Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1941 (OG) |
195288-Reh. & Improv. of Existing Road B/T road from Abbas Chowk to Tunnel Dara (ER) (AIP) |
FR Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 226.189 | 0 | 100 | 100 | 82.203 | 0 | 0 | 126.189 | 44% |
- December - 2020 |
Work in progress |
No Image |
1941 (OG) |
195288-Reh. & Improv. of Existing Road B/T road from Abbas Chowk to Tunnel Dara (ER) (AIP) |
FR Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 226.189 | 0 | 100 | 100 | 82.203 | 0 | 0 | 126.189 | 44% |
- December - 2020 |
Work in progress |
No Image |
1941 (OG) |
195288-Reh. & Improv. of Existing Road B/T road from Abbas Chowk to Tunnel Dara (ER) (AIP) |
FR Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 226.189 | 0 | 100 | 100 | 40.678 | 0 | 0 | 126.189 | 44% |
- October - 2020 |
joint survey complted |
No Image |
1941 (OG) |
195288-Reh. & Improv. of Existing Road B/T road from Abbas Chowk to Tunnel Dara (ER) (AIP) |
FR Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 226.189 | 0 | 100 | 100 | 25 | 0 | 0 | 126.189 | 44% |
- September - 2020 |
joint survey complted |
No Image |
1941 (OG) |
195288-Reh. & Improv. of Existing Road B/T road from Abbas Chowk to Tunnel Dara (ER) (AIP) |
FR Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 226.189 | 0 | 100 | 100 | 0 | 0 | 0 | 126.189 | 44% |
- August - 2020 |
procurement under processs. |
No Image |
1941 (OG) |
195288-Reh. & Improv. of Existing Road B/T road from Abbas Chowk to Tunnel Dara (ER) (AIP) |
FR Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 226.189 | 0 | 100 | 0 | 0 | 0 | 0 | 126.189 | 44% |
- July - 2020 |
procurement under processs. |
No Image |
1941 (OG) |
195288-Reh. & Improv. of Existing Road B/T road from Abbas Chowk to Tunnel Dara (ER) (AIP) |
FR Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 226.189 | 0 | 100 | 82.203 | 82.203 | 5.441 | 5.441 | 126.189 | 44% |
2% March - 2021 |
Work in progress |
No Image |
Abbas Chowk to Tunnel Dara 6.40 KM FR Kohat | |||||||||||||||||||
1941 (OG) |
195288-Reh. & Improv. of Existing Road B/T road from Abbas Chowk to Tunnel Dara (ER) (AIP) |
FR Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 226.189 | 0 | 100 | 82.203 | 82.203 | 5.441 | 5.441 | 126.189 | 44% |
2% February - 2021 |
Work in progress |
No Image |
Abbas Chowk to Tunnel Dara 6.40 KM FR Kohat | |||||||||||||||||||
1941 (OG) |
195288-Reh. & Improv. of Existing Road B/T road from Abbas Chowk to Tunnel Dara (ER) (AIP) |
FR Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 226.189 | 0 | 100 | 82.203 | 82.203 | 0 | 0 | 126.189 | 44% |
- January - 2021 |
Work in progress |
No Image |
Abbas Chowk to Tunnel Dara 6.40 KM FR Kohat | |||||||||||||||||||
1941 (OG) |
195288-Reh. & Improv. of Existing Road B/T road from Abbas Chowk to Tunnel Dara (ER) (AIP) |
Kohat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 226.189 | 0 | 100 | 82.203 | 82.203 | 31.217 | 31.217 | 126.189 | 44% |
14% May - 2021 |
Work in progress |
No Image |
Abbas Chowk to Tunnel Dara 6.40 KM FR Kohat | |||||||||||||||||||
1941 (OG) |
195288-Reh. & Improv. of Existing Road B/T road from Abbas Chowk to Tunnel Dara (ER) (AIP) |
Kohat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 226.189 | 0 | 100 | 82.203 | 82.203 | 31.217 | 31.217 | 126.189 | 44% |
14% April - 2021 |
Work in progress |
No Image |
Abbas Chowk to Tunnel Dara 6.40 KM FR Kohat | |||||||||||||||||||
Pages : 1 |