Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1914 (OG) |
195247-Construction of B/Topped Road from Mastak Bridge to Shadally via Methra in Tribal District, Khyber (28-KMs) Khyber (FMR) (AIP) |
Khyber |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 934.418 | 206 | 200 | 0 | 0 | 0 | 206 | 528.418 | 43% |
22% July - 2020 |
Earth work & Road work in progress. |
No Image |
1914 (OG) |
195247-Construction of B/Topped Road from Mastak Bridge to Shadally via Methra in Tribal District, Khyber (28-KMs) Khyber (FMR) (AIP) |
Khyber HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 934.418 | 206 | 200 | 200 | 91.357 | 25.483 | 231.483 | 528.418 | 43% |
25% December - 2020 |
03- Packages
Package-1 E/Work 75%, Road Work 15% & S/Work 30% Completed.
Package-II E/Work 33% Road work 11% , S/Work 2% completed.
Package-III E/Work 83% Road work 11% completed. |
No Image |
1914 (OG) |
195247-Construction of B/Topped Road from Mastak Bridge to Shadally via Methra in Tribal District, Khyber (28-KMs) Khyber (FMR) (AIP) |
Khyber HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 934.418 | 206 | 200 | 200 | 91.357 | 25.483 | 231.483 | 528.418 | 43% |
25% December - 2020 |
03- Packages
Package-1 E/Work 75%, Road Work 15% & S/Work 30% Completed.
Package-II E/Work 33% Road work 11% , S/Work 2% completed.
Package-III E/Work 83% Road work 11% completed. |
No Image |
1914 (OG) |
195247-Construction of B/Topped Road from Mastak Bridge to Shadally via Methra in Tribal District, Khyber (28-KMs) Khyber (FMR) (AIP) |
Khyber HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 934.418 | 206 | 200 | 200 | 60 | 0 | 206 | 528.418 | 43% |
22% October - 2020 |
03- Packages
Package-1 E/Work 75%, Road Work 15% & S/Work 30% Completed.
Package-II E/Work 33% Road work 11% , S/Work 2% completed.
Package-III E/Work 83% Road work 11% completed. |
No Image |
1914 (OG) |
195247-Construction of B/Topped Road from Mastak Bridge to Shadally via Methra in Tribal District, Khyber (28-KMs) Khyber (FMR) (AIP) |
Khyber HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 934.418 | 206 | 200 | 200 | 60 | 0 | 206 | 528.418 | 43% |
22% September - 2020 |
03- Packages
Package-1 E/Work 75%, Road Work 15% & S/Work 30% Completed.
Package-II E/Work 33% Road work 11% , S/Work 2% completed.
Package-III E/Work 83% Road work 11% completed. |
No Image |
1914 (OG) |
195247-Construction of B/Topped Road from Mastak Bridge to Shadally via Methra in Tribal District, Khyber (28-KMs) Khyber (FMR) (AIP) |
Khyber HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 934.418 | 206 | 200 | 200 | 60 | 0 | 206 | 528.418 | 43% |
22% August - 2020 |
Earth work & Road work in progress. |
No Image |
1914 (OG) |
195247-Construction of B/Topped Road from Mastak Bridge to Shadally via Methra in Tribal District, Khyber (28-KMs) Khyber (FMR) (AIP) |
Khyber HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 934.418 | 206 | 200 | 91.357 | 91.357 | 91.357 | 297.357 | 528.418 | 43% |
32% May - 2021 |
03- Packages
Package-1 E/Work 75%, Road Work 15% & S/Work 30% Completed.
Package-II E/Work 33% Road work 11% , S/Work 2% completed.
Package-III E/Work 83% Road work 11% completed. |
No Image |
1914 (OG) |
195247-Construction of B/Topped Road from Mastak Bridge to Shadally via Methra in Tribal District, Khyber (28-KMs) Khyber (FMR) (AIP) |
Khyber HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 934.418 | 206 | 200 | 91.357 | 91.357 | 91.357 | 297.357 | 528.418 | 43% |
32% April - 2021 |
03- Packages
Package-1 E/Work 75%, Road Work 15% & S/Work 30% Completed.
Package-II E/Work 33% Road work 11% , S/Work 2% completed.
Package-III E/Work 83% Road work 11% completed. |
No Image |
1914 (OG) |
195247-Construction of B/Topped Road from Mastak Bridge to Shadally via Methra in Tribal District, Khyber (28-KMs) Khyber (FMR) (AIP) |
Khyber HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 934.418 | 206 | 200 | 91.357 | 91.357 | 71.027 | 277.027 | 528.418 | 43% |
30% March - 2021 |
03- Packages
Package-1 E/Work 75%, Road Work 15% & S/Work 30% Completed.
Package-II E/Work 33% Road work 11% , S/Work 2% completed.
Package-III E/Work 83% Road work 11% completed. |
No Image |
1914 (OG) |
195247-Construction of B/Topped Road from Mastak Bridge to Shadally via Methra in Tribal District, Khyber (28-KMs) Khyber (FMR) (AIP) |
Khyber HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 934.418 | 206 | 200 | 91.357 | 91.357 | 71.027 | 277.027 | 528.418 | 43% |
30% February - 2021 |
03- Packages
Package-1 E/Work 75%, Road Work 15% & S/Work 30% Completed.
Package-II E/Work 33% Road work 11% , S/Work 2% completed.
Package-III E/Work 83% Road work 11% completed. |
No Image |
1914 (OG) |
195247-Construction of B/Topped Road from Mastak Bridge to Shadally via Methra in Tribal District, Khyber (28-KMs) Khyber (FMR) (AIP) |
Khyber HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 934.418 | 206 | 200 | 91.357 | 91.357 | 25.483 | 231.483 | 528.418 | 43% |
25% January - 2021 |
03- Packages
Package-1 E/Work 75%, Road Work 15% & S/Work 30% Completed.
Package-II E/Work 33% Road work 11% , S/Work 2% completed.
Package-III E/Work 83% Road work 11% completed. |
No Image |
Pages : 1 |