Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1812 (OG) |
191798-180363 - Construction, & Rehabilitation of existing Blacktop roads in Upper District Kurram. [MA] |
Kurram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 204.243 | 35 | 45 | 0 | 0 | 0 | 35 | 0 |
July - 2020 |
No Image | ||
1812 (OG) |
191798-180363 - Construction, & Rehabilitation of existing Blacktop roads in Upper District Kurram. [MA] |
Kurram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 204.243 | 30 | 45 | 32.562 | 32.562 | 32.42 | 62.42 | 129.243 | 37% |
31% May - 2021 |
03 Packages
1 In progres
2 Site not yet identifed
3 Site not yet identifed |
No Image |
Package I
1. Const: of BTR of remaining portion Sayed Abass Jan Main Road 0.6 KM
2. Const: of BTR of Road Korizgai to Malana 2 KM
Package II
1. Const: of BTR of Ghulam Jan Check post to Inter Link Faqeer Baba and Khawar Colony Parachinar 2 KM
2. Const: of BTR road of Main Kirman road to College Colony 1 KM
Package III
1. Const: of BTR of road form Zahir Mila to Tajak Qabristan 2 KM
2. Const: of BTR of road Imam Bagh to Zore Kali Linking to Barota Mir Kalam Road | |||||||||||||||||||
1812 (OG) |
191798-180363 - Construction, & Rehabilitation of existing Blacktop roads in Upper District Kurram. [MA] |
Kurram HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 204.243 | 55.544 | 45 | 32.562 | 32.562 | 17.562 | 73.106 | 103.699 | 49% |
36% December - 2020 |
Earth work completed. S/Work & Road work in progress. |
No Image |
1812 (OG) |
191798-180363 - Construction, & Rehabilitation of existing Blacktop roads in Upper District Kurram. [MA] |
Kurram HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 204.243 | 55.544 | 45 | 32.562 | 32.562 | 17.562 | 73.106 | 103.699 | 49% |
36% December - 2020 |
Earth work completed. S/Work & Road work in progress. |
No Image |
1812 (OG) |
191798-180363 - Construction, & Rehabilitation of existing Blacktop roads in Upper District Kurram. [MA] |
Kurram HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 204.243 | 55.544 | 45 | 45 | 17.562 | 15 | 70.544 | 103.699 | 49% |
35% October - 2020 |
Earth work completed. S/Work & Road work in progress. |
No Image |
1812 (OG) |
191798-180363 - Construction, & Rehabilitation of existing Blacktop roads in Upper District Kurram. [MA] |
Kurram HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 204.243 | 55.544 | 45 | 45 | 7 | 0 | 55.544 | 103.699 | 49% |
27% September - 2020 |
Earth work completed. S/Work & Road work in progress. |
No Image |
1812 (OG) |
191798-180363 - Construction, & Rehabilitation of existing Blacktop roads in Upper District Kurram. [MA] |
Kurram HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 204.243 | 55.544 | 45 | 45 | 7 | 0 | 55.544 | 103.699 | 49% |
27% August - 2020 |
Earth work completed. S/Work & Road work in progress. |
No Image |
1812 (OG) |
191798-180363 - Construction, & Rehabilitation of existing Blacktop roads in Upper District Kurram. [MA] |
Kurram HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 204.243 | 30 | 45 | 32.562 | 32.562 | 32.42 | 62.42 | 129.243 | 37% |
31% April - 2021 |
03 Packages
1 In progres
2 Site not yet identifed
3 Site not yet identifed |
No Image |
Package I
1. Const: of BTR of remaining portion Sayed Abass Jan Main Road 0.6 KM
2. Const: of BTR of Road Korizgai to Malana 2 KM
Package II
1. Const: of BTR of Ghulam Jan Check post to Inter Link Faqeer Baba and Khawar Colony Parachinar 2 KM
2. Const: of BTR road of Main Kirman road to College Colony 1 KM
Package III
1. Const: of BTR of road form Zahir Mila to Tajak Qabristan 2 KM
2. Const: of BTR of road Imam Bagh to Zore Kali Linking to Barota Mir Kalam Road | |||||||||||||||||||
1812 (OG) |
191798-180363 - Construction, & Rehabilitation of existing Blacktop roads in Upper District Kurram. [MA] |
Kurram HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 204.243 | 30 | 45 | 32.562 | 32.562 | 25.395 | 55.395 | 129.243 | 37% |
27% March - 2021 |
03 Packages
1 In progres
2 Site not yet identifed
3 Site not yet identifed |
No Image |
Package I
1. Const: of BTR of remaining portion Sayed Abass Jan Main Road 0.6 KM
2. Const: of BTR of Road Korizgai to Malana 2 KM
Package II
1. Const: of BTR of Ghulam Jan Check post to Inter Link Faqeer Baba and Khawar Colony Parachinar 2 KM
2. Const: of BTR road of Main Kirman road to College Colony 1 KM
Package III
1. Const: of BTR of road form Zahir Mila to Tajak Qabristan 2 KM
2. Const: of BTR of road Imam Bagh to Zore Kali Linking to Barota Mir Kalam Road | |||||||||||||||||||
1812 (OG) |
191798-180363 - Construction, & Rehabilitation of existing Blacktop roads in Upper District Kurram. [MA] |
Kurram HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 204.243 | 30 | 45 | 32.562 | 32.562 | 25.395 | 55.395 | 129.243 | 37% |
27% February - 2021 |
03 Packages
1 In progres
2 Site not yet identifed
3 Site not yet identifed |
No Image |
Package I
1. Const: of BTR of remaining portion Sayed Abass Jan Main Road 0.6 KM
2. Const: of BTR of Road Korizgai to Malana 2 KM
Package II
1. Const: of BTR of Ghulam Jan Check post to Inter Link Faqeer Baba and Khawar Colony Parachinar 2 KM
2. Const: of BTR road of Main Kirman road to College Colony 1 KM
Package III
1. Const: of BTR of road form Zahir Mila to Tajak Qabristan 2 KM
2. Const: of BTR of road Imam Bagh to Zore Kali Linking to Barota Mir Kalam Road | |||||||||||||||||||
1812 (OG) |
191798-180363 - Construction, & Rehabilitation of existing Blacktop roads in Upper District Kurram. [MA] |
Kurram HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 204.243 | 55.544 | 45 | 32.562 | 32.562 | 17.562 | 73.106 | 103.699 | 49% |
36% January - 2021 |
Earth work completed. S/Work & Road work in progress. |
No Image |
Pages : 1 |