Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
2009 (OG) |
150751-Feasibility and improvement/construction of Arbab Niaz Cricket Stadium Peshawar. |
Peshawar MPD-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1377.878 | 360.368 | 440 | 347 | 347 | 260.467 | 620.835 | 577.51 | 58% |
45% May - 2021 |
Hostel block, F.S work completed. Toilet Block, plaster & Floor PCCi in E1, E2 Block and BB work is in progress. Pavilion Block. External finishing in progress. Floor Tyling, PCC completed. Tuck shops Block A&B Frame S/Work & internal plaster finishing in progress.
Balance work tender under process |
No Image |
Arbab Niaz Cricket Stadium, Peshawar | |||||||||||||||||||
2009 (OG) |
150751-Feasibility and improvement/construction of Arbab Niaz Cricket Stadium Peshawar. |
Peshawar MPD-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1377.878 | 360.368 | 440 | 440 | 440 | 251 | 611.368 | 577.51 | 58% |
44% April - 2021 |
Hostel block, F.S work completed. Toilet Block, plaster & Floor PCCi in E1, E2 Block and BB work is in progress. Pavilion Block. External finishing in progress. Floor Tyling, PCC completed. Tuck shops Block A&B Frame S/Work & internal plaster finishing in progress.
Balance work tender under process |
No Image |
Arbab Niaz Cricket Stadium, Peshawar | |||||||||||||||||||
2009 (OG) |
150751-Feasibility and improvement/construction of Arbab Niaz Cricket Stadium Peshawar. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1377.878 | 360.368 | 440 | 440 | 440 | 94.208 | 454.576 | 577.51 | 58% |
33% December - 2020 |
Hostel block, F.S work completed. Toilet Block, plaster & Floor PCCi in E1, E2 Block and BB work is in progress. Pavilion Block. External finishing in progress. Floor Tyling, PCC completed. Tuck shops Block A&B Frame S/Work & internal plaster finishing in progress.
TS Submitted |
No Image |
Arbab Niaz Cricket Stadium, Peshawar | |||||||||||||||||||
2009 (OG) |
150751-Feasibility and improvement/construction of Arbab Niaz Cricket Stadium Peshawar. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1377.878 | 360.368 | 440 | 440 | 440 | 94.208 | 454.576 | 577.51 | 58% |
33% December - 2020 |
Hostel block, F.S work completed. Toilet Block, plaster & Floor PCCi in E1, E2 Block and BB work is in progress. Pavilion Block. External finishing in progress. Floor Tyling, PCC completed. Tuck shops Block A&B Frame S/Work & internal plaster finishing in progress.
TS Submitted |
No Image |
Arbab Niaz Cricket Stadium, Peshawar | |||||||||||||||||||
2009 (OG) |
150751-Feasibility and improvement/construction of Arbab Niaz Cricket Stadium Peshawar. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1377.878 | 0 | 440 | 440 | 275 | 59.605 | 59.605 | 937.878 | 32% |
4% October - 2020 |
Hostel block, F.S work completed. Toilet Block, plaster & Floor PCCinE1,E2 Block and BB work is in progress. Pavilion Block. External finishing in progress. Floor Tyling, PCC completed. Tuck shops Block A&B Frame S/Work & internal plaster finishing in progress. |
No Image |
Arbab Niaz Cricket Stadium, Peshawar | |||||||||||||||||||
2009 (OG) |
150751-Feasibility and improvement/construction of Arbab Niaz Cricket Stadium Peshawar. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1377.878 | 0 | 440 | 440 | 275 | 25.68 | 25.68 | 937.878 | 32% |
2% September - 2020 |
Hostel block, F.S work completed. Toilet Block, plaster & Floor PCCinE1,E2 Block and BB work is in progress. Pavilion Block. External finishing in progress. Floor Tyling, PCC completed. Tuck shops Block A&B Frame S/Work & internal plaster finishing in progress. |
No Image |
Arbab Niaz Cricket Stadium, Peshawar | |||||||||||||||||||
2009 (OG) |
150751-Feasibility and improvement/construction of Arbab Niaz Cricket Stadium Peshawar. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1377.878 | 0 | 440 | 440 | 0 | 0 | 0 | 937.878 | 32% |
- August - 2020 |
Hostel block, F.S work completed. Toilet Block, plaster & Floor PCCinE1,E2 Block and BB work is in progress. Pavilion Block. External finishing in progress. Floor Tyling, PCC completed. Tuck shops Block A&B Frame S/Work & internal plaster finishing in progress. |
No Image |
Arbab Niaz Cricket Stadium, Peshawar | |||||||||||||||||||
2009 (OG) |
150751-Feasibility and improvement/construction of Arbab Niaz Cricket Stadium Peshawar. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1377.878 | 418 | 440 | 0 | 0 | 0 | 418 | 519.878 | 62% |
30% July - 2020 |
Hostel block, F.S work completed. Toilet Block, p |
No Image |
Arbab Niaz Cricket Stadium, Peshawar | |||||||||||||||||||
2009 (OG) |
150751-Feasibility and improvement/construction of Arbab Niaz Cricket Stadium Peshawar. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1377.878 | 360.368 | 440 | 440 | 440 | 115.997 | 476.365 | 577.51 | 58% |
35% March - 2021 |
Hostel block, F.S work completed. Toilet Block, plaster & Floor PCCi in E1, E2 Block and BB work is in progress. Pavilion Block. External finishing in progress. Floor Tyling, PCC completed. Tuck shops Block A&B Frame S/Work & internal plaster finishing in progress.
TS Submitted |
No Image |
Arbab Niaz Cricket Stadium, Peshawar | |||||||||||||||||||
2009 (OG) |
150751-Feasibility and improvement/construction of Arbab Niaz Cricket Stadium Peshawar. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1377.878 | 360.368 | 440 | 440 | 440 | 115.997 | 476.365 | 577.51 | 58% |
35% February - 2021 |
Hostel block, F.S work completed. Toilet Block, plaster & Floor PCCi in E1, E2 Block and BB work is in progress. Pavilion Block. External finishing in progress. Floor Tyling, PCC completed. Tuck shops Block A&B Frame S/Work & internal plaster finishing in progress.
TS Submitted |
No Image |
Arbab Niaz Cricket Stadium, Peshawar | |||||||||||||||||||
2009 (OG) |
150751-Feasibility and improvement/construction of Arbab Niaz Cricket Stadium Peshawar. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1377.878 | 360.368 | 440 | 440 | 440 | 94.208 | 454.576 | 577.51 | 58% |
33% January - 2021 |
Hostel block, F.S work completed. Toilet Block, plaster & Floor PCCi in E1, E2 Block and BB work is in progress. Pavilion Block. External finishing in progress. Floor Tyling, PCC completed. Tuck shops Block A&B Frame S/Work & internal plaster finishing in progress.
TS Submitted |
No Image |
Arbab Niaz Cricket Stadium, Peshawar | |||||||||||||||||||