Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2021, January - 2019, February - 2021, February - 2019, March - 2021, March - 2019, April - 2019, April - 2021, May - 2021, July - 2020, August - 2020, September - 2020, October - 2020, November - 2018, December - 2018, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
210
(OG)
191142-180311 - Construction of Tehsil Building in Ping, Sub-Division Tank. [MA]
FR Tank
30-11--1 30-11--1 - 30-11--1 - 20 0 20 20 7 0 0 0 100% -
December - 2020
Work stopped due to decision of proper site from Administrative Side, for which Deputy Commissioner Tank has been requested to resolove the matter. New site identified and handed over to C&W Deptt: the contractor order to start the work. But the contractor filed petition in High Court against shifting of site.
No Image
210
(OG)
191142-180311 - Construction of Tehsil Building in Ping, Sub-Division Tank. [MA]
FR Tank
30-11--1 30-11--1 - 30-11--1 - 20 0 20 20 7 0 0 0 100% -
December - 2020
Work stopped due to decision of proper site from Administrative Side, for which Deputy Commissioner Tank has been requested to resolove the matter. New site identified and handed over to C&W Deptt: the contractor order to start the work. But the contractor filed petition in High Court against shifting of site.
No Image
210
(OG)
191142-180311 - Construction of Tehsil Building in Ping, Sub-Division Tank. [MA]
FR Tank
30-11--1 30-11--1 - 30-11--1 - 20 0 20 20 7 0 0 0 100% -
October - 2020
Work stopped due to decision of proper site from Administrative Side, for which Deputy Commissioner Tank has been requested to resolove the matter. New site identified and handed over to C&W Deptt: the contractor order to start the work. But the contractor filed petition in High Court against shifting of site.
No Image
210
(OG)
191142-180311 - Construction of Tehsil Building in Ping, Sub-Division Tank. [MA]
FR Tank
30-11--1 30-11--1 - 30-11--1 - 20 0 20 20 0 0 0 0 100% -
September - 2020
Work stopped due to decision of proper site from Administrative Side, for which Deputy Commissioner Tank has been requested to resolove the matter. New site identified and handed over to C&W Deptt: the contractor order to start the work. But the contractor filed petition in High Court against shifting of site.
No Image
210
(OG)
191142-180311 - Construction of Tehsil Building in Ping, Sub-Division Tank. [MA]
FR Tank
30-11--1 30-11--1 - 30-11--1 - 20 0 20 20 0 0 0 0 100% -
August - 2020
Work stopped due to decision of proper site from Administrative Side, for which Deputy Commissioner Tank has been requested to resolove the matter. New site identified and handed over to C&W Deptt: the contractor order to start the work. But the contractor filed petition in High Court against shifting of site.
No Image
210
(OG)
191142-180311 - Construction of Tehsil Building in Ping, Sub-Division Tank. [MA]
FR Tank
30-11--1 30-11--1 - 30-11--1 - 20 0 20 0 0 0 0 0 -
July - 2020
No Image
210
(OG)
191142-180311 - Construction of Tehsil Building in Ping, Sub-Division Tank. [MA]
FR Tank
30-11--1 30-11--1 - 30-11--1 - 20 0 20 11.694 11.694 0 0 0 100% -
May - 2021
Work stopped due to decision of proper site from Administrative Side, for which Deputy Commissioner Tank has been requested to resolove the matter. New site identified and handed over to C&W Deptt: the contractor order to start the work. But the contractor filed petition in High Court against shifting of site.
No Image
210
(OG)
191142-180311 - Construction of Tehsil Building in Ping, Sub-Division Tank. [MA]
FR Tank
30-11--1 30-11--1 - 30-11--1 - 20 0 20 11.694 11.694 0 0 0 100% -
April - 2021
Work stopped due to decision of proper site from Administrative Side, for which Deputy Commissioner Tank has been requested to resolove the matter. New site identified and handed over to C&W Deptt: the contractor order to start the work. But the contractor filed petition in High Court against shifting of site.
No Image
210
(OG)
191142-180311 - Construction of Tehsil Building in Ping, Sub-Division Tank. [MA]
FR Tank
30-11--1 30-11--1 - 30-11--1 - 20 0 20 11.694 11.694 0 0 0 100% -
March - 2021
Work stopped due to decision of proper site from Administrative Side, for which Deputy Commissioner Tank has been requested to resolove the matter. New site identified and handed over to C&W Deptt: the contractor order to start the work. But the contractor filed petition in High Court against shifting of site.
No Image
210
(OG)
191142-180311 - Construction of Tehsil Building in Ping, Sub-Division Tank. [MA]
FR Tank
30-11--1 30-11--1 - 30-11--1 - 20 0 20 11.694 11.694 0 0 0 100% -
February - 2021
Work stopped due to decision of proper site from Administrative Side, for which Deputy Commissioner Tank has been requested to resolove the matter. New site identified and handed over to C&W Deptt: the contractor order to start the work. But the contractor filed petition in High Court against shifting of site.
No Image
210
(OG)
191142-180311 - Construction of Tehsil Building in Ping, Sub-Division Tank. [MA]
FR Tank
30-11--1 30-11--1 - 30-11--1 - 20 0 20 20 7 0 0 0 100% -
January - 2021
Work stopped due to decision of proper site from Administrative Side, for which Deputy Commissioner Tank has been requested to resolove the matter. New site identified and handed over to C&W Deptt: the contractor order to start the work. But the contractor filed petition in High Court against shifting of site.
No Image
210
(OG)
150553-Construction of building for Elementary Education Foundation (EEF).
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 60 56.137 0 0 0 0 56.137 3.863 - 94%
December - 2018
Finishing in progress. Revised PC-I/DCE for Rs.80.103 m submitted to MD EEF Peshawar on 02/03/2018.
No Image
Peshawar
210
(OG)
150553-Construction of building for Elementary Education Foundation (EEF).
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 60 56.137 0 0 0 0 56.137 3.863 - 94%
November - 2018
Finishing in progress. Revised PC-I/DCE for Rs.80.103 m submitted to MD EEF Peshawar on 02/03/2018.
No Image
Peshawar
210
(OG)
150553-Construction of building for Elementary Education Foundation (EEF).
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 60 56.137 0 0 0 0 56.137 3.863 - 94%
November - 2018
Finishing in progress. Revised PC-I/DCE for Rs.80.103 m submitted to MD EEF Peshawar on 02/03/2018.
No Image
Peshawar
210
(OG)
150553-Construction of building for Elementary Education Foundation (EEF).
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 69.38 56.137 1.5 1.5 1.5 0 56.137 11.743 83% 81%
April - 2019
Finishing in progress.
No Image
Peshawar
210
(OG)
150553-Construction of building for Elementary Education Foundation (EEF).
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 69.38 56.137 1.5 1.5 1.5 0 56.137 11.743 83% 81%
March - 2019
Finishing in progress.
No Image
Peshawar
210
(OG)
150553-Construction of building for Elementary Education Foundation (EEF).
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 69.38 56.137 1.5 1.5 1.5 0 56.137 11.743 83% 81%
March - 2019
Finishing in progress.
No Image
Peshawar
210
(OG)
150553-Construction of building for Elementary Education Foundation (EEF).
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 69.38 56.137 1.5 1.5 1.5 0 56.137 11.743 83% 81%
February - 2019
Finishing in progress.
No Image
Peshawar
210
(OG)
150553-Construction of building for Elementary Education Foundation (EEF).
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 60 56.137 0 0 0 0 56.137 3.863 - 94%
January - 2019
Finishing in progress. Revised PC-I/DCE for Rs.80.103 m submitted to MD EEF Peshawar on 02/03/2018.
No Image
Peshawar
210
(OG)
150553-Construction of building for Elementary Education Foundation (EEF).
Provincial
30-11--1 30-11--1 - 30-11--1 - 60 0.321 3 3 0 0 0.321 0 - -
December - 2018
No Image
210
(OG)
150553-Construction of building for Elementary Education Foundation (EEF).
Provincial
30-11--1 30-11--1 - 30-11--1 - 60 0.321 3 3 0 0 0.321 0 - -
November - 2018
No Image
210
(OG)
150553-Construction of building for Elementary Education Foundation (EEF).
Provincial
30-11--1 30-11--1 - 30-11--1 - 60 0.321 3 3 0 0 0.321 0 - -
November - 2018
No Image
210
(OG)
150553-Construction of building for Elementary Education Foundation (EEF).
Provincial
30-11--1 30-11--1 - 30-11--1 - 60 0.321 3 3 0 0 0.321 0 - -
April - 2019
No Image
210
(OG)
150553-Construction of building for Elementary Education Foundation (EEF).
Provincial
30-11--1 30-11--1 - 30-11--1 - 60 0.321 3 3 0 0 0.321 0 - -
March - 2019
No Image
210
(OG)
150553-Construction of building for Elementary Education Foundation (EEF).
Provincial
30-11--1 30-11--1 - 30-11--1 - 60 0.321 3 3 0 0 0.321 0 - -
March - 2019
No Image
210
(OG)
150553-Construction of building for Elementary Education Foundation (EEF).
Provincial
30-11--1 30-11--1 - 30-11--1 - 60 0.321 3 3 0 0 0.321 0 - -
February - 2019
No Image
210
(OG)
150553-Construction of building for Elementary Education Foundation (EEF).
Provincial
30-11--1 30-11--1 - 30-11--1 - 60 0.321 3 3 0 0 0.321 0 - -
January - 2019
No Image
Pages : 1