Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1915
(OG)
195248-Construction BTR road from Mashoo Mela to Jarando Killi Sher Khel (16-KMs) Bara Sub Division Khyber (FMR) (AIP)
Khyber
30-11--1 30-11--1 - 30-11--1 - 400 44 100 0 0 0 44 256 36% 11%
July - 2020
Earth work, Road work and Structure work in progress.
No Image
1915
(OG)
195248-Construction BTR road from Mashoo Mela to Jarando Killi Sher Khel (16-KMs) Bara Sub Division Khyber (FMR) (AIP)
Khyber
HW
30-11--1 30-11--1 - 30-11--1 - 400 44 100 100 68.678 64.645 108.645 256 36% 27%
December - 2020
E/Work 70% Road work 40% , S/Work 47% in progress.
No Image
1915
(OG)
195248-Construction BTR road from Mashoo Mela to Jarando Killi Sher Khel (16-KMs) Bara Sub Division Khyber (FMR) (AIP)
Khyber
HW
30-11--1 30-11--1 - 30-11--1 - 400 44 100 100 68.678 64.645 108.645 256 36% 27%
December - 2020
E/Work 70% Road work 40% , S/Work 47% in progress.
No Image
1915
(OG)
195248-Construction BTR road from Mashoo Mela to Jarando Killi Sher Khel (16-KMs) Bara Sub Division Khyber (FMR) (AIP)
Khyber
HW
30-11--1 30-11--1 - 30-11--1 - 400 44 100 100 25 25 69 256 36% 17%
October - 2020
E/Work 70% Road work 40% , S/Work 47% in progress.
No Image
1915
(OG)
195248-Construction BTR road from Mashoo Mela to Jarando Killi Sher Khel (16-KMs) Bara Sub Division Khyber (FMR) (AIP)
Khyber
HW
30-11--1 30-11--1 - 30-11--1 - 400 44 100 100 25 0 44 256 36% 11%
September - 2020
E/Work 70% Road work 40% , S/Work 47% in progress.
No Image
1915
(OG)
195248-Construction BTR road from Mashoo Mela to Jarando Killi Sher Khel (16-KMs) Bara Sub Division Khyber (FMR) (AIP)
Khyber
HW
30-11--1 30-11--1 - 30-11--1 - 400 44 100 100 10 0 44 256 36% 11%
August - 2020
Earth work, Road work and Structure work in progress.
No Image
1915
(OG)
195248-Construction BTR road from Mashoo Mela to Jarando Killi Sher Khel (16-KMs) Bara Sub Division Khyber (FMR) (AIP)
Khyber
HW
30-11--1 30-11--1 - 30-11--1 - 400 44 100 68.654 68.654 68.654 112.654 256 36% 28%
May - 2021
E/Work 70% Road work 40% , S/Work 47% in progress.
No Image
1915
(OG)
195248-Construction BTR road from Mashoo Mela to Jarando Killi Sher Khel (16-KMs) Bara Sub Division Khyber (FMR) (AIP)
Khyber
HW
30-11--1 30-11--1 - 30-11--1 - 400 44 100 68.654 68.654 68.654 112.654 256 36% 28%
April - 2021
E/Work 70% Road work 40% , S/Work 47% in progress.
No Image
1915
(OG)
195248-Construction BTR road from Mashoo Mela to Jarando Killi Sher Khel (16-KMs) Bara Sub Division Khyber (FMR) (AIP)
Khyber
HW
30-11--1 30-11--1 - 30-11--1 - 400 44 100 68.654 68.654 68.654 112.654 256 36% 28%
March - 2021
E/Work 70% Road work 40% , S/Work 47% in progress.
No Image
1915
(OG)
195248-Construction BTR road from Mashoo Mela to Jarando Killi Sher Khel (16-KMs) Bara Sub Division Khyber (FMR) (AIP)
Khyber
HW
30-11--1 30-11--1 - 30-11--1 - 400 44 100 68.654 68.654 68.654 112.654 256 36% 28%
February - 2021
E/Work 70% Road work 40% , S/Work 47% in progress.
No Image
1915
(OG)
195248-Construction BTR road from Mashoo Mela to Jarando Killi Sher Khel (16-KMs) Bara Sub Division Khyber (FMR) (AIP)
Khyber
HW
30-11--1 30-11--1 - 30-11--1 - 400 44 100 64.645 64.645 64.645 108.645 256 36% 27%
January - 2021
E/Work 70% Road work 40% , S/Work 47% in progress.
No Image