Progressive Review for the month(s) of : January - 2021, February - 2021, March - 2021, April - 2021, May - 2021, July - 2020, August - 2020, September - 2020, October - 2020, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1815
(OG)
191709-170140-Construction & Black Topping of Roads in Orakzai Agency. [MA]
Orakzai
30-11--1 30-11--1 - 30-11--1 - 133.027 87.251 45.776 45.776 22.74 8.092 95.343 0 100% 72%
December - 2020
03- Units Length 10.5 Km S/B, B/C, S/W & Asphalt premix in progress. Completion : June-2021.
No Image
1) TotanitoDarak road (4-Km)
2) Nikot to Akheria Kalay (5-Km)
3) Ghiljo to Dabbori via Sampog (1.3Kms)
1815
(OG)
191709-170140-Construction & Black Topping of Roads in Orakzai Agency. [MA]
Orakzai
30-11--1 30-11--1 - 30-11--1 - 133.027 87.251 45.776 45.776 22.74 8.092 95.343 0 100% 72%
December - 2020
03- Units Length 10.5 Km S/B, B/C, S/W & Asphalt premix in progress. Completion : June-2021.
No Image
1) TotanitoDarak road (4-Km)
2) Nikot to Akheria Kalay (5-Km)
3) Ghiljo to Dabbori via Sampog (1.3Kms)
1815
(OG)
191709-170140-Construction & Black Topping of Roads in Orakzai Agency. [MA]
Orakzai
30-11--1 30-11--1 - 30-11--1 - 133.027 87.251 45.776 45.776 12 5.966 93.217 0 100% 70%
October - 2020
03- Units Length 10.5 Km S/B, B/C, S/W & Asphalt premix in progress. Completion : June-2021.
No Image
1) TotanitoDarak road (4-Km)
2) Nikot to Akheria Kalay (5-Km)
3) Ghiljo to Dabbori via Sampog (1.3Kms)
1815
(OG)
191709-170140-Construction & Black Topping of Roads in Orakzai Agency. [MA]
Orakzai
30-11--1 30-11--1 - 30-11--1 - 133.027 87.251 45.776 45.776 12 5.966 93.217 0 100% 70%
September - 2020
03- Units Length 10.5 Km S/B, B/C, S/W & Asphalt premix in progress. Completion : June-2021.
No Image
1815
(OG)
191709-170140-Construction & Black Topping of Roads in Orakzai Agency. [MA]
Orakzai
30-11--1 30-11--1 - 30-11--1 - 133.027 87.251 45.776 45.776 12 0 87.251 0 100% 66%
August - 2020
03- Units Length 10.5 Km S/B, B/C, S/W & Asphalt premix in progress. Completion : June-2021.
No Image
1815
(OG)
191709-170140-Construction & Black Topping of Roads in Orakzai Agency. [MA]
Orakzai
30-11--1 30-11--1 - 30-11--1 - 133.027 87.251 45.776 0 0 0 87.251 0
July - 2020
No Image
1815
(OG)
191709-170140-Construction & Black Topping of Roads in Orakzai Agency. [MA]
Orakzai
30-11--1 30-11--1 - 30-11--1 - 133.027 87.251 45.776 22.774 22.774 8.19 95.441 0 100% 72%
March - 2021
03- Units Length 10.5 Km S/B, B/C, S/W & Asphalt premix in progress. Completion : June-2021.
No Image
1) TotanitoDarak road (4-Km)
2) Nikot to Akheria Kalay (5-Km)
3) Ghiljo to Dabbori via Sampog (1.3Kms)
1815
(OG)
191709-170140-Construction & Black Topping of Roads in Orakzai Agency. [MA]
Orakzai
30-11--1 30-11--1 - 30-11--1 - 133.027 87.251 45.776 22.774 22.774 8.19 95.441 0 100% 72%
February - 2021
03- Units Length 10.5 Km S/B, B/C, S/W & Asphalt premix in progress. Completion : June-2021.
No Image
1) TotanitoDarak road (4-Km)
2) Nikot to Akheria Kalay (5-Km)
3) Ghiljo to Dabbori via Sampog (1.3Kms)
1815
(OG)
191709-170140-Construction & Black Topping of Roads in Orakzai Agency. [MA]
Orakzai
30-11--1 30-11--1 - 30-11--1 - 133.027 87.251 45.776 22.774 22.774 8.19 95.441 0 100% 72%
January - 2021
03- Units Length 10.5 Km S/B, B/C, S/W & Asphalt premix in progress. Completion : June-2021.
No Image
1) TotanitoDarak road (4-Km)
2) Nikot to Akheria Kalay (5-Km)
3) Ghiljo to Dabbori via Sampog (1.3Kms)
1815
(OG)
191709-170140-Construction & Black Topping of Roads in Orakzai Agency. [MA]
Orakzai
HW
30-11--1 30-11--1 - 30-11--1 - 133.027 87.251 45.776 12.774 12.774 9.817 97.068 0 100% 73%
May - 2021
03- Units Length 10.5 Km S/B, B/C, S/W & Asphalt premix in progress. Cannot be completed
No Image
1) Totani to Darak road (4-Km)
2) Nikot to Akheria Kalay (5-Km)
3) Ghiljo to Dabbori via Sampog (1.3Kms)
1815
(OG)
191709-170140-Construction & Black Topping of Roads in Orakzai Agency. [MA]
Orakzai
HW
30-11--1 30-11--1 - 30-11--1 - 133.027 87.251 45.776 12.774 12.774 9.59 96.841 0 100% 73%
April - 2021
03- Units Length 10.5 Km S/B, B/C, S/W & Asphalt premix in progress. Cannot be completed
No Image
1) Totani to Darak road (4-Km)
2) Nikot to Akheria Kalay (5-Km)
3) Ghiljo to Dabbori via Sampog (1.3Kms)
Pages : 1