Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2021, February - 2021, March - 2021, April - 2021, May - 2021, July - 2020, August - 2020, September - 2020, October - 2020, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1804
(OG)
191783-160171-Construction of Black Topped Roads in NWA, Phase-II. [MA]
North Waziristan
HW
30-11--1 30-11--1 - 30-11--1 - 359.85 320.719 39.131 39.131 18.184 9.764 330.483 0 100% 92%
December - 2020
06- Units. (Length 20-KMs) Completed= 13km (04 Units) Unit No.1&4 (7-Km) S/B, B/C & Structure work is in progress. Completion : June-2021.
No Image
1804
(OG)
191783-160171-Construction of Black Topped Roads in NWA, Phase-II. [MA]
North Waziristan
HW
30-11--1 30-11--1 - 30-11--1 - 359.85 320.719 39.131 39.131 18.184 9.764 330.483 0 100% 92%
December - 2020
06- Units. (Length 20-KMs) Completed= 13km (04 Units) Unit No.1&4 (7-Km) S/B, B/C & Structure work is in progress. Completion : June-2021.
No Image
1804
(OG)
191783-160171-Construction of Black Topped Roads in NWA, Phase-II. [MA]
North Waziristan
HW
30-11--1 30-11--1 - 30-11--1 - 359.85 320.719 39.131 39.131 18.184 7.881 328.6 0 100% 91%
October - 2020
06- Units. (Length 20-KMs) Completed= 13km (04 Units) Unit No.1&4 (7-Km) S/B, B/C & Structure work is in progress. Completion : June-2021.
No Image
1804
(OG)
191783-160171-Construction of Black Topped Roads in NWA, Phase-II. [MA]
North Waziristan
HW
30-11--1 30-11--1 - 30-11--1 - 359.85 320.719 39.131 39.131 9 0 320.719 0 100% 89%
September - 2020
06- Units. (Length 20-KMs) Completed= 13km (04 Units) Unit No.1&4 (7-Km) S/B, B/C & Structure work is in progress. Completion : June-2021.
No Image
1804
(OG)
191783-160171-Construction of Black Topped Roads in NWA, Phase-II. [MA]
North Waziristan
HW
30-11--1 30-11--1 - 30-11--1 - 359.85 320.719 39.131 39.131 9 0 320.719 0 - -
August - 2020
06- Units. (Length 20-KMs) Completed= 13km (04 Units) Unit No.1&4 (7-Km) S/B, B/C & Structure work is in progress. Completion : June-2021.
No Image
1804
(OG)
191783-160171-Construction of Black Topped Roads in NWA, Phase-II. [MA]
North Waziristan
HW
30-11--1 30-11--1 - 30-11--1 - 359.85 320.716 39.131 39.131 39.131 22.373 343.089 0.003 100% 95%
May - 2021
06- Units. (Length 20-KMs) Completed= 13km (04 Units) Unit No.1&4 (7-Km) S/B, B/C & Structure work is in progress. Completion : June-2021.
No Image
1804
(OG)
191783-160171-Construction of Black Topped Roads in NWA, Phase-II. [MA]
North Waziristan
HW
30-11--1 30-11--1 - 30-11--1 - 359.85 320.716 39.131 18.184 18.184 18.184 338.9 0.003 100% 94%
April - 2021
06- Units. (Length 20-KMs) Completed= 13km (04 Units) Unit No.1&4 (7-Km) S/B, B/C & Structure work is in progress. Completion : June-2021.
No Image
1804
(OG)
191783-160171-Construction of Black Topped Roads in NWA, Phase-II. [MA]
North Waziristan
HW
30-11--1 30-11--1 - 30-11--1 - 359.85 320.716 39.131 18.184 18.184 9.764 330.48 0.003 100% 92%
March - 2021
06- Units. (Length 20-KMs) Completed= 13km (04 Units) Unit No.1&4 (7-Km) S/B, B/C & Structure work is in progress. Completion : June-2021.
No Image
1804
(OG)
191783-160171-Construction of Black Topped Roads in NWA, Phase-II. [MA]
North Waziristan
HW
30-11--1 30-11--1 - 30-11--1 - 359.85 320.716 39.131 18.184 18.184 9.764 330.48 0.003 100% 92%
February - 2021
06- Units. (Length 20-KMs) Completed= 13km (04 Units) Unit No.1&4 (7-Km) S/B, B/C & Structure work is in progress. Completion : June-2021.
No Image
1804
(OG)
191783-160171-Construction of Black Topped Roads in NWA, Phase-II. [MA]
North Waziristan
HW
30-11--1 30-11--1 - 30-11--1 - 359.85 320.716 39.131 18.184 18.184 9.764 330.48 0.003 100% 92%
January - 2021
06- Units. (Length 20-KMs) Completed= 13km (04 Units) Unit No.1&4 (7-Km) S/B, B/C & Structure work is in progress. Completion : June-2021.
No Image
1804
(OG)
191783-160171-Construction of Black Topped Roads in NWA, Phase-II. [MA]
North Wazirstan
30-11--1 30-11--1 - 30-11--1 - 359.85 320.719 39.131 0 0 0 320.719 0
July - 2020
No Image
Pages : 1