Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : July - 2018, September - 2018,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
253
(OG)
150603-Construction / Renovation of Treasury / District Accounts Offices in Khyber Pakhtunkhwa.
Battagram
30-11--1 30-11--1 - 30-11--1 - 43.209 18.4562 0 0 0 0 18.4562 24.753 - 43%
September - 2018
Work started. Revised PC-I/DCE for i/c of land, submitted to CA for approval.
No Image
District Accounts Office Battagram
253
(OG)
150603-Construction / Renovation of Treasury / District Accounts Offices in Khyber Pakhtunkhwa.
Battagram
30-11--1 30-11--1 - 30-11--1 - 43.209 18.4562 0 0 0 0 18.4562 24.753 - 43%
July - 2018
Work started. Revised PC-I/DCE for i/c of land, submitted to CA for approval.
No Image
District Accounts Office Battagram
253
(OG)
150603-Construction / Renovation of Treasury / District Accounts Offices in Khyber Pakhtunkhwa.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 5.504 4.536 0 0 0 0 4.536 0.968 - 82%
September - 2018
Strong room - finishing in progress.
No Image
Construction of Strong Room at Charsadda
253
(OG)
150603-Construction / Renovation of Treasury / District Accounts Offices in Khyber Pakhtunkhwa.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 5.504 4.536 0 0 0 0 4.536 0.968 - 82%
July - 2018
Strong room - finishing in progress.
No Image
Construction of Strong Room at Charsadda
253
(OG)
150603-Construction / Renovation of Treasury / District Accounts Offices in Khyber Pakhtunkhwa.
Chitral
30-11--1 30-11--1 - 30-11--1 - 6.2 5.356 0 0 0 0 5.356 0.844 - 86%
September - 2018
Finishing in progress.
No Image
DAO Chitral
253
(OG)
150603-Construction / Renovation of Treasury / District Accounts Offices in Khyber Pakhtunkhwa.
Chitral
30-11--1 30-11--1 - 30-11--1 - 6.2 5.356 0 0 0 0 5.356 0.844 - 86%
July - 2018
Finishing in progress.
No Image
DAO Chitral
253
(OG)
150603-Construction / Renovation of Treasury / District Accounts Offices in Khyber Pakhtunkhwa.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 38.182 8 0 0 0 0 8 30.182 - 21%
September - 2018
Finishing stage. Dismantling involved.
No Image
Construction of Strong Room DI.Khan
253
(OG)
150603-Construction / Renovation of Treasury / District Accounts Offices in Khyber Pakhtunkhwa.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 38.182 8 0 0 0 0 8 30.182 - 21%
July - 2018
Finishing stage. Dismantling involved.
No Image
Construction of Strong Room DI.Khan
253
(OG)
150603-Construction / Renovation of Treasury / District Accounts Offices in Khyber Pakhtunkhwa.
Hangu
30-11--1 30-11--1 - 30-11--1 - 22.709 19 0 0 0 0 19 3.709 - 84%
September - 2018
Finishing stage.
No Image
Construction of new building at Hangu
253
(OG)
150603-Construction / Renovation of Treasury / District Accounts Offices in Khyber Pakhtunkhwa.
Hangu
30-11--1 30-11--1 - 30-11--1 - 22.709 19 0 0 0 0 19 3.709 - 84%
July - 2018
Floor tiles in progress. Finishing stage.
No Image
Construction of new building at Hangu
253
(OG)
150603-Construction / Renovation of Treasury / District Accounts Offices in Khyber Pakhtunkhwa.
Kohat
30-11--1 30-11--1 - 30-11--1 - 7.8 3 0 0 0 0 3 4.8 - 38%
September - 2018
Plastering in progress.
No Image
Strong Room / Guard Room at Treasury Building Kohat
253
(OG)
150603-Construction / Renovation of Treasury / District Accounts Offices in Khyber Pakhtunkhwa.
Kohat
30-11--1 30-11--1 - 30-11--1 - 7.8 3 0 0 0 0 3 4.8 - 38%
July - 2018
Plastering in progress.
No Image
Strong Room / Guard Room at Treasury Building Kohat
253
(OG)
150603-Construction / Renovation of Treasury / District Accounts Offices in Khyber Pakhtunkhwa.
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 4.975 4.831 0 0 0 0 4.831 0.144 - 97%
September - 2018
Completed & H/O.
No Image
Construction of Strong Room for District Accounts Office PK-75 Lakki Marwat
253
(OG)
150603-Construction / Renovation of Treasury / District Accounts Offices in Khyber Pakhtunkhwa.
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 4.975 4.831 0 0 0 0 4.831 0.144 - 97%
July - 2018
Main building - finishing in progress.
No Image
Construction of Strong Room for District Accounts Office PK-75 Lakki Marwat
253
(OG)
150603-Construction / Renovation of Treasury / District Accounts Offices in Khyber Pakhtunkhwa.
Mardan
30-11--1 30-11--1 - 30-11--1 - 92.739 33.638 0 0 0 0 33.638 59.101 - 36%
September - 2018
Site shifted to near Police Station Mardan. DPC level.
No Image
Construction of new office building for treasury office at Mardan
253
(OG)
150603-Construction / Renovation of Treasury / District Accounts Offices in Khyber Pakhtunkhwa.
Mardan
30-11--1 30-11--1 - 30-11--1 - 92.739 33.638 0 0 0 0 33.638 59.101 - 36%
July - 2018
Site shifted to near Police Station Mardan. Work in foundation in progresa at new site.
No Image
Construction of new office building for treasury office at Mardan
253
(OG)
150603-Construction / Renovation of Treasury / District Accounts Offices in Khyber Pakhtunkhwa.
Provincial
30-11--1 30-11--1 - 30-11--1 - 639 0 112.996 112.996 0 0 0 0 - -
September - 2018
No Image
253
(OG)
150603-Construction / Renovation of Treasury / District Accounts Offices in Khyber Pakhtunkhwa.
Provincial
30-11--1 30-11--1 - 30-11--1 - 639 0 112.996 112.996 0 0 0 0 - -
July - 2018
No Image