [MA]
South Waziristan
HW
30-11--1 30-11--1 - 30-11--1 - 351.326 76.499 129.424 129.424 45.376 38.993 115.492 145.403 59% 33%
December - 2020
E/Work,S/B, B/C & Structure work in progress.
No Image
1785
(OG)
191765-170303-Construction of BT Roads in Sarwakai Sub Division, SWA. [MA]
South Waziristan
HW
30-11--1 30-11--1 - 30-11--1 - 351.326 76.499 129.424 129.424 45.376 27.48 103.979 145.403 59% 30%
October - 2020
E/Work,S/B, B/C & Structure work in progress.
No Image
1785
(OG)
191765-170303-Construction of BT Roads in Sarwakai Sub Division, SWA. [MA]
South Waziristan
HW
30-11--1 30-11--1 - 30-11--1 - 351.326 76.499 129.424 129.424 15 15 91.499 145.403 59% 26%
September - 2020
E/Work,S/B, B/C & Structure work in progress.
No Image
1785
(OG)
191765-170303-Construction of BT Roads in Sarwakai Sub Division, SWA. [MA]
South Waziristan
HW
30-11--1 30-11--1 - 30-11--1 - 351.326 76.499 129.424 129.424 15 8 84.499 145.403 59% 24%
August - 2020
Work in progress.
No Image
1785
(OG)
191765-170303-Construction of BT Roads in Sarwakai Sub Division, SWA. [MA]
South Waziristan
HW
30-11--1 30-11--1 - 30-11--1 - 351.326 76.499 129.424 80.056 80.056 80.056 156.555 145.403 59% 45%
May - 2021
E/Work,S/B, B/C & Structure work in progress.
No Image
1785
(OG)
191765-170303-Construction of BT Roads in Sarwakai Sub Division, SWA. [MA]
South Waziristan
HW
30-11--1 30-11--1 - 30-11--1 - 351.326 76.499 129.424 160.056 160.056 58.36 134.859 145.403 59% 38%
April - 2021
E/Work,S/B, B/C & Structure work in progress.
No Image
1785
(OG)
191765-170303-Construction of BT Roads in Sarwakai Sub Division, SWA. [MA]
South Waziristan
HW
30-11--1 30-11--1 - 30-11--1 - 351.326 76.499 129.424 160.056 160.056 49.83 126.329 145.403 59% 36%
March - 2021
E/Work,S/B, B/C & Structure work in progress.
No Image
1785
(OG)
191765-170303-Construction of BT Roads in Sarwakai Sub Division, SWA. [MA]
South Waziristan
HW
30-11--1 30-11--1 - 30-11--1 - 351.326 76.499 129.424 160.056 160.056 49.83 126.329 145.403 59% 36%
February - 2021
E/Work,S/B, B/C & Structure work in progress.
No Image
1785
(OG)
191765-170303-Construction of BT Roads in Sarwakai Sub Division, SWA. [MA]
South Waziristan
HW
30-11--1 30-11--1 - 30-11--1 - 351.326 76.499 129.424 160.056 160.056 38.933 115.432 145.403 59% 33%
January - 2021
E/Work,S/B, B/C & Structure work in progress.
No Image
1785
(OG)
191765-170303-Construction of BT Roads in Sarwakai Sub Division, SWA. [MA]
South Wazirstan
30-11--1 30-11--1 - 30-11--1 - 351.326 76.499 129.424 0 0 0 76.499 0
July - 2020
No Image
Pages : 1