Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
2024 (OG) |
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 35.532 | 0 | 0 | 0 | 0 | 0 | 0 | 35.532 | - |
- December - 2020 |
Approved. |
No Image |
2024 (OG) |
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 35.532 | 0 | 0 | 0 | 0 | 0 | 0 | 35.532 | - |
- December - 2020 |
Approved. |
No Image |
2024 (OG) |
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 35.532 | 0 | 0 | 0 | 0 | 0 | 0 | 35.532 | - |
- October - 2020 |
Approved. |
No Image |
2024 (OG) |
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 35.532 | 0 | 0 | 0 | 0 | 0 | 0 | 35.532 | - |
- September - 2020 |
Approved. |
No Image |
2024 (OG) |
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 35.532 | 0 | 0 | 0 | 0 | 0 | 0 | 35.532 | - |
- August - 2020 |
Approved. |
No Image |
2024 (OG) |
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 35.532 | 0 | 0 | 0 | 0 | 0 | 0 | 35.532 | - |
- May - 2021 |
04- Units
1. Work started
2. Work order issued
3. Work started
4. Work order issued |
No Image |
1 Basket Ball Ground in City Sporty Complex Abbottabad
2 PG Banda SIngllain
3 Squash Court City Sporty Complex Abbottabad
4 PG at Barahotar | |||||||||||||||||||
2024 (OG) |
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 35.532 | 0 | 0 | 0 | 0 | 0 | 0 | 35.532 | - |
- April - 2021 |
Approved. |
No Image |
1 Basket Ball Ground in City Sporty Complex Abbottabad
2 PG Banda SIngllain
3 Squash Court City Sporty Complex Abbottabad
4 PG at Barahotar | |||||||||||||||||||
2024 (OG) |
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 35.532 | 0 | 0 | 0 | 0 | 0 | 0 | 35.532 | - |
- March - 2021 |
Approved. |
No Image |
1 Basket Ball Ground in City Sporty Complex Abbottabad
2 PG Banda SIngllain
3 Squash Court City Sporty Complex Abbottabad
4 PG at Barahotar | |||||||||||||||||||
2024 (OG) |
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 35.532 | 0 | 0 | 0 | 0 | 0 | 0 | 35.532 | - |
- February - 2021 |
Approved. |
No Image |
1 Basket Ball Ground in City Sporty Complex Abbottabad
2 PG Banda SIngllain
3 Squash Court City Sporty Complex Abbottabad
4 PG at Barahotar | |||||||||||||||||||
2024 (OG) |
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 35.532 | 0 | 0 | 0 | 0 | 0 | 0 | 35.532 | - |
- January - 2021 |
Approved. |
No Image |
1 Basket Ball Ground in City Sporty Complex Abbottabad
2 PG Banda SIngllain
3 Squash Court City Sporty Complex Abbottabad
4 PG at Barahotar | |||||||||||||||||||
2024 (OG) |
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 35.02 | 0 | 0 | 0 | 0 | 0 | 0 | 35.02 | - |
- December - 2020 |
Approved. |
No Image |
2024 (OG) |
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 35.02 | 0 | 0 | 0 | 0 | 0 | 0 | 35.02 | - |
- December - 2020 |
Approved. |
No Image |
2024 (OG) |
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 35.02 | 0 | 0 | 0 | 0 | 0 | 0 | 35.02 | - |
- October - 2020 |
Approved. |
No Image |
2024 (OG) |
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 35.02 | 0 | 0 | 0 | 0 | 0 | 0 | 35.02 | - |
- September - 2020 |
Approved. |
No Image |
2024 (OG) |
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 35.02 | 0 | 0 | 0 | 0 | 0 | 0 | 35.02 | - |
- August - 2020 |
Approved. |
No Image |
2024 (OG) |
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 35.02 | 0 | 0 | 0 | 0 | 0 | 0 | 35.02 | - |
- May - 2021 |
Approved. |
No Image |
2024 (OG) |
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 35.02 | 0 | 0 | 0 | 0 | 0 | 0 | 35.02 | - |
- April - 2021 |
Approved. |
No Image |
2024 (OG) |
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 35.02 | 0 | 0 | 0 | 0 | 0 | 0 | 35.02 | - |
- March - 2021 |
Approved. |
No Image |
2024 (OG) |
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 35.02 | 0 | 0 | 0 | 0 | 0 | 0 | 35.02 | - |
- February - 2021 |
Approved. |
No Image |
2024 (OG) |
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 35.02 | 0 | 0 | 0 | 0 | 0 | 0 | 35.02 | - |
- January - 2021 |
Approved. |
No Image |
2024 (OG) |
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn). |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 41.86 | 0 | 0 | 0 | 0 | 0 | 0 | 41.86 | - |
- December - 2020 |
Approved. |
No Image |
2024 (OG) |
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn). |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 41.86 | 0 | 0 | 0 | 0 | 0 | 0 | 41.86 | - |
- December - 2020 |
Approved. |
No Image |
2024 (OG) |
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn). |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 41.86 | 0 | 0 | 0 | 0 | 0 | 0 | 41.86 | - |
- October - 2020 |
Approved. |
No Image |
2024 (OG) |
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn). |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 41.86 | 0 | 0 | 0 | 0 | 0 | 0 | 41.86 | - |
- September - 2020 |
Approved. |
No Image |
2024 (OG) |
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn). |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 41.86 | 0 | 0 | 0 | 0 | 0 | 0 | 41.86 | - |
- August - 2020 |
Approved. |
No Image |
2024 (OG) |
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn). |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 41.86 | 0 | 3.2 | 3.2 | 3.2 | 2.3 | 2.3 | 38.66 | 8% |
5% May - 2021 |
05- Units
1. Layout given
2. Volley Ball court in progress
3. Levelling Dressing in progress
4. Badmenton, Basket Ball, Cricket Pitch & Volley Ball court in progress
5. Levelling Dressing in progress/Layout given for pitches |
No Image |
1. PG at GGHS Kulyari 9.28 M
2. V/B cout at GHSS Chinar 0.560 M
3. PG at GHSS Ambela 7.00 M
4. Playing facilitities 2.02 M
5. V/B and Gabadi Cout at GHS Sora 7.81 M | |||||||||||||||||||
2024 (OG) |
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn). |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 41.86 | 0 | 3.2 | 3.2 | 3.2 | 2.3 | 2.3 | 38.66 | 8% |
5% April - 2021 |
05 units work in porgress
Funds Demanded rs: 20 M |
No Image |
1. PG at GGHS Kulyari 9.28 M
2. V/B cout at GHSS Chinar 0.560 M
3. PG at GHSS Ambela 7.00 M
4. Playing facilitities 2.02 M
5. V/B and Gabadi Cout at GHS Sora 7.81 M | |||||||||||||||||||
2024 (OG) |
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn). |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 41.86 | 0 | 3.2 | 3.2 | 3.2 | 2.3 | 2.3 | 38.66 | 8% |
5% March - 2021 |
05 units work in porgress
Funds Demanded rs: 20 M |
No Image |
1. PG at GGHS Kulyari 9.28 M
2. V/B cout at GHSS Chinar 0.560 M
3. PG at GHSS Ambela 7.00 M
4. Playing facilitities 2.02 M
5. V/B and Gabadi Cout at GHS Sora 7.81 M | |||||||||||||||||||
2024 (OG) |
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn). |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 41.86 | 0 | 3.2 | 3.2 | 3.2 | 2.3 | 2.3 | 38.66 | 8% |
5% February - 2021 |
05 units work in porgress
Funds Demanded rs: 20 M |
No Image |
1. PG at GGHS Kulyari 9.28 M
2. V/B cout at GHSS Chinar 0.560 M
3. PG at GHSS Ambela 7.00 M
4. Playing facilitities 2.02 M
5. V/B and Gabadi Cout at GHS Sora 7.81 M | |||||||||||||||||||
2024 (OG) |
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn). |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 41.86 | 0 | 0 | 0 | 0 | 0 | 0 | 41.86 | - |
- January - 2021 |
05 units work in porgress
Funds Demanded rs: 20 M |
No Image |
1. PG at GGHS Kulyari 9.28 M
2. V/B cout at GHSS Chinar 0.560 M
3. PG at GHSS Ambela 7.00 M
4. Playing facilitities 2.02 M
5. V/B and Gabadi Cout at GHS Sora 7.81 M | |||||||||||||||||||
2024 (OG) |
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn). |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.01 | 0 | 0 | 0 | 0 | 0 | 0 | 36.01 | - |
- October - 2020 |
Approved. |
No Image |
2024 (OG) |
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn). |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.01 | 0 | 0 | 0 | 0 | 0 | 0 | 36.01 | - |
- September - 2020 |
Approved. |
No Image |
2024 (OG) |
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn). |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.01 | 0 | 0 | 0 | 0 | 0 | 0 | 36.01 | - |
- August - 2020 |
Approved. |
No Image |
2024 (OG) |
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn). |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.01 | 0 | 0 | 0 | 0 | 0 | 0 | 36.01 | - |
- May - 2021 |
Approved. |
No Image |
2024 (OG) |
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn). |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.01 | 0 | 0 | 0 | 0 | 0 | 0 | 36.01 | - |
- April - 2021 |
Approved. |
No Image |
2024 (OG) |
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn). |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.01 | 0 | 0 | 0 | 0 | 0 | 0 | 36.01 | - |
- March - 2021 |
Approved. |
No Image |
2024 (OG) |
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn). |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.01 | 0 | 0 | 0 | 0 | 0 | 0 | 36.01 | - |
- February - 2021 |
Approved. |
No Image |
2024 (OG) |
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn). |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.01 | 0 | 0 | 0 | 0 | 0 | 0 | 36.01 | - |
- January - 2021 |
Approved. |
No Image |
2024 (OG) |
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn). |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 11.34 | 0 | 14.77 | 14.77 | 14.77 | 6.562 | 6.562 | 0 | 100% |
58% December - 2020 |
work in progress. |
No Image |
2024 (OG) |
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn). |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 11.34 | 0 | 14.77 | 14.77 | 14.77 | 6.562 | 6.562 | 0 | 100% |
58% December - 2020 |
work in progress. |
No Image |
2024 (OG) |
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn). |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 11.34 | 0 | 10.93 | 10.93 | 10.93 | 0 | 0 | 0.41 | 96% |
- October - 2020 |
work in progress. |
No Image |
2024 (OG) |
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn). |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 11.34 | 0 | 10.93 | 10.93 | 10.93 | 0 | 0 | 0.41 | 96% |
- September - 2020 |
work in progress. |
No Image |
2024 (OG) |
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn). |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 11.34 | 0 | 0 | 0 | 0 | 0 | 0 | 11.34 | - |
- August - 2020 |
Approved. |
No Image |
2024 (OG) |
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn). |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 11.34 | 0 | 22.938 | 22.938 | 22.938 | 13.848 | 13.848 | 0 | 100% |
100% May - 2021 |
work in progress. |
No Image |
Scope of work:
| |||||||||||||||||||
2024 (OG) |
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn). |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 11.34 | 0 | 22.938 | 22.938 | 22.938 | 13.848 | 13.848 | 0 | 100% |
100% April - 2021 |
work in progress. |
No Image |
| |||||||||||||||||||
2024 (OG) |
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn). |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 11.34 | 0 | 14.77 | 14.77 | 14.77 | 10.493 | 10.493 | 0 | 100% |
93% March - 2021 |
work in progress. |
No Image |
| |||||||||||||||||||
2024 (OG) |
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn). |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 11.34 | 0 | 0 | 0 | 0 | 0 | 0 | 11.34 | - |
- February - 2021 |
work in progress. |
No Image |
| |||||||||||||||||||
2024 (OG) |
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn). |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 11.34 | 0 | 14.77 | 14.77 | 14.77 | 10.493 | 10.493 | 0 | 100% |
93% January - 2021 |
work in progress. |
No Image |
2024 (OG) |
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn). |
Chitral Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 33.43 | 0 | 16.209 | 16.209 | 16.209 | 9.867 | 9.867 | 17.221 | 48% |
30% December - 2020 |
Approved. Work is in progress Rs.24.440 M IS REQUIRED DURING NEXT FININCIAL YEAR 2020-21 |
No Image |
2024 (OG) |
180553-Development of 1000 Playing facilities in Khyber Pakhtunkhwa (Total Cost Rs. 5500 Mn - Phase-I Cost Rs. 2500 Mn). |
Chitral Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 33.43 | 0 | 16.209 | 16.209 | 16.209 | 9.867 | 9.867 | 17.221 | 48% |
30% December - 2020 |
Approved. Work is in progress Rs.24.440 M IS REQUIRED DURING NEXT FININCIAL YEAR 2020-21 |
No Image |