Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2021, February - 2021, March - 2021, April - 2021, May - 2021, July - 2020, August - 2020, September - 2020, October - 2020, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1868
(OG)
191803-180297 - Rehabilitation and Widening of Roads in Sub-Division Peshawar. [MA]
FR Peshawar
30-11--1 30-11--1 - 30-11--1 - 21.2 5.25 32.05 32.05 24.388 14.296 19.546 0 100% 92%
December - 2020
(Length- 2 Km) E/W , S/B ,B/C & S/Work in progess. Completion : June-2021.
No Image
1868
(OG)
191803-180297 - Rehabilitation and Widening of Roads in Sub-Division Peshawar. [MA]
FR Peshawar
30-11--1 30-11--1 - 30-11--1 - 21.2 5.25 32.05 32.05 24.388 14.296 19.546 0 100% 92%
December - 2020
(Length- 2 Km) E/W , S/B ,B/C & S/Work in progess. Completion : June-2021.
No Image
1868
(OG)
191803-180297 - Rehabilitation and Widening of Roads in Sub-Division Peshawar. [MA]
FR Peshawar
30-11--1 30-11--1 - 30-11--1 - 21.2 5.25 32.05 32.05 17.522 10 15.25 0 100% 72%
October - 2020
(Length- 2 Km) E/W , S/B ,B/C & S/Work in progess. Completion : June-2021.
No Image
1868
(OG)
191803-180297 - Rehabilitation and Widening of Roads in Sub-Division Peshawar. [MA]
FR Peshawar
30-11--1 30-11--1 - 30-11--1 - 21.2 5.25 32.05 32.05 10 10 15.25 0 100% 72%
September - 2020
(Length- 2 Km) E/W , S/B ,B/C & S/Work in progess. Completion : June-2021.
No Image
1868
(OG)
191803-180297 - Rehabilitation and Widening of Roads in Sub-Division Peshawar. [MA]
FR Peshawar
30-11--1 30-11--1 - 30-11--1 - 21.2 5.25 32.05 32.05 0 0 5.25 0 100% 25%
August - 2020
(Length- 2 Km) E/W , S/B ,B/C & S/Work in progess. Completion : June-2021.
No Image
1868
(OG)
191803-180297 - Rehabilitation and Widening of Roads in Sub-Division Peshawar. [MA]
FR Peshawar
30-11--1 30-11--1 - 30-11--1 - 32.05 0 32.05 0 0 0 0 0 -
July - 2020
No Image
1868
(OG)
191803-180297 - Rehabilitation and Widening of Roads in Sub-Division Peshawar. [MA]
FR Peshawar
30-11--1 30-11--1 - 30-11--1 - 21.2 5.25 32.05 17.522 17.522 14.296 19.546 0 100% 92%
March - 2021
(Length- 2 Km) E/W , S/B ,B/C & S/Work in progess. Completion : June-2021.
No Image
Rehabilitation and Widening of Roads in Sub-Division Peshawar.
1868
(OG)
191803-180297 - Rehabilitation and Widening of Roads in Sub-Division Peshawar. [MA]
FR Peshawar
30-11--1 30-11--1 - 30-11--1 - 21.2 5.25 32.05 17.522 17.522 14.296 19.546 0 100% 92%
February - 2021
(Length- 2 Km) E/W , S/B ,B/C & S/Work in progess. Completion : June-2021.
No Image
Rehabilitation and Widening of Roads in Sub-Division Peshawar.
1868
(OG)
191803-180297 - Rehabilitation and Widening of Roads in Sub-Division Peshawar. [MA]
FR Peshawar
30-11--1 30-11--1 - 30-11--1 - 21.2 5.25 32.05 17.522 17.522 14.296 19.546 0 100% 92%
January - 2021
(Length- 2 Km) E/W , S/B ,B/C & S/Work in progess. Completion : June-2021.
No Image
Rehabilitation and Widening of Roads in Sub-Division Peshawar.
1868
(OG)
191803-180297 - Rehabilitation and Widening of Roads in Sub-Division Peshawar. [MA]
Peshawar
30-11--1 30-11--1 - 30-11--1 - 21.2 5.25 32.05 17.522 17.522 14.296 19.546 0 100% 92%
May - 2021
(Length- 2 Km) E/W , S/B ,B/C & S/Work in progess. Road leads to area where mineral have been explored and uneven loading. Cannot be completed due to revission required to revision requiremnet.
No Image
Rehabilitation and Widening of Roads in Sub-Division Peshawar.
1868
(OG)
191803-180297 - Rehabilitation and Widening of Roads in Sub-Division Peshawar. [MA]
Peshawar
30-11--1 30-11--1 - 30-11--1 - 21.2 5.25 32.05 17.522 17.522 14.296 19.546 0 100% 92%
April - 2021
(Length- 2 Km) E/W , S/B ,B/C & S/Work in progess. Road leads to area where mineral have been explored and uneven loading. Cannot be completed due to revission required to revision requiremnet.