1815 (OG) |
191709-170140-Construction & Black Topping of Roads in Orakzai Agency. [MA] |
Orakzai |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 133.027 | 87.251 | 45.776 | 45.776 | 22.74 | 8.092 | 95.343 | 0 | 100% |
72% December - 2020 |
03- Units
Length 10.5 Km
S/B, B/C, S/W & Asphalt premix in progress.
Completion : June-2021. |
No Image |
1) TotanitoDarak road (4-Km)
2) Nikot to Akheria Kalay (5-Km)
3) Ghiljo to Dabbori via Sampog (1.3Kms) | |||||||||||||||||||
1815 (OG) |
191709-170140-Construction & Black Topping of Roads in Orakzai Agency. [MA] |
Orakzai |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 133.027 | 87.251 | 45.776 | 45.776 | 22.74 | 8.092 | 95.343 | 0 | 100% |
72% December - 2020 |
03- Units
Length 10.5 Km
S/B, B/C, S/W & Asphalt premix in progress.
Completion : June-2021. |
No Image |
1) TotanitoDarak road (4-Km)
2) Nikot to Akheria Kalay (5-Km)
3) Ghiljo to Dabbori via Sampog (1.3Kms) | |||||||||||||||||||
1815 (OG) |
191709-170140-Construction & Black Topping of Roads in Orakzai Agency. [MA] |
Orakzai |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 133.027 | 87.251 | 45.776 | 45.776 | 12 | 5.966 | 93.217 | 0 | 100% |
70% October - 2020 |
03- Units
Length 10.5 Km
S/B, B/C, S/W & Asphalt premix in progress.
Completion : June-2021. |
No Image |
1) TotanitoDarak road (4-Km)
2) Nikot to Akheria Kalay (5-Km)
3) Ghiljo to Dabbori via Sampog (1.3Kms) | |||||||||||||||||||
1815 (OG) |
191709-170140-Construction & Black Topping of Roads in Orakzai Agency. [MA] |
Orakzai |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 133.027 | 87.251 | 45.776 | 45.776 | 12 | 5.966 | 93.217 | 0 | 100% |
70% September - 2020 |
03- Units
Length 10.5 Km
S/B, B/C, S/W & Asphalt premix in progress.
Completion : June-2021. |
No Image |
1815 (OG) |
191709-170140-Construction & Black Topping of Roads in Orakzai Agency. [MA] |
Orakzai |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 133.027 | 87.251 | 45.776 | 45.776 | 12 | 0 | 87.251 | 0 | 100% |
66% August - 2020 |
03- Units
Length 10.5 Km
S/B, B/C, S/W & Asphalt premix in progress.
Completion : June-2021. |
No Image |
1815 (OG) |
191709-170140-Construction & Black Topping of Roads in Orakzai Agency. [MA] |
Orakzai |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 133.027 | 87.251 | 45.776 | 0 | 0 | 0 | 87.251 | 0 |
July - 2020 |
No Image | ||
1815 (OG) |
191709-170140-Construction & Black Topping of Roads in Orakzai Agency. [MA] |
Orakzai |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 133.027 | 87.251 | 45.776 | 22.774 | 22.774 | 8.19 | 95.441 | 0 | 100% |
72% March - 2021 |
03- Units
Length 10.5 Km
S/B, B/C, S/W & Asphalt premix in progress.
Completion : June-2021. |
No Image |
1) TotanitoDarak road (4-Km)
2) Nikot to Akheria Kalay (5-Km)
3) Ghiljo to Dabbori via Sampog (1.3Kms) | |||||||||||||||||||
1815 (OG) |
191709-170140-Construction & Black Topping of Roads in Orakzai Agency. [MA] |
Orakzai |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 133.027 | 87.251 | 45.776 | 22.774 | 22.774 | 8.19 | 95.441 | 0 | 100% |
72% February - 2021 |
03- Units
Length 10.5 Km
S/B, B/C, S/W & Asphalt premix in progress.
Completion : June-2021. |
No Image |
1) TotanitoDarak road (4-Km)
2) Nikot to Akheria Kalay (5-Km)
3) Ghiljo to Dabbori via Sampog (1.3Kms) | |||||||||||||||||||
1815 (OG) |
191709-170140-Construction & Black Topping of Roads in Orakzai Agency. [MA] |
Orakzai |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 133.027 | 87.251 | 45.776 | 22.774 | 22.774 | 8.19 | 95.441 | 0 | 100% |
72% January - 2021 |
03- Units
Length 10.5 Km
S/B, B/C, S/W & Asphalt premix in progress.
Completion : June-2021. |
No Image |
1) TotanitoDarak road (4-Km)
2) Nikot to Akheria Kalay (5-Km)
3) Ghiljo to Dabbori via Sampog (1.3Kms) | |||||||||||||||||||
1815 (OG) |
191709-170140-Construction & Black Topping of Roads in Orakzai Agency. [MA] |
Orakzai HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 133.027 | 87.251 | 45.776 | 12.774 | 12.774 | 9.817 | 97.068 | 0 | 100% |
73% May - 2021 |
03- Units
Length 10.5 Km
S/B, B/C, S/W & Asphalt premix in progress.
Cannot be completed |
No Image |
1) Totani to Darak road (4-Km)
2) Nikot to Akheria Kalay (5-Km)
3) Ghiljo to Dabbori via Sampog (1.3Kms) | |||||||||||||||||||
1815 (OG) |
191709-170140-Construction & Black Topping of Roads in Orakzai Agency. [MA] |
Orakzai HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 133.027 | 87.251 | 45.776 | 12.774 | 12.774 | 9.59 | 96.841 | 0 | 100% |
73% April - 2021 |
03- Units
Length 10.5 Km
S/B, B/C, S/W & Asphalt premix in progress.
Cannot be completed |
No Image |
1) Totani to Darak road (4-Km)
2) Nikot to Akheria Kalay (5-Km)
3) Ghiljo to Dabbori via Sampog (1.3Kms) | |||||||||||||||||||