Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1891 (OG) |
195298-Construction of balance portion of Road from Inzar Gori khel to Ladha 20-Kms District South Waziristan (AIP) |
South Waziristan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 253.15 | 50 | 100 | 100 | 40.678 | 29.943 | 79.943 | 103.15 | 59% |
32% December - 2020 |
Length10.5 Km
E/Work in progress. |
No Image |
1891 (OG) |
195298-Construction of balance portion of Road from Inzar Gori khel to Ladha 20-Kms District South Waziristan (AIP) |
South Waziristan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 253.15 | 50 | 100 | 100 | 40.678 | 29.943 | 79.943 | 103.15 | 59% |
32% December - 2020 |
Length10.5 Km
E/Work in progress. |
No Image |
1891 (OG) |
195298-Construction of balance portion of Road from Inzar Gori khel to Ladha 20-Kms District South Waziristan (AIP) |
South Waziristan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 253.15 | 50 | 100 | 100 | 40.678 | 25 | 75 | 103.15 | 59% |
30% October - 2020 |
Length10.5 Km
E/Work in progress. |
No Image |
1891 (OG) |
195298-Construction of balance portion of Road from Inzar Gori khel to Ladha 20-Kms District South Waziristan (AIP) |
South Waziristan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 253.15 | 50 | 100 | 100 | 25 | 25 | 75 | 103.15 | 59% |
30% September - 2020 |
Length10.5 Km
E/Work in progress. |
No Image |
1891 (OG) |
195298-Construction of balance portion of Road from Inzar Gori khel to Ladha 20-Kms District South Waziristan (AIP) |
South Waziristan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 253.15 | 50 | 100 | 100 | 0 | 0 | 50 | 103.15 | 59% |
20% August - 2020 |
Work in progress. |
No Image |
1891 (OG) |
195298-Construction of balance portion of Road from Inzar Gori khel to Ladha 20-Kms District South Waziristan (AIP) |
South Waziristan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 253.15 | 50 | 100 | 40.678 | 40.678 | 29.943 | 79.943 | 103.15 | 59% |
32% May - 2021 |
Length10.5 Km
E/Work in progress. |
No Image |
1891 (OG) |
195298-Construction of balance portion of Road from Inzar Gori khel to Ladha 20-Kms District South Waziristan (AIP) |
South Waziristan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 253.15 | 50 | 100 | 40.678 | 40.678 | 29.943 | 79.943 | 103.15 | 59% |
32% April - 2021 |
Length10.5 Km
E/Work in progress. |
No Image |
1891 (OG) |
195298-Construction of balance portion of Road from Inzar Gori khel to Ladha 20-Kms District South Waziristan (AIP) |
South Waziristan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 253.15 | 50 | 100 | 40.678 | 40.678 | 29.943 | 79.943 | 103.15 | 59% |
32% March - 2021 |
Length10.5 Km
E/Work in progress. |
No Image |
1891 (OG) |
195298-Construction of balance portion of Road from Inzar Gori khel to Ladha 20-Kms District South Waziristan (AIP) |
South Waziristan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 253.15 | 50 | 100 | 40.678 | 40.678 | 29.943 | 79.943 | 103.15 | 59% |
32% February - 2021 |
Length10.5 Km
E/Work in progress. |
No Image |
1891 (OG) |
195298-Construction of balance portion of Road from Inzar Gori khel to Ladha 20-Kms District South Waziristan (AIP) |
South Waziristan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 253.15 | 50 | 100 | 40.678 | 40.678 | 29.943 | 79.943 | 103.15 | 59% |
32% January - 2021 |
Length10.5 Km
E/Work in progress. |
No Image |
1891 (OG) |
195298-Construction of balance portion of Road from Inzar Gori khel to Ladha 20-Kms District South Waziristan (AIP) |
South Wazirstan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 253.15 | 0 | 100 | 0 | 0 | 0 | 0 | 0 |
- July - 2020 |
No Image | ||
Pages : 1 |