Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1926 (OG) |
195260-Construction and B/Topping of Tang Khata Dherai Road (02-KMs) Bajaur (FMR) (AIP) |
Bajaur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 46.249 | 0 | 15 | 0 | 0 | 0 | 0 | 31.249 | 32% |
- July - 2020 |
Work in progress. |
No Image |
1926 (OG) |
195260-Construction and B/Topping of Tang Khata Dherai Road (02-KMs) Bajaur (FMR) (AIP) |
Bajaur HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 46.249 | 25 | 15 | 15 | 7.352 | 0 | 25 | 6.249 | 86% |
54% December - 2020 |
Earth work & S/work in progress. |
No Image |
1926 (OG) |
195260-Construction and B/Topping of Tang Khata Dherai Road (02-KMs) Bajaur (FMR) (AIP) |
Bajaur HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 46.249 | 25 | 15 | 15 | 7.352 | 0 | 25 | 6.249 | 86% |
54% December - 2020 |
Earth work & S/work in progress. |
No Image |
1926 (OG) |
195260-Construction and B/Topping of Tang Khata Dherai Road (02-KMs) Bajaur (FMR) (AIP) |
Bajaur HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 46.249 | 25 | 15 | 15 | 5 | 0 | 25 | 6.249 | 86% |
54% October - 2020 |
Earth work & S/work in progress. |
No Image |
1926 (OG) |
195260-Construction and B/Topping of Tang Khata Dherai Road (02-KMs) Bajaur (FMR) (AIP) |
Bajaur HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 46.249 | 25 | 15 | 15 | 5 | 0 | 25 | 6.249 | 86% |
54% September - 2020 |
Earth work & S/work in progress. |
No Image |
1926 (OG) |
195260-Construction and B/Topping of Tang Khata Dherai Road (02-KMs) Bajaur (FMR) (AIP) |
Bajaur HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 46.249 | 25 | 15 | 15 | 0 | 0 | 25 | 6.249 | 86% |
54% August - 2020 |
Earth work in progress. |
No Image |
1926 (OG) |
195260-Construction and B/Topping of Tang Khata Dherai Road (02-KMs) Bajaur (FMR) (AIP) |
Bajaur HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 46.249 | 25 | 15 | 7.352 | 7.352 | 0 | 25 | 6.249 | 86% |
54% May - 2021 |
Earth work & S/work in progress. |
No Image |
1926 (OG) |
195260-Construction and B/Topping of Tang Khata Dherai Road (02-KMs) Bajaur (FMR) (AIP) |
Bajaur HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 46.249 | 25 | 15 | 7.352 | 7.352 | 0 | 25 | 6.249 | 86% |
54% April - 2021 |
Earth work & S/work in progress. |
No Image |
1926 (OG) |
195260-Construction and B/Topping of Tang Khata Dherai Road (02-KMs) Bajaur (FMR) (AIP) |
Bajaur HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 46.249 | 25 | 15 | 7.352 | 7.352 | 0 | 25 | 6.249 | 86% |
54% March - 2021 |
Earth work & S/work in progress. |
No Image |
1926 (OG) |
195260-Construction and B/Topping of Tang Khata Dherai Road (02-KMs) Bajaur (FMR) (AIP) |
Bajaur HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 46.249 | 25 | 15 | 7.352 | 7.352 | 0 | 25 | 6.249 | 86% |
54% February - 2021 |
Earth work & S/work in progress. |
No Image |
1926 (OG) |
195260-Construction and B/Topping of Tang Khata Dherai Road (02-KMs) Bajaur (FMR) (AIP) |
Bajaur HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 46.249 | 25 | 15 | 7.352 | 7.352 | 0 | 25 | 6.249 | 86% |
54% January - 2021 |
Earth work & S/work in progress. |
No Image |
Pages : 1 |