Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1817 (OG) |
191711-170142- Rehabilitation of Road in Lower Sub Division of District Orakzai. (5 kms) [MA] |
Orakzai |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 48.679 | 0 | 46.679 | 46.679 | 12.956 | 7.94 | 7.94 | 2 | 96% |
16% December - 2020 |
Work Started.
Completion : June-2021. |
No Image |
1817 (OG) |
191711-170142- Rehabilitation of Road in Lower Sub Division of District Orakzai. (5 kms) [MA] |
Orakzai |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 48.679 | 0 | 46.679 | 46.679 | 12.956 | 7.94 | 7.94 | 2 | 96% |
16% December - 2020 |
Work Started.
Completion : June-2021. |
No Image |
1817 (OG) |
191711-170142- Rehabilitation of Road in Lower Sub Division of District Orakzai. (5 kms) [MA] |
Orakzai |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 48.679 | 0 | 46.679 | 46.679 | 12 | 0 | 0 | 2 | 96% |
- October - 2020 |
Work Started.
Completion : June-2021. |
No Image |
1817 (OG) |
191711-170142- Rehabilitation of Road in Lower Sub Division of District Orakzai. (5 kms) [MA] |
Orakzai |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 48.679 | 2 | 46.679 | 46.679 | 12 | 0 | 2 | 0 | 100% |
4% September - 2020 |
Work Started.
Completion : June-2021. |
No Image |
1817 (OG) |
191711-170142- Rehabilitation of Road in Lower Sub Division of District Orakzai. (5 kms) [MA] |
Orakzai |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 48.679 | 2 | 46.679 | 46.679 | 12 | 0 | 2 | 0 | 100% |
4% August - 2020 |
Work Started.
Completion : June-2021. |
No Image |
1817 (OG) |
191711-170142- Rehabilitation of Road in Lower Sub Division of District Orakzai. (5 kms) [MA] |
Orakzai |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 48.679 | 2 | 46.679 | 0 | 0 | 0 | 2 | 0 |
July - 2020 |
No Image | ||
1817 (OG) |
191711-170142- Rehabilitation of Road in Lower Sub Division of District Orakzai. (5 kms) [MA] |
Orakzai |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 48.679 | 0 | 46.679 | 12.956 | 12.956 | 7.94 | 7.94 | 2 | 96% |
16% March - 2021 |
Work in progress
Completion : June-2021. |
No Image |
Hassan Zai Dara Road 5 KM | |||||||||||||||||||
1817 (OG) |
191711-170142- Rehabilitation of Road in Lower Sub Division of District Orakzai. (5 kms) [MA] |
Orakzai |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 48.679 | 0 | 46.679 | 12.956 | 12.956 | 7.94 | 7.94 | 2 | 96% |
16% February - 2021 |
Work in progress
Completion : June-2021. |
No Image |
Hassan Zai Dara Road 5 KM | |||||||||||||||||||
1817 (OG) |
191711-170142- Rehabilitation of Road in Lower Sub Division of District Orakzai. (5 kms) [MA] |
Orakzai |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 48.679 | 0 | 46.679 | 12.956 | 12.956 | 7.94 | 7.94 | 2 | 96% |
16% January - 2021 |
Work Started.
Completion : June-2021. |
No Image |
Hassan Zai Dara Road 5 KM | |||||||||||||||||||
1817 (OG) |
191711-170142- Rehabilitation of Road in Lower Sub Division of District Orakzai. (5 kms) [MA] |
Orakzai HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 48.679 | 0 | 46.679 | 12.956 | 12.956 | 11.82 | 11.82 | 2 | 96% |
24% May - 2021 |
Work in progress
Demand Rs: 5 M
Completion : June-2021. |
No Image |
Hassan Zai Dara Road 5 KM | |||||||||||||||||||
1817 (OG) |
191711-170142- Rehabilitation of Road in Lower Sub Division of District Orakzai. (5 kms) [MA] |
Orakzai HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 48.679 | 0 | 46.679 | 12.956 | 12.956 | 11.82 | 11.82 | 2 | 96% |
24% April - 2021 |
Work in progress
Demand Rs: 5 M
Completion : June-2021. |
No Image |
Hassan Zai Dara Road 5 KM | |||||||||||||||||||
Pages : 1 |