Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
249 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 4 Districts of Khyber Pakhtunkhwa. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 87.64 | 66.57 | 0 | 0 | 0 | 0 | 66.57 | 21.07 | - |
76% September - 2018 |
GF/FF - finishing in progress. 2nd floor - finishing in progress. |
No Image |
DI.Khan | |||||||||||||||||||
249 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 4 Districts of Khyber Pakhtunkhwa. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 87.64 | 66.57 | 0 | 0 | 0 | 0 | 66.57 | 21.07 | - |
76% July - 2018 |
GF/FF - finishing in progress. 2nd floor - finishing in progress. |
No Image |
DI.Khan | |||||||||||||||||||
249 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 4 Districts of Khyber Pakhtunkhwa. |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 97.69 | 12 | 0 | 0 | 0 | 0 | 12 | 85.69 | - |
12% September - 2018 |
Lean concrete in foundation laid. Work stopped due to court direction. |
No Image |
Tax Facilitation Center District Nowshera | |||||||||||||||||||
249 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 4 Districts of Khyber Pakhtunkhwa. |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 97.69 | 12 | 0 | 0 | 0 | 0 | 12 | 85.69 | - |
12% July - 2018 |
Lean concrete in foundation laid. Work stopped due to court direction. |
No Image |
Tax Facilitation Center District Nowshera | |||||||||||||||||||
249 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 4 Districts of Khyber Pakhtunkhwa. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 222.25 | 78.333 | 0 | 0 | 0 | 0 | 78.333 | 143.917 | - |
35% September - 2018 |
OHT excavation completed. BW excavation in progress. |
No Image |
Tax Facilitation Center at Hayatabad, Peshawar | |||||||||||||||||||
249 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 4 Districts of Khyber Pakhtunkhwa. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 222.25 | 78.333 | 0 | 0 | 0 | 0 | 78.333 | 143.917 | - |
35% July - 2018 |
OHT excavation completed. BW excavation in progress. |
No Image |
Tax Facilitation Center at Hayatabad, Peshawar | |||||||||||||||||||
249 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 4 Districts of Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 600 | 51.57 | 56 | 56 | 0 | 0 | 51.57 | 0 | - |
- September - 2018 |
No Image | |
249 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 4 Districts of Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 600 | 51.57 | 56 | 56 | 0 | 0 | 51.57 | 0 | - |
- July - 2018 |
No Image | |
Pages : 1 |