Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2021, February - 2021, March - 2021, April - 2021, May - 2021, July - 2020, August - 2020, September - 2020, October - 2020, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1941
(OG)
195288-Reh. & Improv. of Existing Road B/T road from Abbas Chowk to Tunnel Dara (ER) (AIP)
FR Kohat
30-11--1 30-11--1 - 30-11--1 - 226.189 0 100 100 82.203 0 0 126.189 44% -
December - 2020
Work in progress
No Image
1941
(OG)
195288-Reh. & Improv. of Existing Road B/T road from Abbas Chowk to Tunnel Dara (ER) (AIP)
FR Kohat
30-11--1 30-11--1 - 30-11--1 - 226.189 0 100 100 82.203 0 0 126.189 44% -
December - 2020
Work in progress
No Image
1941
(OG)
195288-Reh. & Improv. of Existing Road B/T road from Abbas Chowk to Tunnel Dara (ER) (AIP)
FR Kohat
30-11--1 30-11--1 - 30-11--1 - 226.189 0 100 100 40.678 0 0 126.189 44% -
October - 2020
joint survey complted
No Image
1941
(OG)
195288-Reh. & Improv. of Existing Road B/T road from Abbas Chowk to Tunnel Dara (ER) (AIP)
FR Kohat
30-11--1 30-11--1 - 30-11--1 - 226.189 0 100 100 25 0 0 126.189 44% -
September - 2020
joint survey complted
No Image
1941
(OG)
195288-Reh. & Improv. of Existing Road B/T road from Abbas Chowk to Tunnel Dara (ER) (AIP)
FR Kohat
30-11--1 30-11--1 - 30-11--1 - 226.189 0 100 100 0 0 0 126.189 44% -
August - 2020
procurement under processs.
No Image
1941
(OG)
195288-Reh. & Improv. of Existing Road B/T road from Abbas Chowk to Tunnel Dara (ER) (AIP)
FR Kohat
30-11--1 30-11--1 - 30-11--1 - 226.189 0 100 0 0 0 0 126.189 44% -
July - 2020
procurement under processs.
No Image
1941
(OG)
195288-Reh. & Improv. of Existing Road B/T road from Abbas Chowk to Tunnel Dara (ER) (AIP)
FR Kohat
30-11--1 30-11--1 - 30-11--1 - 226.189 0 100 82.203 82.203 5.441 5.441 126.189 44% 2%
March - 2021
Work in progress
No Image
Abbas Chowk to Tunnel Dara 6.40 KM FR Kohat
1941
(OG)
195288-Reh. & Improv. of Existing Road B/T road from Abbas Chowk to Tunnel Dara (ER) (AIP)
FR Kohat
30-11--1 30-11--1 - 30-11--1 - 226.189 0 100 82.203 82.203 5.441 5.441 126.189 44% 2%
February - 2021
Work in progress
No Image
Abbas Chowk to Tunnel Dara 6.40 KM FR Kohat
1941
(OG)
195288-Reh. & Improv. of Existing Road B/T road from Abbas Chowk to Tunnel Dara (ER) (AIP)
FR Kohat
30-11--1 30-11--1 - 30-11--1 - 226.189 0 100 82.203 82.203 0 0 126.189 44% -
January - 2021
Work in progress
No Image
Abbas Chowk to Tunnel Dara 6.40 KM FR Kohat
1941
(OG)
195288-Reh. & Improv. of Existing Road B/T road from Abbas Chowk to Tunnel Dara (ER) (AIP)
Kohat
HW
30-11--1 30-11--1 - 30-11--1 - 226.189 0 100 82.203 82.203 31.217 31.217 126.189 44% 14%
May - 2021
Work in progress
No Image
Abbas Chowk to Tunnel Dara 6.40 KM FR Kohat
1941
(OG)
195288-Reh. & Improv. of Existing Road B/T road from Abbas Chowk to Tunnel Dara (ER) (AIP)
Kohat
HW
30-11--1 30-11--1 - 30-11--1 - 226.189 0 100 82.203 82.203 31.217 31.217 126.189 44% 14%
April - 2021
Work in progress
No Image
Abbas Chowk to Tunnel Dara 6.40 KM FR Kohat
Pages : 1