Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1819 (OG) |
191773-170370-Construction of Road from Kasha to Darran Via Bego Tangi Phase-I in Orakzai Agency. [MA] |
Orakzai |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 157.233 | 142.715 | 10.792 | 10.792 | 7.533 | 7.533 | 150.248 | 3.726 | 98% |
96% December - 2020 |
S/B, B/C completed S/W & Asphalt premix in progress.
Completion : June-2021. |
No Image |
1819 (OG) |
191773-170370-Construction of Road from Kasha to Darran Via Bego Tangi Phase-I in Orakzai Agency. [MA] |
Orakzai |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 157.233 | 142.715 | 10.792 | 10.792 | 7.533 | 7.533 | 150.248 | 3.726 | 98% |
96% December - 2020 |
S/B, B/C completed S/W & Asphalt premix in progress.
Completion : June-2021. |
No Image |
1819 (OG) |
191773-170370-Construction of Road from Kasha to Darran Via Bego Tangi Phase-I in Orakzai Agency. [MA] |
Orakzai |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 157.233 | 142.715 | 10.792 | 10.792 | 5 | 0.103 | 142.818 | 3.726 | 98% |
91% October - 2020 |
S/B, B/C completed S/W & Asphalt premix in progress.
Completion : June-2021. |
No Image |
1819 (OG) |
191773-170370-Construction of Road from Kasha to Darran Via Bego Tangi Phase-I in Orakzai Agency. [MA] |
Orakzai |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 157.233 | 142.715 | 10.792 | 10.792 | 5 | 0 | 142.715 | 3.726 | 98% |
91% September - 2020 |
S/B, B/C completed S/W & Asphalt premix in progress.
Completion : June-2021. |
No Image |
1819 (OG) |
191773-170370-Construction of Road from Kasha to Darran Via Bego Tangi Phase-I in Orakzai Agency. [MA] |
Orakzai |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 157.233 | 142.715 | 10.792 | 10.792 | 5 | 0 | 142.715 | 3.726 | 98% |
91% August - 2020 |
S/B, B/C, S/W & Asphalt premix in progress.
Completion : June-2021. |
No Image |
1819 (OG) |
191773-170370-Construction of Road from Kasha to Darran Via Bego Tangi Phase-I in Orakzai Agency. [MA] |
Orakzai |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 157.233 | 146.441 | 10.792 | 0 | 0 | 0 | 146.441 | 0 |
July - 2020 |
No Image | ||
1819 (OG) |
191773-170370-Construction of Road from Kasha to Darran Via Bego Tangi Phase-I in Orakzai Agency. [MA] |
Orakzai |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 157.233 | 142.715 | 10.792 | 7.533 | 7.533 | 7.533 | 150.248 | 3.726 | 98% |
96% March - 2021 |
S/B, B/C completed S/W & Asphalt premix in progress.
Completion : June-2021. |
No Image |
Hassanzai Dara Road (5-KM) | |||||||||||||||||||
1819 (OG) |
191773-170370-Construction of Road from Kasha to Darran Via Bego Tangi Phase-I in Orakzai Agency. [MA] |
Orakzai |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 157.233 | 142.715 | 10.792 | 7.533 | 7.533 | 7.533 | 150.248 | 3.726 | 98% |
96% February - 2021 |
S/B, B/C completed S/W & Asphalt premix in progress.
Completion : June-2021. |
No Image |
Hassanzai Dara Road (5-KM) | |||||||||||||||||||
1819 (OG) |
191773-170370-Construction of Road from Kasha to Darran Via Bego Tangi Phase-I in Orakzai Agency. [MA] |
Orakzai |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 157.233 | 142.715 | 10.792 | 7.533 | 7.533 | 7.533 | 150.248 | 3.726 | 98% |
96% January - 2021 |
S/B, B/C completed S/W & Asphalt premix in progress.
Completion : June-2021. |
No Image |
1819 (OG) |
191773-170370-Construction of Road from Kasha to Darran Via Bego Tangi Phase-I in Orakzai Agency. [MA] |
Orakzai HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 157.233 | 142.715 | 10.792 | 12.533 | 12.533 | 7.533 | 150.248 | 3.726 | 98% |
96% May - 2021 |
S/B, B/C completed S/W & Asphalt premix in progress.
Reappropiration Demand Rs; 5 M
Completion : June-2021. |
No Image |
Hassanzai Dara Road (5-KM) | |||||||||||||||||||
1819 (OG) |
191773-170370-Construction of Road from Kasha to Darran Via Bego Tangi Phase-I in Orakzai Agency. [MA] |
Orakzai HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 157.233 | 142.715 | 10.792 | 7.533 | 7.533 | 7.533 | 150.248 | 3.726 | 98% |
96% April - 2021 |
S/B, B/C completed S/W & Asphalt premix in progress.
Reappropiration Demand Rs; 5 M
Completion : June-2021. |
No Image |
Hassanzai Dara Road (5-KM) | |||||||||||||||||||
Pages : 1 |