Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1929 (OG) |
195295-Improvement of road from Khar to Timergara and Toor Ghundi-Khar Road, 37.845 Km. (AIP) |
Bajaur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 3583.58 | 0 | 1000 | 0 | 0 | 0 | 0 | 0 |
- July - 2020 |
No Image | ||
1929 (OG) |
195295-Improvement of road from Khar to Timergara and Toor Ghundi-Khar Road, 37.845 Km. (AIP) |
Bajaur PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2583.38 | 0 | 1000 | 1000 | 1000 | 578.5 | 578.5 | 1583.38 | 39% |
22% December - 2020 |
Shifted to Pak Army. |
No Image |
1929 (OG) |
195295-Improvement of road from Khar to Timergara and Toor Ghundi-Khar Road, 37.845 Km. (AIP) |
Bajaur PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2583.38 | 0 | 1000 | 1000 | 1000 | 578.5 | 578.5 | 1583.38 | 39% |
22% December - 2020 |
Shifted to Pak Army. |
No Image |
1929 (OG) |
195295-Improvement of road from Khar to Timergara and Toor Ghundi-Khar Road, 37.845 Km. (AIP) |
Bajaur PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2583.38 | 0 | 1000 | 1000 | 0 | 0 | 0 | 1583.38 | 39% |
- October - 2020 |
Shifted to Pak Army. |
No Image |
1929 (OG) |
195295-Improvement of road from Khar to Timergara and Toor Ghundi-Khar Road, 37.845 Km. (AIP) |
Bajaur PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2583.38 | 0 | 1000 | 1000 | 0 | 0 | 0 | 1583.38 | 39% |
- September - 2020 |
Shifted to Pak Army. |
No Image |
1929 (OG) |
195295-Improvement of road from Khar to Timergara and Toor Ghundi-Khar Road, 37.845 Km. (AIP) |
Bajaur PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2583.38 | 0 | 1000 | 1000 | 0 | 0 | 0 | 1583.38 | 39% |
- August - 2020 |
Shifted to Pak Army. |
No Image |
1929 (OG) |
195295-Improvement of road from Khar to Timergara and Toor Ghundi-Khar Road, 37.845 Km. (AIP) |
Bajaur PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2583.38 | 0 | 1000 | 1000 | 1000 | 1000 | 1000 | 1583.38 | 39% |
39% May - 2021 |
Shifted to Pak Army. |
No Image |
1929 (OG) |
195295-Improvement of road from Khar to Timergara and Toor Ghundi-Khar Road, 37.845 Km. (AIP) |
Bajaur PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2583.38 | 0 | 1000 | 1000 | 1000 | 1000 | 1000 | 1583.38 | 39% |
39% April - 2021 |
Shifted to Pak Army. |
No Image |
1929 (OG) |
195295-Improvement of road from Khar to Timergara and Toor Ghundi-Khar Road, 37.845 Km. (AIP) |
Bajaur PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2583.38 | 0 | 1000 | 1000 | 1000 | 578.5 | 578.5 | 1583.38 | 39% |
22% March - 2021 |
Shifted to Pak Army. |
No Image |
1929 (OG) |
195295-Improvement of road from Khar to Timergara and Toor Ghundi-Khar Road, 37.845 Km. (AIP) |
Bajaur PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2583.38 | 0 | 1000 | 1000 | 1000 | 578.5 | 578.5 | 1583.38 | 39% |
22% February - 2021 |
Shifted to Pak Army. |
No Image |
1929 (OG) |
195295-Improvement of road from Khar to Timergara and Toor Ghundi-Khar Road, 37.845 Km. (AIP) |
Bajaur PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2583.38 | 0 | 1000 | 1000 | 1000 | 578.5 | 578.5 | 1583.38 | 39% |
22% January - 2021 |
Shifted to Pak Army. |
No Image |