195263-Construction of Road from Chakai Kalai to Sakhi Ahmad Shah Killi (Thall Parachinar Main Road) Lower Kurram (2.0-KMs) (FMR) (AIP) |
Kurram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 62.691 | 0 | 25 | 0 | 0 | 0 | 0 | 0 |
- July - 2020 |
No Image | ||
1903 (OG) |
195263-Construction of Road from Chakai Kalai to Sakhi Ahmad Shah Killi (Thall Parachinar Main Road) Lower Kurram (2.0-KMs) (FMR) (AIP) |
Kurram HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 62.357 | 3.12 | 25 | 13.92 | 13.92 | 0 | 3.12 | 34.237 | 45% |
5% December - 2020 |
Work in progress. |
No Image |
1903 (OG) |
195263-Construction of Road from Chakai Kalai to Sakhi Ahmad Shah Killi (Thall Parachinar Main Road) Lower Kurram (2.0-KMs) (FMR) (AIP) |
Kurram HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 62.357 | 3.12 | 25 | 13.92 | 13.92 | 0 | 3.12 | 34.237 | 45% |
5% December - 2020 |
Work in progress. |
No Image |
1903 (OG) |
195263-Construction of Road from Chakai Kalai to Sakhi Ahmad Shah Killi (Thall Parachinar Main Road) Lower Kurram (2.0-KMs) (FMR) (AIP) |
Kurram HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 62.357 | 3.12 | 25 | 25 | 10 | 0 | 3.12 | 34.237 | 45% |
5% October - 2020 |
Work in progress. |
No Image |
1903 (OG) |
195263-Construction of Road from Chakai Kalai to Sakhi Ahmad Shah Killi (Thall Parachinar Main Road) Lower Kurram (2.0-KMs) (FMR) (AIP) |
Kurram HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 62.357 | 3.12 | 25 | 25 | 10 | 0 | 3.12 | 34.237 | 45% |
5% September - 2020 |
Work in progress. |
No Image |
1903 (OG) |
195263-Construction of Road from Chakai Kalai to Sakhi Ahmad Shah Killi (Thall Parachinar Main Road) Lower Kurram (2.0-KMs) (FMR) (AIP) |
Kurram HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 62.357 | 3.12 | 25 | 25 | 10 | 0 | 3.12 | 34.237 | 45% |
5% August - 2020 |
Work in progress. |
No Image |
1903 (OG) |
195263-Construction of Road from Chakai Kalai to Sakhi Ahmad Shah Killi (Thall Parachinar Main Road) Lower Kurram (2.0-KMs) (FMR) (AIP) |
Kurram HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 62.357 | 3.12 | 25 | 13.92 | 13.92 | 0 | 3.12 | 34.237 | 45% |
5% May - 2021 |
Work in progress. |
No Image |
1903 (OG) |
195263-Construction of Road from Chakai Kalai to Sakhi Ahmad Shah Killi (Thall Parachinar Main Road) Lower Kurram (2.0-KMs) (FMR) (AIP) |
Kurram HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 62.357 | 3.12 | 25 | 13.92 | 13.92 | 0 | 3.12 | 34.237 | 45% |
5% April - 2021 |
Work in progress. |
No Image |
1903 (OG) |
195263-Construction of Road from Chakai Kalai to Sakhi Ahmad Shah Killi (Thall Parachinar Main Road) Lower Kurram (2.0-KMs) (FMR) (AIP) |
Kurram HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 62.357 | 3.12 | 25 | 13.92 | 13.92 | 0 | 3.12 | 34.237 | 45% |
5% March - 2021 |
Work in progress. |
No Image |
1903 (OG) |
195263-Construction of Road from Chakai Kalai to Sakhi Ahmad Shah Killi (Thall Parachinar Main Road) Lower Kurram (2.0-KMs) (FMR) (AIP) |
Kurram HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 62.357 | 3.12 | 25 | 13.92 | 13.92 | 0 | 3.12 | 34.237 | 45% |
5% February - 2021 |
Work in progress. |
No Image |
1903 (OG) |
195263-Construction of Road from Chakai Kalai to Sakhi Ahmad Shah Killi (Thall Parachinar Main Road) Lower Kurram (2.0-KMs) (FMR) (AIP) |
Kurram HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 62.357 | 3.12 | 25 | 13.92 | 13.92 | 0 | 3.12 | 34.237 | 45% |
5% January - 2021 |
Work in progress. |
No Image |