Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1915 (OG) |
195248-Construction BTR road from Mashoo Mela to Jarando Killi Sher Khel (16-KMs) Bara Sub Division Khyber (FMR) (AIP) |
Khyber |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 400 | 44 | 100 | 0 | 0 | 0 | 44 | 256 | 36% |
11% July - 2020 |
Earth work, Road work and Structure work in progress. |
No Image |
1915 (OG) |
195248-Construction BTR road from Mashoo Mela to Jarando Killi Sher Khel (16-KMs) Bara Sub Division Khyber (FMR) (AIP) |
Khyber HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 400 | 44 | 100 | 100 | 68.678 | 64.645 | 108.645 | 256 | 36% |
27% December - 2020 |
E/Work 70% Road work 40% , S/Work 47% in progress. |
No Image |
1915 (OG) |
195248-Construction BTR road from Mashoo Mela to Jarando Killi Sher Khel (16-KMs) Bara Sub Division Khyber (FMR) (AIP) |
Khyber HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 400 | 44 | 100 | 100 | 68.678 | 64.645 | 108.645 | 256 | 36% |
27% December - 2020 |
E/Work 70% Road work 40% , S/Work 47% in progress. |
No Image |
1915 (OG) |
195248-Construction BTR road from Mashoo Mela to Jarando Killi Sher Khel (16-KMs) Bara Sub Division Khyber (FMR) (AIP) |
Khyber HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 400 | 44 | 100 | 100 | 25 | 25 | 69 | 256 | 36% |
17% October - 2020 |
E/Work 70% Road work 40% , S/Work 47% in progress. |
No Image |
1915 (OG) |
195248-Construction BTR road from Mashoo Mela to Jarando Killi Sher Khel (16-KMs) Bara Sub Division Khyber (FMR) (AIP) |
Khyber HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 400 | 44 | 100 | 100 | 25 | 0 | 44 | 256 | 36% |
11% September - 2020 |
E/Work 70% Road work 40% , S/Work 47% in progress. |
No Image |
1915 (OG) |
195248-Construction BTR road from Mashoo Mela to Jarando Killi Sher Khel (16-KMs) Bara Sub Division Khyber (FMR) (AIP) |
Khyber HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 400 | 44 | 100 | 100 | 10 | 0 | 44 | 256 | 36% |
11% August - 2020 |
Earth work, Road work and Structure work in progress. |
No Image |
1915 (OG) |
195248-Construction BTR road from Mashoo Mela to Jarando Killi Sher Khel (16-KMs) Bara Sub Division Khyber (FMR) (AIP) |
Khyber HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 400 | 44 | 100 | 68.654 | 68.654 | 68.654 | 112.654 | 256 | 36% |
28% May - 2021 |
E/Work 70% Road work 40% , S/Work 47% in progress. |
No Image |
1915 (OG) |
195248-Construction BTR road from Mashoo Mela to Jarando Killi Sher Khel (16-KMs) Bara Sub Division Khyber (FMR) (AIP) |
Khyber HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 400 | 44 | 100 | 68.654 | 68.654 | 68.654 | 112.654 | 256 | 36% |
28% April - 2021 |
E/Work 70% Road work 40% , S/Work 47% in progress. |
No Image |
1915 (OG) |
195248-Construction BTR road from Mashoo Mela to Jarando Killi Sher Khel (16-KMs) Bara Sub Division Khyber (FMR) (AIP) |
Khyber HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 400 | 44 | 100 | 68.654 | 68.654 | 68.654 | 112.654 | 256 | 36% |
28% March - 2021 |
E/Work 70% Road work 40% , S/Work 47% in progress. |
No Image |
1915 (OG) |
195248-Construction BTR road from Mashoo Mela to Jarando Killi Sher Khel (16-KMs) Bara Sub Division Khyber (FMR) (AIP) |
Khyber HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 400 | 44 | 100 | 68.654 | 68.654 | 68.654 | 112.654 | 256 | 36% |
28% February - 2021 |
E/Work 70% Road work 40% , S/Work 47% in progress. |
No Image |
1915 (OG) |
195248-Construction BTR road from Mashoo Mela to Jarando Killi Sher Khel (16-KMs) Bara Sub Division Khyber (FMR) (AIP) |
Khyber HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 400 | 44 | 100 | 64.645 | 64.645 | 64.645 | 108.645 | 256 | 36% |
27% January - 2021 |
E/Work 70% Road work 40% , S/Work 47% in progress. |
No Image |
Pages : 1 |