Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
2010 (OG) |
170533-Provision of Swimming Pool at Hayatabad Sports Complex. |
Peshawar MPD-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 88.227 | 0 | 88 | 34 | 34 | 26.102 | 26.102 | 0.227 | 100% |
30% May - 2021 |
Side wall sides completed
Excavation for swimming pool completed, coloumn started, Trusses work started
Cannot be completed due to revised PC-I under process on request of Sports Depatt: |
No Image |
2010 (OG) |
170533-Provision of Swimming Pool at Hayatabad Sports Complex. |
Peshawar MPD-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 88.227 | 0 | 88 | 44 | 44 | 15.121 | 15.121 | 0.227 | 100% |
17% April - 2021 |
Side wall sides completed
Excavation for swimming pool completed, coloumn started, Trusses work started
Cannot be completed due to revised PC-I under process on request of Sports Depatt: |
No Image |
2010 (OG) |
170533-Provision of Swimming Pool at Hayatabad Sports Complex. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 88.227 | 0 | 88 | 88 | 20 | 15.121 | 15.121 | 0.227 | 100% |
17% December - 2020 |
Work in progress. Raft foundation in progress.
TS Submitted to SE |
No Image |
2010 (OG) |
170533-Provision of Swimming Pool at Hayatabad Sports Complex. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 88.227 | 0 | 88 | 88 | 20 | 15.121 | 15.121 | 0.227 | 100% |
17% December - 2020 |
Work in progress. Raft foundation in progress.
TS Submitted to SE |
No Image |
2010 (OG) |
170533-Provision of Swimming Pool at Hayatabad Sports Complex. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 88.227 | 0 | 88 | 88 | 20 | 0.136 | 0.136 | 0.227 | 100% |
0% October - 2020 |
Work in progress. |
No Image |
2010 (OG) |
170533-Provision of Swimming Pool at Hayatabad Sports Complex. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 88.227 | 0 | 88 | 88 | 0 | 0 | 0 | 0.227 | 100% |
- September - 2020 |
Work order issued to contractor and layout given. |
No Image |
2010 (OG) |
170533-Provision of Swimming Pool at Hayatabad Sports Complex. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 88.227 | 0 | 88 | 88 | 0 | 0 | 0 | 0.227 | 100% |
- August - 2020 |
Work order issued to contractor and layout given. |
No Image |
2010 (OG) |
170533-Provision of Swimming Pool at Hayatabad Sports Complex. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 88.227 | 0 | 88 | 0 | 0 | 0 | 0 | 0.227 | 100% |
- July - 2020 |
Tender called on 15/01/2020. Technical Evaluation |
No Image |
2010 (OG) |
170533-Provision of Swimming Pool at Hayatabad Sports Complex. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 88.227 | 0 | 88 | 20 | 20 | 15.121 | 15.121 | 0.227 | 100% |
17% March - 2021 |
Side wall sides completed
Excavation for swimming pool completed, coloumn started, Trusses work started |
No Image |
2010 (OG) |
170533-Provision of Swimming Pool at Hayatabad Sports Complex. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 88.227 | 0 | 88 | 20 | 20 | 15.121 | 15.121 | 0.227 | 100% |
17% February - 2021 |
Side wall sides completed
Excavation for swimming pool completed, coloumn started, Trusses work started |
No Image |
2010 (OG) |
170533-Provision of Swimming Pool at Hayatabad Sports Complex. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 88.227 | 0 | 88 | 20 | 20 | 15.121 | 15.121 | 0.227 | 100% |
17% January - 2021 |
Work in progress. Raft foundation in progress.
TS Submitted to SE |
No Image |
Pages : 1 |