Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : July - 2018, September - 2018,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
264
(OG)
170613-Construction of Food Grain Godowns of 2000 Ton Capacity in District Dir Lower.
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 53.31 5 25 25 12.5 12.5 17.5 23.31 56% 33%
September - 2018
SS in progress.
No Image
Dir Lower
264
(OG)
170613-Construction of Food Grain Godowns of 2000 Ton Capacity in District Dir Lower.
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 53.31 5 25 25 0 0 5 23.31 56% 9%
July - 2018
Layout given.
No Image
Dir Lower
Pages : 1