Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
307 (OG) |
170608-Construction of Food Grain Godowns of 9000 Ton Capacity in District Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 315 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- December - 2018 |
Site identified 20 Kanal but not yet H/O. |
No Image |
Food Grain Godown Dir Upper (9000 ton capacity) | |||||||||||||||||||
307 (OG) |
170608-Construction of Food Grain Godowns of 9000 Ton Capacity in District Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 315 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- November - 2018 |
PC-I/DCE submitted to Food Deptt. New site identified 20 Kanal but not yet H/O. |
No Image |
Food Grain Godown Dir Upper (9000 ton capacity) | |||||||||||||||||||
307 (OG) |
170608-Construction of Food Grain Godowns of 9000 Ton Capacity in District Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 315 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- November - 2018 |
PC-I/DCE submitted to Food Deptt. New site identified 20 Kanal but not yet H/O. |
No Image |
Food Grain Godown Dir Upper (9000 ton capacity) | |||||||||||||||||||
307 (OG) |
170608-Construction of Food Grain Godowns of 9000 Ton Capacity in District Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 315 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- April - 2019 |
Site identified 20 Kanal but not yet H/O. |
No Image |
Food Grain Godown Dir Upper (9000 ton capacity) | |||||||||||||||||||
307 (OG) |
170608-Construction of Food Grain Godowns of 9000 Ton Capacity in District Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 315 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- March - 2019 |
Site identified 20 Kanal but not yet H/O. |
No Image |
Food Grain Godown Dir Upper (9000 ton capacity) | |||||||||||||||||||
307 (OG) |
170608-Construction of Food Grain Godowns of 9000 Ton Capacity in District Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 315 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- March - 2019 |
Site identified 20 Kanal but not yet H/O. |
No Image |
Food Grain Godown Dir Upper (9000 ton capacity) | |||||||||||||||||||
307 (OG) |
170608-Construction of Food Grain Godowns of 9000 Ton Capacity in District Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 315 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- February - 2019 |
Site identified 20 Kanal but not yet H/O. |
No Image |
Food Grain Godown Dir Upper (9000 ton capacity) | |||||||||||||||||||
307 (OG) |
170608-Construction of Food Grain Godowns of 9000 Ton Capacity in District Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 315 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- January - 2019 |
Site identified 20 Kanal but not yet H/O. |
No Image |
Food Grain Godown Dir Upper (9000 ton capacity) | |||||||||||||||||||
307 (OG) |
80643-Upgradation of 10 BHUs to RHCs in Khyber Pakhtunkhwa on need basis. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 60.021 | 55.941 | 0 | 0 | 0 | 0 | 55.941 | 4.08 | - |
93% September - 2018 |
Completed & H/O (1 unit). |
No Image |
BHU Village Kangra PK-51 | |||||||||||||||||||
307 (OG) |
80643-Upgradation of 10 BHUs to RHCs in Khyber Pakhtunkhwa on need basis. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 60.021 | 55.941 | 0 | 0 | 0 | 0 | 55.941 | 4.08 | - |
93% July - 2018 |
Completed & H/O (1 unit). |
No Image |
BHU Village Kangra PK-51 | |||||||||||||||||||
307 (OG) |
80643-Upgradation of 10 BHUs to RHCs in Khyber Pakhtunkhwa on need basis. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 76.122 | 55.134 | 3 | 3 | 3 | 0 | 55.134 | 17.988 | 76% |
72% September - 2018 |
Finishing in progress. |
No Image |
BHU Naran PK-54 | |||||||||||||||||||
307 (OG) |
80643-Upgradation of 10 BHUs to RHCs in Khyber Pakhtunkhwa on need basis. |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 76.122 | 55.134 | 0 | 0 | 0 | 0 | 55.134 | 20.988 | - |
72% July - 2018 |
Finishing in progress. |
No Image |
BHU Naran PK-54 | |||||||||||||||||||
307 (OG) |
80643-Upgradation of 10 BHUs to RHCs in Khyber Pakhtunkhwa on need basis. |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 395.078 | 255.244 | 0 | 0 | 0 | 0 | 255.244 | 139.834 | - |
65% September - 2018 |
Out of 4 units, all in progress. Demolition in progress. |
No Image |
1) BHU Khazana Dheri PK-23
2) BHU Sheikh Yousaf PK-25 (site changed to Garhi Daulatzai PK-25)
3) BHU Bakshali Gaddar PK-30
4) BHU Sawal Dher PK-29 | |||||||||||||||||||
307 (OG) |
80643-Upgradation of 10 BHUs to RHCs in Khyber Pakhtunkhwa on need basis. |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 395.078 | 255.244 | 0 | 0 | 0 | 0 | 255.244 | 139.834 | - |
65% July - 2018 |
Out of 4 units, all in progress. Demolition in progress. |
No Image |
1) BHU Khazana Dheri PK-23
2) BHU Sheikh Yousaf PK-25 (site changed to Garhi Daulatzai PK-25)
3) BHU Bakshali Gaddar PK-30
4) BHU Sawal Dher PK-29 | |||||||||||||||||||
307 (OG) |
80643-Upgradation of 10 BHUs to RHCs in Khyber Pakhtunkhwa on need basis. |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 55.561 | 41.478 | 2 | 2 | 2 | 1.058 | 42.536 | 12.083 | 78% |
77% September - 2018 |
Main building - GF/FF finishing in progress. Residential portion - finishing in progress. Dev work in progress. |
No Image |
307 (OG) |
80643-Upgradation of 10 BHUs to RHCs in Khyber Pakhtunkhwa on need basis. |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 55.561 | 41.478 | 0 | 0 | 0 | 0 | 41.478 | 14.083 | - |
75% July - 2018 |
Main building - GF/FF finishing in progress. Residential portion - finishing in progress. Dev work in progress. |
No Image |
307 (OG) |
80643-Upgradation of 10 BHUs to RHCs in Khyber Pakhtunkhwa on need basis. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 980.409 | 542.348 | 10 | 10 | 0 | 0 | 542.348 | 0 | - |
- September - 2018 |
No Image | |
307 (OG) |
80643-Upgradation of 10 BHUs to RHCs in Khyber Pakhtunkhwa on need basis. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 980.409 | 542.348 | 10 | 10 | 0 | 0 | 542.348 | 0 | - |
- July - 2018 |
No Image | |
Pages : 1 |