Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1831 (OG) |
191809-170445 - Construction of Black Topping of Road from Sher Khel to Serai Kandow upto Dars Masjid (10.5 KMs) & Sarzai to Sangara Balance Portion (2.5 KMs) in Tirah, Khyber District (GD). [MA] |
Khyber |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 210.494 | 109.609 | 24 | 0 | 0 | 0 | 109.609 | 76.885 | 63% |
52% July - 2020 |
Work in progress. |
No Image |
1831 (OG) |
191809-170445 - Construction of Black Topping of Road from Sher Khel to Serai Kandow upto Dars Masjid (10.5 KMs) & Sarzai to Sangara Balance Portion (2.5 KMs) in Tirah, Khyber District (GD). [MA] |
Khyber HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 210.494 | 109.609 | 24 | 24 | 10.633 | 0 | 109.609 | 76.885 | 63% |
52% December - 2020 |
Length 13 Km - 2.5 km asphlat laid |
No Image |
1831 (OG) |
191809-170445 - Construction of Black Topping of Road from Sher Khel to Serai Kandow upto Dars Masjid (10.5 KMs) & Sarzai to Sangara Balance Portion (2.5 KMs) in Tirah, Khyber District (GD). [MA] |
Khyber HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 210.494 | 109.609 | 24 | 24 | 10.633 | 0 | 109.609 | 76.885 | 63% |
52% December - 2020 |
Length 13 Km - 2.5 km asphlat laid |
No Image |
1831 (OG) |
191809-170445 - Construction of Black Topping of Road from Sher Khel to Serai Kandow upto Dars Masjid (10.5 KMs) & Sarzai to Sangara Balance Portion (2.5 KMs) in Tirah, Khyber District (GD). [MA] |
Khyber HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 210.494 | 109.609 | 24 | 24 | 5 | 0 | 109.609 | 76.885 | 63% |
52% October - 2020 |
Work in progress. |
No Image |
1831 (OG) |
191809-170445 - Construction of Black Topping of Road from Sher Khel to Serai Kandow upto Dars Masjid (10.5 KMs) & Sarzai to Sangara Balance Portion (2.5 KMs) in Tirah, Khyber District (GD). [MA] |
Khyber HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 210.494 | 109.609 | 24 | 24 | 5 | 0 | 109.609 | 76.885 | 63% |
52% September - 2020 |
Work in progress. |
No Image |
1831 (OG) |
191809-170445 - Construction of Black Topping of Road from Sher Khel to Serai Kandow upto Dars Masjid (10.5 KMs) & Sarzai to Sangara Balance Portion (2.5 KMs) in Tirah, Khyber District (GD). [MA] |
Khyber HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 210.494 | 109.609 | 24 | 24 | 5 | 0 | 109.609 | 76.885 | 63% |
52% August - 2020 |
Work in progress. |
No Image |
1831 (OG) |
191809-170445 - Construction of Black Topping of Road from Sher Khel to Serai Kandow upto Dars Masjid (10.5 KMs) & Sarzai to Sangara Balance Portion (2.5 KMs) in Tirah, Khyber District (GD). [MA] |
Khyber HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 210.494 | 109.609 | 24 | 24 | 24 | 10.563 | 120.172 | 76.885 | 63% |
57% May - 2021 |
Length 13 Km - 2.5 km asphlat laid |
No Image |
1831 (OG) |
191809-170445 - Construction of Black Topping of Road from Sher Khel to Serai Kandow upto Dars Masjid (10.5 KMs) & Sarzai to Sangara Balance Portion (2.5 KMs) in Tirah, Khyber District (GD). [MA] |
Khyber HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 210.494 | 109.609 | 24 | 10.633 | 10.633 | 9.742 | 119.351 | 76.885 | 63% |
57% April - 2021 |
Length 13 Km - 2.5 km asphlat laid |
No Image |
1831 (OG) |
191809-170445 - Construction of Black Topping of Road from Sher Khel to Serai Kandow upto Dars Masjid (10.5 KMs) & Sarzai to Sangara Balance Portion (2.5 KMs) in Tirah, Khyber District (GD). [MA] |
Khyber HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 210.494 | 109.609 | 24 | 10.633 | 10.633 | 9.742 | 119.351 | 76.885 | 63% |
57% March - 2021 |
Length 13 Km - 2.5 km asphlat laid |
No Image |
1831 (OG) |
191809-170445 - Construction of Black Topping of Road from Sher Khel to Serai Kandow upto Dars Masjid (10.5 KMs) & Sarzai to Sangara Balance Portion (2.5 KMs) in Tirah, Khyber District (GD). [MA] |
Khyber HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 210.494 | 109.609 | 24 | 10.633 | 10.633 | 9.742 | 119.351 | 76.885 | 63% |
57% February - 2021 |
Length 13 Km - 2.5 km asphlat laid |
No Image |
1831 (OG) |
191809-170445 - Construction of Black Topping of Road from Sher Khel to Serai Kandow upto Dars Masjid (10.5 KMs) & Sarzai to Sangara Balance Portion (2.5 KMs) in Tirah, Khyber District (GD). [MA] |
Khyber HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 210.494 | 109.609 | 24 | 10.633 | 10.633 | 0 | 109.609 | 76.885 | 63% |
52% January - 2021 |
Length 13 Km - 2.5 km asphlat laid |
No Image |
Pages : 1 |