Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
301 (OG) |
140612-Establishment of 160 Govt. Primary Schools (B&G) on need basis in Khyber Pakhtunkhwa (Phase-IV). |
Abbottabad |
16-09-15 | - | - | 28-08-14 | - | 112.2 | 52.675 | 10.179 | 10.179 | 10.179 | 10.124 | 62.799 | 49.346 | 56% |
56% December - 2017 |
Out of 11 units, 9 in progress, 3 work order issued. |
No Image |
1) GGPS Missar UC Kuthila PK-46
2) GPS Mehal UC Chammad PK-46
3) GGPS Keri UC Nara PK-47
4) GGPS Tikhar | |||||||||||||||||||
301 (OG) |
140612-Establishment of 160 Govt. Primary Schools (B&G) on need basis in Khyber Pakhtunkhwa (Phase-IV). |
Abbottabad |
16-09-15 | - | - | 28-08-14 | - | 112.2 | 52.675 | 10.179 | 10.179 | 10.179 | 5.065 | 57.74 | 49.346 | 56% |
51% September - 2017 |
Out of 11 units, 9 in progress, 3 work order issued. |
No Image |
1) GGPS Missar UC Kuthila PK-46
2) GPS Mehal UC Chammad PK-46
3) GGPS Keri UC Nara PK-47
4) GGPS Tikhar | |||||||||||||||||||
301 (OG) |
140612-Establishment of 160 Govt. Primary Schools (B&G) on need basis in Khyber Pakhtunkhwa (Phase-IV). |
Abbottabad |
16-09-15 | - | - | 28-08-14 | - | 112.2 | 52.675 | 10.179 | 10.179 | 10.179 | 0 | 52.675 | 49.346 | 56% |
47% August - 2017 |
Out of 11 units, 9 in progress, 3 work order issued. |
No Image |
1) GGPS Missar UC Kuthila PK-46
2) GPS Mehal UC Chammad PK-46
3) GGPS Keri UC Nara PK-47
4) GGPS Tikhar | |||||||||||||||||||
301 (OG) |
140612-Establishment of 160 Govt. Primary Schools (B&G) on need basis in Khyber Pakhtunkhwa (Phase-IV). |
Abbottabad |
16-09-15 | - | - | 28-08-14 | - | 112.2 | 52.675 | 0 | 0 | 0 | 0 | 52.675 | 59.525 | - |
47% July - 2017 |
Out of 11 units, 9 in progress, 3 work order issued. |
No Image |
1) GGPS Missar UC Kuthila PK-46
2) GPS Mehal UC Chammad PK-46
3) GGPS Keri UC Nara PK-47
4) GGPS Tikhar | |||||||||||||||||||
301 (OG) |
140612-Establishment of 160 Govt. Primary Schools (B&G) on need basis in Khyber Pakhtunkhwa (Phase-IV). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 112.2 | 52.675 | 10.179 | 10.179 | 10.179 | 10.124 | 62.799 | 49.346 | 56% |
56% November - 2017 |
Out of 11 units, 9 in progress, 3 work order issued. |
No Image |
1) GGPS Missar UC Kuthila PK-46
2) GPS Mehal UC Chammad PK-46
3) GGPS Keri UC Nara PK-47
4) GGPS Tikhar | |||||||||||||||||||
301 (OG) |
140612-Establishment of 160 Govt. Primary Schools (B&G) on need basis in Khyber Pakhtunkhwa (Phase-IV). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 112.2 | 52.675 | 10.179 | 10.179 | 10.179 | 5.065 | 57.74 | 49.346 | 56% |
51% October - 2017 |
Out of 11 units, 9 in progress, 3 work order issued. |
No Image |
1) GGPS Missar UC Kuthila PK-46
2) GPS Mehal UC Chammad PK-46
3) GGPS Keri UC Nara PK-47
4) GGPS Tikhar | |||||||||||||||||||
301 (OG) |
140612-Establishment of 160 Govt. Primary Schools (B&G) on need basis in Khyber Pakhtunkhwa (Phase-IV). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 112.2 | 52.675 | 26.837 | 26.837 | 26.837 | 26.836 | 79.511 | 32.688 | 71% |
71% June - 2018 |
Out of 10 units, 9 in progress, 3 work order issued. |
No Image |
1) GGPS Missar UC Kuthila PK-46
2) GGPS Keri UC Nara PK-47 shifted to Kehan
3) GPS Borrian PK-48
4) GPS Guddi PK-44
5) GPS Thoya Balolia PK-44
6) GPS Mengal Dara PK-46
7) GPS Mohallah Noor Din Bazar PK-44
8) GGPS Deedal Masan PK-45
9) GGPS Mast Maira PK-46 shifted to Bodia Kuhmar Bandi
10) GGPS Lundi Mundri PK-45 | |||||||||||||||||||
301 (OG) |
140612-Establishment of 160 Govt. Primary Schools (B&G) on need basis in Khyber Pakhtunkhwa (Phase-IV). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 112.2 | 52.675 | 26.928 | 26.928 | 26.928 | 21.491 | 74.166 | 32.597 | 71% |
66% May - 2018 |
Out of 10 units, 9 in progress, 3 work order issued. |
No Image |
1) GGPS Missar UC Kuthila PK-46
2) GGPS Keri UC Nara PK-47 shifted to Kehan
3) GPS Borrian PK-48
4) GPS Guddi PK-44
5) GPS Thoya Balolia PK-44
6) GPS Mengal Dara PK-46
7) GPS Mohallah Noor Din Bazar PK-44
8) GGPS Deedal Masan PK-45
9) GGPS Mast Maira PK-46 shifted to Bodia Kuhmar Bandi
10) GGPS Lundi Mundri PK-45 | |||||||||||||||||||
301 (OG) |
140612-Establishment of 160 Govt. Primary Schools (B&G) on need basis in Khyber Pakhtunkhwa (Phase-IV). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 112.2 | 52.675 | 26.928 | 26.928 | 26.928 | 21.491 | 74.166 | 32.597 | 71% |
66% April - 2018 |
Out of 10 units, 9 in progress, 3 work order issued. |
No Image |
1) GGPS Missar UC Kuthila PK-46
2) GGPS Keri UC Nara PK-47 shifted to Kehan
3) GPS Borrian PK-48
4) GPS Guddi PK-44
5) GPS Thoya Balolia PK-44
6) GPS Mengal Dara PK-46
7) GPS Mohallah Noor Din Bazar PK-44
8) GGPS Deedal Masan PK-45
9) GGPS Mast Maira PK-46 shifted to Bodia Kuhmar Bandi
10) GGPS Lundi Mundri PK-45 | |||||||||||||||||||
301 (OG) |
140612-Establishment of 160 Govt. Primary Schools (B&G) on need basis in Khyber Pakhtunkhwa (Phase-IV). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 112.2 | 52.675 | 26.928 | 26.928 | 26.928 | 17.575 | 70.25 | 32.597 | 71% |
63% March - 2018 |
Out of 10 units, 9 in progress, 3 work order issued. |
No Image |
1) GGPS Missar UC Kuthila PK-46
2) GGPS Keri UC Nara PK-47 shifted to Kehan
3) GPS Borrian PK-48
4) GPS Guddi PK-44
5) GPS Thoya Balolia PK-44
6) GPS Mengal Dara PK-46
7) GPS Mohallah Noor Din Bazar PK-44
8) GGPS Deedal Masan PK-45
9) GGPS Mast Maira PK-46 shifted to Bodia Kuhmar Bandi
10) GGPS Lundi Mundri PK-45 | |||||||||||||||||||
301 (OG) |
140612-Establishment of 160 Govt. Primary Schools (B&G) on need basis in Khyber Pakhtunkhwa (Phase-IV). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 112.2 | 52.675 | 26.928 | 26.928 | 26.928 | 15.002 | 67.677 | 32.597 | 71% |
60% February - 2018 |
Out of 10 units, 9 in progress, 3 work order issued. |
No Image |
1) GGPS Missar UC Kuthila PK-46
2) GGPS Keri UC Nara PK-47 shifted to Kehan
3) GPS Borrian PK-48
4) GPS Guddi PK-44
5) GPS Thoya Balolia PK-44
6) GPS Mengal Dara PK-46
7) GPS Mohallah Noor Din Bazar PK-44
8) GGPS Deedal Masan PK-45
9) GGPS Mast Maira PK-46 shifted to Bodia Kuhmar Bandi
10) GGPS Lundi Mundri PK-45 | |||||||||||||||||||
301 (OG) |
140612-Establishment of 160 Govt. Primary Schools (B&G) on need basis in Khyber Pakhtunkhwa (Phase-IV). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 112.2 | 52.675 | 10.179 | 10.179 | 10.179 | 10.124 | 62.799 | 49.346 | 56% |
56% January - 2018 |
Out of 11 units, 9 in progress, 3 work order issued. |
No Image |
1) GGPS Missar UC Kuthila PK-46 2) GGPS Keri UC Nara PK-47 shifted toKehan 3) GPS Borrian PK-48 4) GPS Guddi PK-44 5) GPS Thoya Balolia PK-44 6) GPS Mengal Dara PK-46 7) GPS Mohallah Noor Din Bazar PK-44 8) GGPS Deedal Masan PK-45 9) GGPS Mast Maira PK-46 shifted to Bodia Kuhmar Bandi 10) GGPSLundi Mundri PK-45 | |||||||||||||||||||
301 (OG) |
140612-Establishment of 160 Govt. Primary Schools (B&G) on need basis in Khyber Pakhtunkhwa (Phase-IV). |
Bannu |
24-01-15 | - | - | 28-08-14 | - | 93.77 | 75.104 | 2.309 | 2.309 | 2.309 | 2.309 | 77.413 | 16.357 | 83% |
83% December - 2017 |
Out of 7 units, 2 completed, 5 in progress. Demand Rs.20 m. |
No Image |
1) GGPS Haji Ayub Murib Khel PK-72
2) GGPS Ferdoos Kamal Sarki Khel Chata Khel PK-71
3) GGPS Sherin Malik Sardi Khel PK-72
4) GGPS Hakumat Khan Khadri Muhammad Khel Domanza PK-72
5) GGPS Nar Faizullah Haroon Abad Nar Jafar | |||||||||||||||||||
301 (OG) |
140612-Establishment of 160 Govt. Primary Schools (B&G) on need basis in Khyber Pakhtunkhwa (Phase-IV). |
Bannu |
24-01-15 | - | - | 28-08-14 | - | 93.77 | 75.104 | 2.309 | 2.309 | 2.309 | 1.13 | 76.234 | 16.357 | 83% |
81% September - 2017 |
Out of 7 units, 2 completed, 5 in progress. |
No Image |
1) GGPS Haji Ayub Murib Khel PK-72
2) GGPS Ferdoos Kamal Sarki Khel Chata Khel PK-71
3) GGPS Sherin Malik Sardi Khel PK-72
4) GGPS Hakumat Khan Khadri Muhammad Khel Domanza PK-72
5) GGPS Nar Faizullah Haroon Abad Nar Jafar | |||||||||||||||||||
301 (OG) |
140612-Establishment of 160 Govt. Primary Schools (B&G) on need basis in Khyber Pakhtunkhwa (Phase-IV). |
Bannu |
24-01-15 | - | - | 28-08-14 | - | 93.77 | 75.104 | 2.309 | 2.309 | 2.309 | 1.13 | 76.234 | 16.357 | 83% |
81% August - 2017 |
Out of 7 units, 2 completed, 5 in progress. |
No Image |
1) GGPS Haji Ayub Murib Khel PK-72
2) GGPS Ferdoos Kamal Sarki Khel Chata Khel PK-71
3) GGPS Sherin Malik Sardi Khel PK-72
4) GGPS Hakumat Khan Khadri Muhammad Khel Domanza PK-72
5) GGPS Nar Faizullah Haroon Abad Nar Jafar | |||||||||||||||||||
301 (OG) |
140612-Establishment of 160 Govt. Primary Schools (B&G) on need basis in Khyber Pakhtunkhwa (Phase-IV). |
Bannu |
24-01-15 | - | - | 28-08-14 | - | 93.77 | 75.104 | 0 | 0 | 0 | 0 | 75.104 | 18.666 | - |
80% July - 2017 |
Out of 7 units, 2 completed, 5 in progress. |
No Image |
1) GGPS Haji Ayub Murib Khel PK-72
2) GGPS Ferdoos Kamal Sarki Khel Chata Khel PK-71
3) GGPS Sherin Malik Sardi Khel PK-72
4) GGPS Hakumat Khan Khadri Muhammad Khel Domanza PK-72
5) GGPS Nar Faizullah Haroon Abad Nar Jafar | |||||||||||||||||||
301 (OG) |
170614-Construction of Food Grain Godowns of 3000 Ton Capacity in District Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 127.117 | 7.5 | 30 | 30 | 10 | 10 | 17.5 | 89.617 | 30% |
14% December - 2018 |
Raft foundation completed. Columns in progress. |
No Image |
Construction of Food Grain Godown at Nar Hafiz Abad PK-71 | |||||||||||||||||||
301 (OG) |
140612-Establishment of 160 Govt. Primary Schools (B&G) on need basis in Khyber Pakhtunkhwa (Phase-IV). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 93.77 | 75.104 | 2.309 | 2.309 | 2.309 | 2.309 | 77.413 | 16.357 | 83% |
83% November - 2017 |
Out of 7 units, 2 completed, 5 in progress. |
No Image |
1) GGPS Haji Ayub Murib Khel PK-72
2) GGPS Ferdoos Kamal Sarki Khel Chata Khel PK-71
3) GGPS Sherin Malik Sardi Khel PK-72
4) GGPS Hakumat Khan Khadri Muhammad Khel Domanza PK-72
5) GGPS Nar Faizullah Haroon Abad Nar Jafar | |||||||||||||||||||
301 (OG) |
170614-Construction of Food Grain Godowns of 3000 Ton Capacity in District Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 127.117 | 7.5 | 30 | 30 | 20 | 10 | 17.5 | 89.617 | 30% |
14% November - 2018 |
Raft foundation completed. Columns in progress. |
No Image |
Construction of Food Grain Godown at Nar Hafiz Abad PK-71 | |||||||||||||||||||
301 (OG) |
170614-Construction of Food Grain Godowns of 3000 Ton Capacity in District Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 127.117 | 7.5 | 30 | 30 | 20 | 10 | 17.5 | 89.617 | 30% |
14% November - 2018 |
Raft foundation completed. Columns in progress. |
No Image |
Construction of Food Grain Godown at Nar Hafiz Abad PK-71 | |||||||||||||||||||
301 (OG) |
140612-Establishment of 160 Govt. Primary Schools (B&G) on need basis in Khyber Pakhtunkhwa (Phase-IV). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 93.77 | 75.104 | 2.309 | 2.309 | 2.309 | 2.043 | 77.147 | 16.357 | 83% |
82% October - 2017 |
Out of 7 units, 2 completed, 5 in progress. |
No Image |
1) GGPS Haji Ayub Murib Khel PK-72
2) GGPS Ferdoos Kamal Sarki Khel Chata Khel PK-71
3) GGPS Sherin Malik Sardi Khel PK-72
4) GGPS Hakumat Khan Khadri Muhammad Khel Domanza PK-72
5) GGPS Nar Faizullah Haroon Abad Nar Jafar | |||||||||||||||||||
301 (OG) |
140612-Establishment of 160 Govt. Primary Schools (B&G) on need basis in Khyber Pakhtunkhwa (Phase-IV). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 97.77 | 75.104 | 7.887 | 7.887 | 7.887 | 6.747 | 81.851 | 14.779 | 85% |
84% June - 2018 |
Out of 7 units, 3 completed, 4 in progress. |
No Image |
1) GGPS Haji Ayub Murib Khel PK-72
2) GGPS Firdous Kamal Sarki Khel Chata Khel PK-71
3) GGPS Sherian Malik Sardi Khel PK-72
4) GGPS Hakomat Khan Khadri Muhammad Khel Domanza PK-72
5) GGPS Nar Faizullah Haroon Abad Nar Jafar PK-73
6) GPS Kotka Amir Mukhtar Lalozai PK-70
7) GGPS Rauf Khan Ghari Mir Alam PK-73 | |||||||||||||||||||
301 (OG) |
140612-Establishment of 160 Govt. Primary Schools (B&G) on need basis in Khyber Pakhtunkhwa (Phase-IV). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 97.77 | 75.104 | 7.887 | 7.887 | 7.887 | 5.068 | 80.172 | 14.779 | 85% |
82% May - 2018 |
Out of 7 units, 2 completed, 5 in progress. Demand Rs.20 m. |
No Image |
1) GGPS Haji Ayub Murib Khel PK-72
2) GGPS Firdous Kamal Sarki Khel Chata Khel PK-71
3) GGPS Sherian Malik Sardi Khel PK-72
4) GGPS Hakomat Khan Khadri Muhammad Khel Domanza PK-72
5) GGPS Nar Faizullah Haroon Abad Nar Jafar PK-73
6) GPS Kotka Amir Mukhtar Lalozai PK-70
7) GGPS Rauf Khan Ghari Mir Alam PK-73 | |||||||||||||||||||
301 (OG) |
140612-Establishment of 160 Govt. Primary Schools (B&G) on need basis in Khyber Pakhtunkhwa (Phase-IV). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 97.77 | 75.104 | 7.887 | 7.887 | 7.887 | 4.84 | 79.944 | 14.779 | 85% |
82% April - 2018 |
Out of 7 units, 2 completed, 5 in progress. Demand Rs.20 m. |
No Image |
1) GGPS Haji Ayub Murib Khel PK-72
2) GGPS Firdous Kamal Sarki Khel Chata Khel PK-71
3) GGPS Sherian Malik Sardi Khel PK-72
4) GGPS Hakomat Khan Khadri Muhammad Khel Domanza PK-72
5) GGPS Nar Faizullah Haroon Abad Nar Jafar PK-73
6) GPS Kotka Amir Mukhtar Lalozai PK-70
7) GGPS Rauf Khan Ghari Mir Alam PK-73 | |||||||||||||||||||
301 (OG) |
170614-Construction of Food Grain Godowns of 3000 Ton Capacity in District Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 127.117 | 7.5 | 30 | 30 | 20 | 20 | 27.5 | 89.617 | 30% |
22% April - 2019 |
Raft foundation completed. Columns, plinth beam in progress. Demand Rs.20 m. |
No Image |
Construction of Food Grain Godown at Nar Hafiz Abad PK-71 | |||||||||||||||||||
301 (OG) |
140612-Establishment of 160 Govt. Primary Schools (B&G) on need basis in Khyber Pakhtunkhwa (Phase-IV). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 97.77 | 75.104 | 7.887 | 7.887 | 7.887 | 4.604 | 79.708 | 14.779 | 85% |
82% March - 2018 |
Out of 7 units, 2 completed, 5 in progress. Demand Rs.20 m. |
No Image |
1) GGPS Haji Ayub Murib Khel PK-72
2) GGPS Firdous Kamal Sarki Khel Chata Khel PK-71
3) GGPS Sherian Malik Sardi Khel PK-72
4) GGPS Hakomat Khan Khadri Muhammad Khel Domanza PK-72
5) GGPS Nar Faizullah Haroon Abad Nar Jafar PK-73
6) GPS Kotka Amir Mukhtar Lalozai PK-70
7) GGPS Rauf Khan Ghari Mir Alam PK-73 | |||||||||||||||||||
301 (OG) |
170614-Construction of Food Grain Godowns of 3000 Ton Capacity in District Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 127.117 | 7.5 | 30 | 30 | 20 | 20 | 27.5 | 89.617 | 30% |
22% March - 2019 |
Raft foundation completed. Columns, plinth beam in progress. Demand Rs. 20 M |
No Image |
Construction of Food Grain Godown at Nar Hafiz Abad PK-71 | |||||||||||||||||||
301 (OG) |
170614-Construction of Food Grain Godowns of 3000 Ton Capacity in District Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 127.117 | 7.5 | 30 | 30 | 20 | 20 | 27.5 | 89.617 | 30% |
22% March - 2019 |
Raft foundation completed. Columns, plinth beam in progress. Demand Rs. 20 M |
No Image |
Construction of Food Grain Godown at Nar Hafiz Abad PK-71 | |||||||||||||||||||
301 (OG) |
140612-Establishment of 160 Govt. Primary Schools (B&G) on need basis in Khyber Pakhtunkhwa (Phase-IV). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 97.77 | 75.104 | 4.963 | 4.963 | 4.963 | 4.604 | 79.708 | 17.703 | 82% |
82% February - 2018 |
Out of 7 units, 2 completed, 5 in progress. Demand Rs.20 m. |
No Image |
1) GGPS Haji Ayub Murib Khel PK-72
2) GGPS Firdous Kamal Sarki Khel Chata Khel PK-71
3) GGPS Sherian Malik Sardi Khel PK-72
4) GGPS Hakomat Khan Khadri Muhammad Khel Domanza PK-72
5) GGPS Nar Faizullah Haroon Abad Nar Jafar PK-73
6) GPS Kotka Amir Mukhtar Lalozai PK-70
7) GGPS Rauf Khan Ghari Mir Alam PK-73 | |||||||||||||||||||
301 (OG) |
170614-Construction of Food Grain Godowns of 3000 Ton Capacity in District Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 127.117 | 7.5 | 30 | 30 | 20 | 20 | 27.5 | 89.617 | 30% |
22% February - 2019 |
Raft foundation completed. Columns, plinth beam in progress. |
No Image |
Construction of Food Grain Godown at Nar Hafiz Abad PK-71 | |||||||||||||||||||
301 (OG) |
140612-Establishment of 160 Govt. Primary Schools (B&G) on need basis in Khyber Pakhtunkhwa (Phase-IV). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 93.77 | 75.104 | 2.309 | 2.309 | 2.309 | 2.309 | 77.413 | 16.357 | 83% |
83% January - 2018 |
Out of 7 units, 2 completed, 5 in progress. Demand Rs.20 m. |
No Image |
1) GGPS Haji Ayub Murib Khel PK-72 2) GGPS Ferdoos Kamal Sarki Khel Chata Khel PK-71 3) GGPS Sherin Malik Sardi Khel PK-72 4) GGPS Hakumat Khan Khadri Muhammad Khel Domanza PK-72 5) GGPS Nar Faizullah Haroon Abad Nar Jafar | |||||||||||||||||||
301 (OG) |
170614-Construction of Food Grain Godowns of 3000 Ton Capacity in District Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 127.117 | 7.5 | 30 | 30 | 20 | 17.384 | 24.884 | 89.617 | 30% |
20% January - 2019 |
Raft foundation completed. Columns in progress. |
No Image |
Construction of Food Grain Godown at Nar Hafiz Abad PK-71 | |||||||||||||||||||
301 (OG) |
140612-Establishment of 160 Govt. Primary Schools (B&G) on need basis in Khyber Pakhtunkhwa (Phase-IV). |
Battagram |
08-08-15 | - | - | 28-08-14 | - | 28.47 | 17.262 | 2.603 | 2.603 | 2.603 | 2.587 | 19.849 | 8.605 | 70% |
70% December - 2017 |
Out of 2 units, all in progress. |
No Image |
1) GPS Jabba Sher Muhammad PK-59
2) GPS Ghanam Rangay PK-60 | |||||||||||||||||||
301 (OG) |
140612-Establishment of 160 Govt. Primary Schools (B&G) on need basis in Khyber Pakhtunkhwa (Phase-IV). |
Battagram |
08-08-15 | - | - | 28-08-14 | - | 28.47 | 17.262 | 2.587 | 2.587 | 2.587 | 1.518 | 18.78 | 8.621 | 70% |
66% September - 2017 |
Out of 2 units, all in progress. |
No Image |
1) GPS Jabba Sher Muhammad PK-59
2) GPS Ghanam Rangay PK-60 | |||||||||||||||||||
301 (OG) |
140612-Establishment of 160 Govt. Primary Schools (B&G) on need basis in Khyber Pakhtunkhwa (Phase-IV). |
Battagram |
08-08-15 | - | - | 28-08-14 | - | 28.47 | 17.262 | 2.587 | 2.587 | 2.587 | 1.518 | 18.78 | 8.621 | 70% |
66% August - 2017 |
Out of 2 units, all in progress. |
No Image |
1) GPS Jabba Sher Muhammad PK-59
2) GPS Ghanam Rangay PK-60 | |||||||||||||||||||
301 (OG) |
140612-Establishment of 160 Govt. Primary Schools (B&G) on need basis in Khyber Pakhtunkhwa (Phase-IV). |
Battagram |
08-08-15 | - | - | 28-08-14 | - | 28.47 | 17.262 | 0 | 0 | 0 | 0 | 17.262 | 11.208 | - |
61% July - 2017 |
Out of 2 units, all in progress. |
No Image |
1) GPS Jabba Sher Muhammad PK-59
2) GPS Ghanam Rangay PK-60 | |||||||||||||||||||
301 (OG) |
140612-Establishment of 160 Govt. Primary Schools (B&G) on need basis in Khyber Pakhtunkhwa (Phase-IV). |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 28.47 | 17.262 | 2.603 | 2.603 | 2.603 | 1.907 | 19.169 | 8.605 | 70% |
67% November - 2017 |
Out of 2 units, all in progress. |
No Image |
1) GPS Jabba Sher Muhammad PK-59
2) GPS Ghanam Rangay PK-60 | |||||||||||||||||||
301 (OG) |
140612-Establishment of 160 Govt. Primary Schools (B&G) on need basis in Khyber Pakhtunkhwa (Phase-IV). |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 28.47 | 17.262 | 2.587 | 2.587 | 2.587 | 1.907 | 19.169 | 8.621 | 70% |
67% October - 2017 |
Out of 2 units, all in progress. |
No Image |
1) GPS Jabba Sher Muhammad PK-59
2) GPS Ghanam Rangay PK-60 | |||||||||||||||||||
301 (OG) |
140612-Establishment of 160 Govt. Primary Schools (B&G) on need basis in Khyber Pakhtunkhwa (Phase-IV). |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 28.47 | 17.269 | 2.587 | 2.587 | 2.587 | 2.587 | 19.856 | 8.614 | 70% |
70% June - 2018 |
Out of 2 units, all in progress. |
No Image |
1) GPS Jabba Sher Muhammad PK-59
2) GPS Ghanam Rangay PK-60 | |||||||||||||||||||
301 (OG) |
140612-Establishment of 160 Govt. Primary Schools (B&G) on need basis in Khyber Pakhtunkhwa (Phase-IV). |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 28.47 | 17.269 | 2.587 | 2.587 | 2.587 | 2.587 | 19.856 | 8.614 | 70% |
70% May - 2018 |
Out of 2 units, all in progress. |
No Image |
1) GPS Jabba Sher Muhammad PK-59
2) GPS Ghanam Rangay PK-60 | |||||||||||||||||||
301 (OG) |
140612-Establishment of 160 Govt. Primary Schools (B&G) on need basis in Khyber Pakhtunkhwa (Phase-IV). |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 28.47 | 17.269 | 2.587 | 2.587 | 2.587 | 2.587 | 19.856 | 8.614 | 70% |
70% April - 2018 |
Out of 2 units, all in progress. |
No Image |
1) GPS Jabba Sher Muhammad PK-59
2) GPS Ghanam Rangay PK-60 | |||||||||||||||||||
301 (OG) |
140612-Establishment of 160 Govt. Primary Schools (B&G) on need basis in Khyber Pakhtunkhwa (Phase-IV). |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 28.47 | 17.269 | 5.524 | 5.524 | 5.524 | 2.587 | 19.856 | 5.677 | 80% |
70% March - 2018 |
Out of 2 units, all in progress. |
No Image |
1) GPS Jabba Sher Muhammad PK-59
2) GPS Ghanam Rangay PK-60 | |||||||||||||||||||
301 (OG) |
140612-Establishment of 160 Govt. Primary Schools (B&G) on need basis in Khyber Pakhtunkhwa (Phase-IV). |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 28.47 | 17.269 | 5.524 | 5.524 | 5.524 | 2.587 | 19.856 | 5.677 | 80% |
70% February - 2018 |
Out of 2 units, all in progress. |
No Image |
1) GPS Jabba Sher Muhammad PK-59
2) GPS Ghanam Rangay PK-60 | |||||||||||||||||||
301 (OG) |
140612-Establishment of 160 Govt. Primary Schools (B&G) on need basis in Khyber Pakhtunkhwa (Phase-IV). |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 28.47 | 17.262 | 2.603 | 2.603 | 2.603 | 2.587 | 19.849 | 8.605 | 70% |
70% January - 2018 |
Out of 2 units, all in progress. |
No Image |
1) GPS Jabba Sher Muhammad PK-59 2) GPS Ghanam Rangay PK-60 | |||||||||||||||||||
301 (OG) |
140612-Establishment of 160 Govt. Primary Schools (B&G) on need basis in Khyber Pakhtunkhwa (Phase-IV). |
Buner |
10-08-15 | - | - | 28-08-14 | - | 78.25 | 33.549 | 2.425 | 2.425 | 2.425 | 1.896 | 35.445 | 42.276 | 46% |
45% December - 2017 |
Out of 6 units, all in progress. |
No Image |
1) GGPS Gir Ray Ghazi Kot PK-77
2) GPS Naraj Golono Buraray PK-78
3) GPS Manzaray Jabba Battai PK-79
4) GPS Dhand Maira Matwanai PK-78
5) GPS Shalbandai No.2 PK-78
6) GPS Khaista Baba PK-78 | |||||||||||||||||||
301 (OG) |
140612-Establishment of 160 Govt. Primary Schools (B&G) on need basis in Khyber Pakhtunkhwa (Phase-IV). |
Buner |
10-08-15 | - | - | 28-08-14 | - | 78.25 | 33.549 | 2.425 | 2.425 | 2.425 | 1.176 | 34.725 | 42.276 | 46% |
44% September - 2017 |
Out of 6 units, all in progress. |
No Image |
1) GGPS Gir Ray Ghazi Kot PK-77
2) GPS Naraj Golono Buraray PK-78
3) GPS Manzaray Jabba Battai PK-79
4) GPS Dhand Maira Matwanai PK-78
5) GPS Shalbandai No.2 PK-78
6) GPS Khaista Baba PK-78 | |||||||||||||||||||
301 (OG) |
140612-Establishment of 160 Govt. Primary Schools (B&G) on need basis in Khyber Pakhtunkhwa (Phase-IV). |
Buner |
10-08-15 | - | - | 28-08-14 | - | 78.25 | 33.549 | 2.425 | 2.425 | 2.425 | 1.176 | 34.725 | 42.276 | 46% |
44% August - 2017 |
Out of 6 units, all in progress. |
No Image |
1) GGPS Gir Ray Ghazi Kot PK-77
2) GPS Naraj Golono Buraray PK-78
3) GPS Manzaray Jabba Battai PK-79
4) GPS Dhand Maira Matwanai PK-78
5) GPS Shalbandai No.2 PK-78
6) GPS Khaista Baba PK-78 | |||||||||||||||||||
301 (OG) |
140612-Establishment of 160 Govt. Primary Schools (B&G) on need basis in Khyber Pakhtunkhwa (Phase-IV). |
Buner |
10-08-15 | - | - | 28-08-14 | - | 78.25 | 33.549 | 0 | 0 | 0 | 0 | 33.549 | 44.701 | - |
43% July - 2017 |
Out of 6 units, all in progress. |
No Image |
1) GGPS Gir Ray Ghazi Kot PK-77
2) GPS Naraj Golono Buraray PK-78
3) GPS Manzaray Jabba Battai PK-79
4) GPS Dhand Maira Matwanai PK-78
5) GPS Shalbandai No.2 PK-78
6) GPS Khaista Baba PK-78 | |||||||||||||||||||
301 (OG) |
140612-Establishment of 160 Govt. Primary Schools (B&G) on need basis in Khyber Pakhtunkhwa (Phase-IV). |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 78.25 | 33.549 | 2.425 | 2.425 | 2.425 | 1.896 | 35.445 | 42.276 | 46% |
45% November - 2017 |
Out of 6 units, all in progress. |
No Image |
1) GGPS Gir Ray Ghazi Kot PK-77
2) GPS Naraj Golono Buraray PK-78
3) GPS Manzaray Jabba Battai PK-79
4) GPS Dhand Maira Matwanai PK-78
5) GPS Shalbandai No.2 PK-78
6) GPS Khaista Baba PK-78 | |||||||||||||||||||
301 (OG) |
140612-Establishment of 160 Govt. Primary Schools (B&G) on need basis in Khyber Pakhtunkhwa (Phase-IV). |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 78.25 | 33.549 | 2.425 | 2.425 | 2.425 | 1.896 | 35.445 | 42.276 | 46% |
45% October - 2017 |
Out of 6 units, all in progress. |
No Image |
1) GGPS Gir Ray Ghazi Kot PK-77
2) GPS Naraj Golono Buraray PK-78
3) GPS Manzaray Jabba Battai PK-79
4) GPS Dhand Maira Matwanai PK-78
5) GPS Shalbandai No.2 PK-78
6) GPS Khaista Baba PK-78 | |||||||||||||||||||