Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1898 (OG) |
195275-Reconstruction and Rehabilitation of Khadi Village (5 km) (ER) (AIP) |
North Waziristan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 71.072 | 25 | 20 | 20 | 10.136 | 6.346 | 31.346 | 26.072 | 63% |
44% December - 2020 |
Length - 5 km - Work in progress. |
No Image |
1898 (OG) |
195275-Reconstruction and Rehabilitation of Khadi Village (5 km) (ER) (AIP) |
North Waziristan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 71.072 | 25 | 20 | 20 | 10.136 | 6.346 | 31.346 | 26.072 | 63% |
44% December - 2020 |
Length - 5 km - Work in progress. |
No Image |
1898 (OG) |
195275-Reconstruction and Rehabilitation of Khadi Village (5 km) (ER) (AIP) |
North Waziristan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 71.072 | 25 | 20 | 20 | 10.136 | 0 | 25 | 26.072 | 63% |
35% October - 2020 |
Length - 5 km - Work in progress. |
No Image |
1898 (OG) |
195275-Reconstruction and Rehabilitation of Khadi Village (5 km) (ER) (AIP) |
North Waziristan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 71.072 | 25 | 20 | 20 | 7 | 0 | 25 | 26.072 | 63% |
35% September - 2020 |
Length - 5 km - Work in progress. |
No Image |
1898 (OG) |
195275-Reconstruction and Rehabilitation of Khadi Village (5 km) (ER) (AIP) |
North Waziristan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 71.072 | 25 | 20 | 20 | 0 | 0 | 25 | 26.072 | 63% |
35% August - 2020 |
Length - 5 km - Work in progress. |
No Image |
1898 (OG) |
195275-Reconstruction and Rehabilitation of Khadi Village (5 km) (ER) (AIP) |
North Waziristan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 71.072 | 25 | 20 | 17.136 | 17.136 | 16.061 | 41.061 | 26.072 | 63% |
58% May - 2021 |
Length - 5 km - Work in progress. |
No Image |
1898 (OG) |
195275-Reconstruction and Rehabilitation of Khadi Village (5 km) (ER) (AIP) |
North Waziristan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 71.072 | 25 | 20 | 17.136 | 17.136 | 16.061 | 41.061 | 26.072 | 63% |
58% April - 2021 |
Length - 5 km - Work in progress. |
No Image |
1898 (OG) |
195275-Reconstruction and Rehabilitation of Khadi Village (5 km) (ER) (AIP) |
North Waziristan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 71.072 | 25 | 20 | 17.14 | 17.14 | 6.35 | 31.35 | 26.072 | 63% |
44% March - 2021 |
Length - 5 km - Work in progress. |
No Image |
1898 (OG) |
195275-Reconstruction and Rehabilitation of Khadi Village (5 km) (ER) (AIP) |
North Waziristan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 71.072 | 25 | 20 | 17.14 | 17.14 | 6.35 | 31.35 | 26.072 | 63% |
44% February - 2021 |
Length - 5 km - Work in progress. |
No Image |
1898 (OG) |
195275-Reconstruction and Rehabilitation of Khadi Village (5 km) (ER) (AIP) |
North Waziristan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 71.072 | 25 | 20 | 17.14 | 17.14 | 6.35 | 31.35 | 26.072 | 63% |
44% January - 2021 |
Length - 5 km - Work in progress. |
No Image |
1898 (OG) |
195275-Reconstruction and Rehabilitation of Khadi Village (5 km) (ER) (AIP) |
North Wazirstan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 71.072 | 0 | 20 | 0 | 0 | 0 | 0 | 0 |
- July - 2020 |
No Image | ||