Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2021, February - 2021, March - 2021, April - 2021, May - 2021, July - 2020, August - 2020, September - 2020, October - 2020, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
217
(OG)
191145-180304 - Construction of Rest House & Jirga Hall at Pastawani Top Sub-Division Peshawar. [MA]
FR Peshawar
30-11--1 30-11--1 - 30-11--1 - 11.5 3 10 10 5 0 3 0 100% 26%
December - 2020
DPC in progress.C/Wall 80% completed.
No Image
217
(OG)
191145-180304 - Construction of Rest House & Jirga Hall at Pastawani Top Sub-Division Peshawar. [MA]
FR Peshawar
30-11--1 30-11--1 - 30-11--1 - 11.5 3 10 10 5 0 3 0 100% 26%
December - 2020
DPC in progress.C/Wall 80% completed.
No Image
217
(OG)
191145-180304 - Construction of Rest House & Jirga Hall at Pastawani Top Sub-Division Peshawar. [MA]
FR Peshawar
30-11--1 30-11--1 - 30-11--1 - 11.5 3 10 10 5 0 3 0 100% 26%
October - 2020
DPC in progress.C/Wall 80% completed.
No Image
217
(OG)
191145-180304 - Construction of Rest House & Jirga Hall at Pastawani Top Sub-Division Peshawar. [MA]
FR Peshawar
30-11--1 30-11--1 - 30-11--1 - 11.5 3 10 10 0 0 3 0 100% 26%
September - 2020
DPC in progress. C/Wall completed.
No Image
217
(OG)
191145-180304 - Construction of Rest House & Jirga Hall at Pastawani Top Sub-Division Peshawar. [MA]
FR Peshawar
30-11--1 30-11--1 - 30-11--1 - 10.008 3 10 10 0 0 3 0 100% 30%
August - 2020
DPC in progress. C/Wall completed.
No Image
217
(OG)
191145-180304 - Construction of Rest House & Jirga Hall at Pastawani Top Sub-Division Peshawar. [MA]
FR Peshawar
30-11--1 30-11--1 - 30-11--1 - 10 3 10 0 0 0 3 0 100% 30%
July - 2020
DPC in progress. C/Wall completed.
No Image
217
(OG)
191145-180304 - Construction of Rest House & Jirga Hall at Pastawani Top Sub-Division Peshawar. [MA]
FR Peshawar
30-11--1 30-11--1 - 30-11--1 - 11.5 3 10 5 5 0 3 0 100% 26%
May - 2021
DPC in progress.C/Wall 80% completed.
No Image
Jirga Hall at Pastawani Top
217
(OG)
191145-180304 - Construction of Rest House & Jirga Hall at Pastawani Top Sub-Division Peshawar. [MA]
FR Peshawar
30-11--1 30-11--1 - 30-11--1 - 11.5 3 10 5 5 0 3 0 100% 26%
April - 2021
DPC in progress.C/Wall 80% completed.
No Image
Jirga Hall at Pastawani Top
217
(OG)
191145-180304 - Construction of Rest House & Jirga Hall at Pastawani Top Sub-Division Peshawar. [MA]
FR Peshawar
30-11--1 30-11--1 - 30-11--1 - 11.5 3 10 5 5 0 3 0 100% 26%
March - 2021
DPC in progress.C/Wall 80% completed.
No Image
Jirga Hall at Pastawani Top
217
(OG)
191145-180304 - Construction of Rest House & Jirga Hall at Pastawani Top Sub-Division Peshawar. [MA]
FR Peshawar
30-11--1 30-11--1 - 30-11--1 - 11.5 3 10 5 5 0 3 0 100% 26%
February - 2021
DPC in progress.C/Wall 80% completed.
No Image
Jirga Hall at Pastawani Top
217
(OG)
191145-180304 - Construction of Rest House & Jirga Hall at Pastawani Top Sub-Division Peshawar. [MA]
FR Peshawar
30-11--1 30-11--1 - 30-11--1 - 11.5 3 10 5 5 0 3 0 100% 26%
January - 2021
DPC in progress.C/Wall 80% completed.
No Image
Jirga Hall at Pastawani Top
Pages : 1