Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
292 (OG) |
150603-Construction / Renovation of Treasury / District Accounts Offices in Khyber Pakhtunkhwa. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 43.209 | 18.4562 | 16.29 | 16.29 | 16.29 | 9.508 | 27.9642 | 8.463 | 80% |
65% December - 2018 |
Work started. Revised PC-I/DCE for i/c of land, submitted to CA for approval. |
No Image |
District Accounts Office Battagram | |||||||||||||||||||
292 (OG) |
150603-Construction / Renovation of Treasury / District Accounts Offices in Khyber Pakhtunkhwa. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 43.209 | 18.4562 | 5 | 5 | 5 | 4.58 | 23.0362 | 19.753 | 54% |
53% November - 2018 |
Work started. Revised PC-I/DCE for i/c of land, submitted to CA for approval. |
No Image |
District Accounts Office Battagram | |||||||||||||||||||
292 (OG) |
150603-Construction / Renovation of Treasury / District Accounts Offices in Khyber Pakhtunkhwa. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 43.209 | 18.4562 | 5 | 5 | 5 | 4.58 | 23.0362 | 19.753 | 54% |
53% November - 2018 |
Work started. Revised PC-I/DCE for i/c of land, submitted to CA for approval. |
No Image |
District Accounts Office Battagram | |||||||||||||||||||
292 (OG) |
150603-Construction / Renovation of Treasury / District Accounts Offices in Khyber Pakhtunkhwa. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 43.209 | 18.4562 | 19.54 | 19.54 | 19.54 | 14.061 | 32.5172 | 5.213 | 88% |
75% April - 2019 |
Work started recently . Site handed over in december 2018. Cannot be completed in CFY. |
No Image |
District Accounts Office Battagram | |||||||||||||||||||
292 (OG) |
150603-Construction / Renovation of Treasury / District Accounts Offices in Khyber Pakhtunkhwa. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 43.209 | 18.4562 | 16.29 | 16.29 | 16.29 | 14.061 | 32.5172 | 8.463 | 80% |
75% March - 2019 |
Work started recently . Site handed over in december 2018. Cannot be completed in CFY. |
No Image |
District Accounts Office Battagram | |||||||||||||||||||
292 (OG) |
150603-Construction / Renovation of Treasury / District Accounts Offices in Khyber Pakhtunkhwa. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 43.209 | 18.4562 | 16.29 | 16.29 | 16.29 | 14.061 | 32.5172 | 8.463 | 80% |
75% March - 2019 |
Work started recently . Site handed over in december 2018. Cannot be completed in CFY. |
No Image |
District Accounts Office Battagram | |||||||||||||||||||
292 (OG) |
150603-Construction / Renovation of Treasury / District Accounts Offices in Khyber Pakhtunkhwa. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 43.209 | 18.4562 | 16.29 | 16.29 | 16.29 | 9.508 | 27.9642 | 8.463 | 80% |
65% February - 2019 |
Work started recently . Site handed over in december 2018. Cannot be complted in CFY |
No Image |
District Accounts Office Battagram | |||||||||||||||||||
292 (OG) |
150603-Construction / Renovation of Treasury / District Accounts Offices in Khyber Pakhtunkhwa. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 43.209 | 18.4562 | 16.29 | 16.29 | 16.29 | 9.508 | 27.9642 | 8.463 | 80% |
65% January - 2019 |
Work started. Revised PC-I/DCE for i/c of land, submitted to CA for approval. |
No Image |
District Accounts Office Battagram | |||||||||||||||||||
292 (OG) |
150603-Construction / Renovation of Treasury / District Accounts Offices in Khyber Pakhtunkhwa. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 5.504 | 4.536 | 0.28 | 0.28 | 0.28 | 0 | 4.536 | 0.688 | 88% |
82% December - 2018 |
Completed. |
No Image |
Construction of Strong Room at Charsadda | |||||||||||||||||||
292 (OG) |
150603-Construction / Renovation of Treasury / District Accounts Offices in Khyber Pakhtunkhwa. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 5.504 | 4.536 | 0 | 0 | 0 | 0 | 4.536 | 0.968 | - |
82% November - 2018 |
Completed. |
No Image |
Construction of Strong Room at Charsadda | |||||||||||||||||||
292 (OG) |
150603-Construction / Renovation of Treasury / District Accounts Offices in Khyber Pakhtunkhwa. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 5.504 | 4.536 | 0 | 0 | 0 | 0 | 4.536 | 0.968 | - |
82% November - 2018 |
Completed. |
No Image |
Construction of Strong Room at Charsadda | |||||||||||||||||||
292 (OG) |
150603-Construction / Renovation of Treasury / District Accounts Offices in Khyber Pakhtunkhwa. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 5.504 | 4.536 | 0.28 | 0.28 | 0.28 | 0.28 | 4.816 | 0.688 | 88% |
88% April - 2019 |
Completed. |
No Image |
Construction of Strong Room at Charsadda | |||||||||||||||||||
292 (OG) |
150603-Construction / Renovation of Treasury / District Accounts Offices in Khyber Pakhtunkhwa. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 5.504 | 4.536 | 0.28 | 0.28 | 0.28 | 0 | 4.536 | 0.688 | 88% |
82% March - 2019 |
Completed. |
No Image |
Construction of Strong Room at Charsadda | |||||||||||||||||||
292 (OG) |
150603-Construction / Renovation of Treasury / District Accounts Offices in Khyber Pakhtunkhwa. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 5.504 | 4.536 | 0.28 | 0.28 | 0.28 | 0 | 4.536 | 0.688 | 88% |
82% March - 2019 |
Completed. |
No Image |
Construction of Strong Room at Charsadda | |||||||||||||||||||
292 (OG) |
150603-Construction / Renovation of Treasury / District Accounts Offices in Khyber Pakhtunkhwa. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 5.504 | 4.536 | 0.28 | 0.28 | 0.28 | 0 | 4.536 | 0.688 | 88% |
82% February - 2019 |
Completed. |
No Image |
Construction of Strong Room at Charsadda | |||||||||||||||||||
292 (OG) |
150603-Construction / Renovation of Treasury / District Accounts Offices in Khyber Pakhtunkhwa. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 5.504 | 4.536 | 0.28 | 0.28 | 0.28 | 0 | 4.536 | 0.688 | 88% |
82% January - 2019 |
Completed. |
No Image |
Construction of Strong Room at Charsadda | |||||||||||||||||||
292 (OG) |
150603-Construction / Renovation of Treasury / District Accounts Offices in Khyber Pakhtunkhwa. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 6.2 | 5.356 | 0 | 0 | 0 | 0 | 5.356 | 0.844 | - |
86% December - 2018 |
Finishing in progress. |
No Image |
DAO Chitral | |||||||||||||||||||
292 (OG) |
150603-Construction / Renovation of Treasury / District Accounts Offices in Khyber Pakhtunkhwa. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 6.2 | 5.356 | 0 | 0 | 0 | 0 | 5.356 | 0.844 | - |
86% November - 2018 |
Finishing in progress. |
No Image |
DAO Chitral | |||||||||||||||||||
292 (OG) |
150603-Construction / Renovation of Treasury / District Accounts Offices in Khyber Pakhtunkhwa. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 6.2 | 5.356 | 0 | 0 | 0 | 0 | 5.356 | 0.844 | - |
86% November - 2018 |
Finishing in progress. |
No Image |
DAO Chitral | |||||||||||||||||||
292 (OG) |
150603-Construction / Renovation of Treasury / District Accounts Offices in Khyber Pakhtunkhwa. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 6.2 | 5.356 | 0 | 0 | 0 | 0 | 5.356 | 0.844 | - |
86% April - 2019 |
Finishing in progress. |
No Image |
DAO Chitral | |||||||||||||||||||
292 (OG) |
150603-Construction / Renovation of Treasury / District Accounts Offices in Khyber Pakhtunkhwa. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 6.2 | 5.356 | 0 | 0 | 0 | 0 | 5.356 | 0.844 | - |
86% March - 2019 |
Finishing in progress. |
No Image |
DAO Chitral | |||||||||||||||||||
292 (OG) |
150603-Construction / Renovation of Treasury / District Accounts Offices in Khyber Pakhtunkhwa. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 6.2 | 5.356 | 0 | 0 | 0 | 0 | 5.356 | 0.844 | - |
86% March - 2019 |
Finishing in progress. |
No Image |
DAO Chitral | |||||||||||||||||||
292 (OG) |
150603-Construction / Renovation of Treasury / District Accounts Offices in Khyber Pakhtunkhwa. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 6.2 | 5.356 | 0 | 0 | 0 | 0 | 5.356 | 0.844 | - |
86% February - 2019 |
Finishing in progress. |
No Image |
DAO Chitral | |||||||||||||||||||
292 (OG) |
150603-Construction / Renovation of Treasury / District Accounts Offices in Khyber Pakhtunkhwa. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 6.2 | 5.356 | 0 | 0 | 0 | 0 | 5.356 | 0.844 | - |
86% January - 2019 |
Finishing in progress. |
No Image |
DAO Chitral | |||||||||||||||||||
292 (OG) |
150603-Construction / Renovation of Treasury / District Accounts Offices in Khyber Pakhtunkhwa. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 38.182 | 8 | 10 | 10 | 10 | 5.937 | 13.937 | 20.182 | 47% |
37% December - 2018 |
Completed. Dismantling involved. |
No Image |
Construction of Strong Room DI.Khan | |||||||||||||||||||
292 (OG) |
150603-Construction / Renovation of Treasury / District Accounts Offices in Khyber Pakhtunkhwa. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 38.182 | 8 | 10 | 10 | 10 | 5.2 | 13.2 | 20.182 | 47% |
35% November - 2018 |
Completed. Dismantling involved. |
No Image |
Construction of Strong Room DI.Khan | |||||||||||||||||||
292 (OG) |
150603-Construction / Renovation of Treasury / District Accounts Offices in Khyber Pakhtunkhwa. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 38.182 | 8 | 10 | 10 | 10 | 5.2 | 13.2 | 20.182 | 47% |
35% November - 2018 |
Completed. Dismantling involved. |
No Image |
Construction of Strong Room DI.Khan | |||||||||||||||||||
292 (OG) |
150603-Construction / Renovation of Treasury / District Accounts Offices in Khyber Pakhtunkhwa. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 38.182 | 8 | 21.385 | 21.385 | 21.385 | 8.075 | 16.075 | 8.797 | 77% |
42% April - 2019 |
Office Block-I, Strong Room, Guard Room - completed. Office block-II - SS in Progress. |
No Image |
Construction of Strong Room DI.Khan | |||||||||||||||||||
292 (OG) |
150603-Construction / Renovation of Treasury / District Accounts Offices in Khyber Pakhtunkhwa. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 38.182 | 8 | 28.06 | 28.06 | 28.06 | 7.969 | 15.969 | 2.122 | 94% |
42% March - 2019 |
Office Block-I, Strong Room, Guard Room - completed. Office block-II - SS in Progress. |
No Image |
Construction of Strong Room DI.Khan | |||||||||||||||||||
292 (OG) |
150603-Construction / Renovation of Treasury / District Accounts Offices in Khyber Pakhtunkhwa. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 38.182 | 8 | 28.06 | 28.06 | 28.06 | 7.969 | 15.969 | 2.122 | 94% |
42% March - 2019 |
Office Block-I, Strong Room, Guard Room - completed. Office block-II - SS in Progress. |
No Image |
Construction of Strong Room DI.Khan | |||||||||||||||||||
292 (OG) |
150603-Construction / Renovation of Treasury / District Accounts Offices in Khyber Pakhtunkhwa. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 38.182 | 8 | 10 | 10 | 10 | 5.937 | 13.937 | 20.182 | 47% |
37% February - 2019 |
Office Block - I : complted
Strong Romm : Complted
Guard Room ; complted
Office block -II : Super structure in Progress. |
No Image |
Construction of Strong Room DI.Khan | |||||||||||||||||||
292 (OG) |
150603-Construction / Renovation of Treasury / District Accounts Offices in Khyber Pakhtunkhwa. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 38.182 | 8 | 10 | 10 | 10 | 5.937 | 13.937 | 20.182 | 47% |
37% January - 2019 |
Completed. Dismantling involved. |
No Image |
Construction of Strong Room DI.Khan | |||||||||||||||||||
292 (OG) |
150603-Construction / Renovation of Treasury / District Accounts Offices in Khyber Pakhtunkhwa. |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 22.709 | 19 | 3.71 | 3.71 | 3.71 | 0 | 19 | 0 | 100% |
84% December - 2018 |
Finishing stage. |
No Image |
Construction of new building at Hangu | |||||||||||||||||||
292 (OG) |
150603-Construction / Renovation of Treasury / District Accounts Offices in Khyber Pakhtunkhwa. |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 22.709 | 19 | 3.71 | 3.71 | 3.71 | 0 | 19 | 0 | 100% |
84% November - 2018 |
Finishing stage. |
No Image |
Construction of new building at Hangu | |||||||||||||||||||
292 (OG) |
150603-Construction / Renovation of Treasury / District Accounts Offices in Khyber Pakhtunkhwa. |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 22.709 | 19 | 3.71 | 3.71 | 3.71 | 0 | 19 | 0 | 100% |
84% November - 2018 |
Finishing stage. |
No Image |
Construction of new building at Hangu | |||||||||||||||||||
292 (OG) |
150603-Construction / Renovation of Treasury / District Accounts Offices in Khyber Pakhtunkhwa. |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 22.709 | 19 | 3.71 | 3.71 | 3.71 | 1.861 | 20.861 | 0 | 100% |
92% April - 2019 |
Substantially completed. |
No Image |
Construction of new building at Hangu | |||||||||||||||||||
292 (OG) |
150603-Construction / Renovation of Treasury / District Accounts Offices in Khyber Pakhtunkhwa. |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 22.709 | 19 | 3.71 | 3.71 | 3.71 | 1.861 | 20.861 | 0 | 100% |
92% March - 2019 |
Substantially completed. |
No Image |
Construction of new building at Hangu | |||||||||||||||||||
292 (OG) |
150603-Construction / Renovation of Treasury / District Accounts Offices in Khyber Pakhtunkhwa. |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 22.709 | 19 | 3.71 | 3.71 | 3.71 | 1.861 | 20.861 | 0 | 100% |
92% March - 2019 |
Substantially completed. |
No Image |
Construction of new building at Hangu | |||||||||||||||||||
292 (OG) |
150603-Construction / Renovation of Treasury / District Accounts Offices in Khyber Pakhtunkhwa. |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 22.709 | 19 | 3.71 | 3.71 | 3.71 | 1.861 | 20.861 | 0 | 100% |
92% February - 2019 |
Substantially completed. |
No Image |
Construction of new building at Hangu | |||||||||||||||||||
292 (OG) |
150603-Construction / Renovation of Treasury / District Accounts Offices in Khyber Pakhtunkhwa. |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 22.709 | 19 | 3.71 | 3.71 | 3.71 | 1.9 | 20.9 | 0 | 100% |
92% January - 2019 |
Substantially completed. |
No Image |
Construction of new building at Hangu | |||||||||||||||||||
292 (OG) |
150603-Construction / Renovation of Treasury / District Accounts Offices in Khyber Pakhtunkhwa. |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 7.8 | 3 | 3 | 3 | 3 | 0.4 | 3.4 | 1.8 | 77% |
44% December - 2018 |
Plastering in progress. |
No Image |
Strong Room / Guard Room at Treasury Building Kohat | |||||||||||||||||||
292 (OG) |
150603-Construction / Renovation of Treasury / District Accounts Offices in Khyber Pakhtunkhwa. |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 7.8 | 3 | 0 | 0 | 0 | 0 | 3 | 4.8 | - |
38% November - 2018 |
Plastering in progress. |
No Image |
Strong Room / Guard Room at Treasury Building Kohat | |||||||||||||||||||
292 (OG) |
150603-Construction / Renovation of Treasury / District Accounts Offices in Khyber Pakhtunkhwa. |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 7.8 | 3 | 0 | 0 | 0 | 0 | 3 | 4.8 | - |
38% November - 2018 |
Plastering in progress. |
No Image |
Strong Room / Guard Room at Treasury Building Kohat | |||||||||||||||||||
292 (OG) |
150603-Construction / Renovation of Treasury / District Accounts Offices in Khyber Pakhtunkhwa. |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 7.8 | 3 | 3 | 3 | 3 | 0.4 | 3.4 | 1.8 | 77% |
44% April - 2019 |
Plastering in progress. |
No Image |
Strong Room / Guard Room at Treasury Building Kohat | |||||||||||||||||||
292 (OG) |
150603-Construction / Renovation of Treasury / District Accounts Offices in Khyber Pakhtunkhwa. |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 7.8 | 3 | 3 | 3 | 3 | 0.4 | 3.4 | 1.8 | 77% |
44% March - 2019 |
Flooring in progress. |
No Image |
Strong Room / Guard Room at Treasury Building Kohat | |||||||||||||||||||
292 (OG) |
150603-Construction / Renovation of Treasury / District Accounts Offices in Khyber Pakhtunkhwa. |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 7.8 | 3 | 3 | 3 | 3 | 0.4 | 3.4 | 1.8 | 77% |
44% March - 2019 |
Flooring in progress. |
No Image |
Strong Room / Guard Room at Treasury Building Kohat | |||||||||||||||||||
292 (OG) |
150603-Construction / Renovation of Treasury / District Accounts Offices in Khyber Pakhtunkhwa. |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 7.8 | 3 | 3 | 3 | 3 | 0.4 | 3.4 | 1.8 | 77% |
44% February - 2019 |
Flooring in progress. |
No Image |
Strong Room / Guard Room at Treasury Building Kohat | |||||||||||||||||||
292 (OG) |
150603-Construction / Renovation of Treasury / District Accounts Offices in Khyber Pakhtunkhwa. |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 7.8 | 3 | 3 | 3 | 3 | 0.4 | 3.4 | 1.8 | 77% |
44% January - 2019 |
Flooring in progress. |
No Image |
Strong Room / Guard Room at Treasury Building Kohat | |||||||||||||||||||
292 (OG) |
150603-Construction / Renovation of Treasury / District Accounts Offices in Khyber Pakhtunkhwa. |
Lakki Marwat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 4.975 | 4.831 | 0 | 0 | 0 | 0 | 4.831 | 0.144 | - |
97% December - 2018 |
Completed & H/O. |
No Image |
Construction of Strong Room for District Accounts Office PK-75 Lakki Marwat | |||||||||||||||||||
292 (OG) |
150603-Construction / Renovation of Treasury / District Accounts Offices in Khyber Pakhtunkhwa. |
Lakki Marwat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 4.975 | 4.831 | 0 | 0 | 0 | 0 | 4.831 | 0.144 | - |
97% November - 2018 |
Completed & H/O. |
No Image |
Construction of Strong Room for District Accounts Office PK-75 Lakki Marwat | |||||||||||||||||||
Pages : 1 2 |