Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1810 (OG) |
191737-070016-Construction of Shingled Road from Angori to Sarak (7 Kms) in Central Kurram (Revised). [MA] |
Kurram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 169.891 | 155.117 | 14.774 | 0 | 0 | 0 | 155.117 | 0 |
July - 2020 |
No Image | ||
1810 (OG) |
191737-070016-Construction of Shingled Road from Angori to Sarak (7 Kms) in Central Kurram (Revised). [MA] |
Kurram HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 168.881 | 173.197 | 14.774 | 4.306 | 0 | 0 | 173.197 | 0 | 100% |
100% December - 2020 |
Physically and financially complted |
No Image |
1810 (OG) |
191737-070016-Construction of Shingled Road from Angori to Sarak (7 Kms) in Central Kurram (Revised). [MA] |
Kurram HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 168.881 | 173.197 | 14.774 | 4.306 | 0 | 0 | 173.197 | 0 | 100% |
100% December - 2020 |
Physically and financially complted |
No Image |
1810 (OG) |
191737-070016-Construction of Shingled Road from Angori to Sarak (7 Kms) in Central Kurram (Revised). [MA] |
Kurram HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 168.881 | 155.117 | 14.774 | 14.774 | 10.457 | 0 | 155.117 | 0 | 100% |
92% October - 2020 |
Earth work completed. S/Work in progress.
Completion : June-2021. |
No Image |
1810 (OG) |
191737-070016-Construction of Shingled Road from Angori to Sarak (7 Kms) in Central Kurram (Revised). [MA] |
Kurram HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 168.881 | 155.117 | 14.774 | 14.774 | 7 | 0 | 155.117 | 0 | 100% |
92% September - 2020 |
Earth work completed. S/Work in progress.
Completion : June-2021. |
No Image |
1810 (OG) |
191737-070016-Construction of Shingled Road from Angori to Sarak (7 Kms) in Central Kurram (Revised). [MA] |
Kurram HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 168.881 | 155.117 | 14.774 | 14.774 | 7 | 0 | 155.117 | 0 | 100% |
92% August - 2020 |
Earth work completed. S/Work in progress.
Completion : June-2021. |
No Image |
1810 (OG) |
191737-070016-Construction of Shingled Road from Angori to Sarak (7 Kms) in Central Kurram (Revised). [MA] |
Kurram HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 168.881 | 173.197 | 14.774 | 0 | 0 | 0 | 173.197 | 0 | 100% |
100% May - 2021 |
Physically and financially complted
Delete from Draft ADP |
No Image |
1810 (OG) |
191737-070016-Construction of Shingled Road from Angori to Sarak (7 Kms) in Central Kurram (Revised). [MA] |
Kurram HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 168.881 | 173.197 | 14.774 | 0 | 0 | 0 | 173.197 | 0 | 100% |
100% April - 2021 |
Physically and financially complted
Delete from Draft ADP |
No Image |
1810 (OG) |
191737-070016-Construction of Shingled Road from Angori to Sarak (7 Kms) in Central Kurram (Revised). [MA] |
Kurram HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 168.881 | 173.197 | 14.774 | 0 | 0 | 0 | 173.197 | 0 | 100% |
100% March - 2021 |
Physically and financially complted |
No Image |
1810 (OG) |
191737-070016-Construction of Shingled Road from Angori to Sarak (7 Kms) in Central Kurram (Revised). [MA] |
Kurram HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 168.881 | 173.197 | 14.774 | 0 | 0 | 0 | 173.197 | 0 | 100% |
100% February - 2021 |
Physically and financially complted |
No Image |
1810 (OG) |
191737-070016-Construction of Shingled Road from Angori to Sarak (7 Kms) in Central Kurram (Revised). [MA] |
Kurram HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 168.881 | 173.197 | 14.774 | 10.467 | 10.467 | 0 | 173.197 | 0 | 100% |
100% January - 2021 |
Physically and financially complted |
No Image |
Pages : 1 |