Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2021, February - 2021, March - 2021, April - 2021, May - 2021, July - 2020, August - 2020, September - 2020, October - 2020, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1929
(OG)
195295-Improvement of road from Khar to Timergara and Toor Ghundi-Khar Road, 37.845 Km. (AIP)
Bajaur
30-11--1 30-11--1 - 30-11--1 - 3583.58 0 1000 0 0 0 0 0 -
July - 2020
No Image
1929
(OG)
195295-Improvement of road from Khar to Timergara and Toor Ghundi-Khar Road, 37.845 Km. (AIP)
Bajaur
PKHA
30-11--1 30-11--1 - 30-11--1 - 2583.38 0 1000 1000 1000 578.5 578.5 1583.38 39% 22%
December - 2020
Shifted to Pak Army.
No Image
1929
(OG)
195295-Improvement of road from Khar to Timergara and Toor Ghundi-Khar Road, 37.845 Km. (AIP)
Bajaur
PKHA
30-11--1 30-11--1 - 30-11--1 - 2583.38 0 1000 1000 1000 578.5 578.5 1583.38 39% 22%
December - 2020
Shifted to Pak Army.
No Image
1929
(OG)
195295-Improvement of road from Khar to Timergara and Toor Ghundi-Khar Road, 37.845 Km. (AIP)
Bajaur
PKHA
30-11--1 30-11--1 - 30-11--1 - 2583.38 0 1000 1000 0 0 0 1583.38 39% -
October - 2020
Shifted to Pak Army.
No Image
1929
(OG)
195295-Improvement of road from Khar to Timergara and Toor Ghundi-Khar Road, 37.845 Km. (AIP)
Bajaur
PKHA
30-11--1 30-11--1 - 30-11--1 - 2583.38 0 1000 1000 0 0 0 1583.38 39% -
September - 2020
Shifted to Pak Army.
No Image
1929
(OG)
195295-Improvement of road from Khar to Timergara and Toor Ghundi-Khar Road, 37.845 Km. (AIP)
Bajaur
PKHA
30-11--1 30-11--1 - 30-11--1 - 2583.38 0 1000 1000 0 0 0 1583.38 39% -
August - 2020
Shifted to Pak Army.
No Image
1929
(OG)
195295-Improvement of road from Khar to Timergara and Toor Ghundi-Khar Road, 37.845 Km. (AIP)
Bajaur
PKHA
30-11--1 30-11--1 - 30-11--1 - 2583.38 0 1000 1000 1000 1000 1000 1583.38 39% 39%
May - 2021
Shifted to Pak Army.
No Image
1929
(OG)
195295-Improvement of road from Khar to Timergara and Toor Ghundi-Khar Road, 37.845 Km. (AIP)
Bajaur
PKHA
30-11--1 30-11--1 - 30-11--1 - 2583.38 0 1000 1000 1000 1000 1000 1583.38 39% 39%
April - 2021
Shifted to Pak Army.
No Image
1929
(OG)
195295-Improvement of road from Khar to Timergara and Toor Ghundi-Khar Road, 37.845 Km. (AIP)
Bajaur
PKHA
30-11--1 30-11--1 - 30-11--1 - 2583.38 0 1000 1000 1000 578.5 578.5 1583.38 39% 22%
March - 2021
Shifted to Pak Army.
No Image
1929
(OG)
195295-Improvement of road from Khar to Timergara and Toor Ghundi-Khar Road, 37.845 Km. (AIP)
Bajaur
PKHA
30-11--1 30-11--1 - 30-11--1 - 2583.38 0 1000 1000 1000 578.5 578.5 1583.38 39% 22%
February - 2021
Shifted to Pak Army.
No Image
1929
(OG)
195295-Improvement of road from Khar to Timergara and Toor Ghundi-Khar Road, 37.845 Km. (AIP)
Bajaur
PKHA
30-11--1 30-11--1 - 30-11--1 - 2583.38 0 1000 1000 1000 578.5 578.5 1583.38 39% 22%
January - 2021
Shifted to Pak Army.
No Image
Pages : 1