Progressive Review for the month(s) of : January - 2021, February - 2021, March - 2021, April - 2021, May - 2021, July - 2020, August - 2020, September - 2020, October - 2020, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1813
(OG)
191799-180364 - Widening & Rehabilitation of existing Blacktop road from Inzera Check Post to Shaheedano Dand (Ph-III) (3 Kms). [MA]
Kurram
30-11--1 30-11--1 - 30-11--1 - 66.204 32.75 33.454 0 0 0 32.75 0
July - 2020
No Image
1813
(OG)
191799-180364 - Widening & Rehabilitation of existing Blacktop road from Inzera Check Post to Shaheedano Dand (Ph-III) (3 Kms). [MA]
Kurram
HW
30-11--1 30-11--1 - 30-11--1 - 66.204 32.75 33.454 38.852 38.852 15.852 48.602 0 100% 73%
December - 2020
Length 03-Km Earth work & Structre work in progress. Completion : June-2021.
No Image
1813
(OG)
191799-180364 - Widening & Rehabilitation of existing Blacktop road from Inzera Check Post to Shaheedano Dand (Ph-III) (3 Kms). [MA]
Kurram
HW
30-11--1 30-11--1 - 30-11--1 - 66.204 32.75 33.454 38.852 38.852 15.852 48.602 0 100% 73%
December - 2020
Length 03-Km Earth work & Structre work in progress. Completion : June-2021.
No Image
1813
(OG)
191799-180364 - Widening & Rehabilitation of existing Blacktop road from Inzera Check Post to Shaheedano Dand (Ph-III) (3 Kms). [MA]
Kurram
HW
30-11--1 30-11--1 - 30-11--1 - 66.204 32.75 33.454 33.454 15.852 15.852 48.602 0 100% 73%
October - 2020
Length 03-Km Earth work & Structre work in progress. Completion : June-2021.
No Image
1813
(OG)
191799-180364 - Widening & Rehabilitation of existing Blacktop road from Inzera Check Post to Shaheedano Dand (Ph-III) (3 Kms). [MA]
Kurram
HW
30-11--1 30-11--1 - 30-11--1 - 66.204 32.75 33.454 33.454 8 0 32.75 0 100% 49%
September - 2020
Length 03-Km Earth work & Structre work in progress. Completion : June-2021.
No Image
1813
(OG)
191799-180364 - Widening & Rehabilitation of existing Blacktop road from Inzera Check Post to Shaheedano Dand (Ph-III) (3 Kms). [MA]
Kurram
HW
30-11--1 30-11--1 - 30-11--1 - 66.204 32.75 33.454 33.454 8 0 32.75 0 100% 49%
August - 2020
Length 03-Km Earth work & Structre work in progress. Completion : June-2021.
No Image
1813
(OG)
191799-180364 - Widening & Rehabilitation of existing Blacktop road from Inzera Check Post to Shaheedano Dand (Ph-III) (3 Kms). [MA]
Kurram
HW
30-11--1 30-11--1 - 30-11--1 - 66.204 32.75 33.454 30.852 30.852 24.431 57.181 0 100% 86%
May - 2021
Length 03-Km Earth work & Structre work in progress. Completion : June-2021.
No Image
1813
(OG)
191799-180364 - Widening & Rehabilitation of existing Blacktop road from Inzera Check Post to Shaheedano Dand (Ph-III) (3 Kms). [MA]
Kurram
HW
30-11--1 30-11--1 - 30-11--1 - 66.204 32.75 33.454 30.852 30.852 24.431 57.181 0 100% 86%
April - 2021
Length 03-Km Earth work & Structre work in progress. Completion : June-2021.
No Image
1813
(OG)
191799-180364 - Widening & Rehabilitation of existing Blacktop road from Inzera Check Post to Shaheedano Dand (Ph-III) (3 Kms). [MA]
Kurram
HW
30-11--1 30-11--1 - 30-11--1 - 66.204 32.75 33.454 30.852 30.852 24.431 57.181 0 100% 86%
March - 2021
Length 03-Km Earth work & Structre work in progress. Completion : June-2021.
No Image
1813
(OG)
191799-180364 - Widening & Rehabilitation of existing Blacktop road from Inzera Check Post to Shaheedano Dand (Ph-III) (3 Kms). [MA]
Kurram
HW
30-11--1 30-11--1 - 30-11--1 - 66.204 32.75 33.454 30.852 30.852 24.431 57.181 0 100% 86%
February - 2021
Length 03-Km Earth work & Structre work in progress. Completion : June-2021.
No Image
1813
(OG)
191799-180364 - Widening & Rehabilitation of existing Blacktop road from Inzera Check Post to Shaheedano Dand (Ph-III) (3 Kms). [MA]
Kurram
HW
30-11--1 30-11--1 - 30-11--1 - 66.204 32.75 33.454 30.852 30.852 15.852 48.602 0 100% 73%
January - 2021
Length 03-Km Earth work & Structre work in progress. Completion : June-2021.
No Image