Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
331 (OG) |
130339-Construction of 6 Cluster Hostels (Female) in Khyber Pakhtunkhwa on need basis (Phase-III). |
Buner |
- | 30-06-18 | - | 25-03-15 | - | 19.939 | 4.24 | 0 | 0 | 0 | 0 | 4.24 | 15.699 | - |
21% December - 2017 |
Work order issued. Site not cleared (GGHS Kalpani). |
No Image |
1) Construction of 1 Cluster Hostel (Female) in Buner | |||||||||||||||||||
331 (OG) |
130339-Construction of 6 Cluster Hostels (Female) in Khyber Pakhtunkhwa on need basis (Phase-III). |
Buner |
- | 30-06-18 | - | 25-03-15 | - | 19.939 | 4.24 | 0 | 0 | 0 | 0 | 4.24 | 15.699 | - |
21% September - 2017 |
Work order issued. Site not cleared (GGHS Kalpani). |
No Image |
1) Construction of 1 Cluster Hostel (Female) in Buner | |||||||||||||||||||
331 (OG) |
130339-Construction of 6 Cluster Hostels (Female) in Khyber Pakhtunkhwa on need basis (Phase-III). |
Buner |
- | 30-06-18 | - | 25-03-15 | - | 19.939 | 4.24 | 0 | 0 | 0 | 0 | 4.24 | 15.699 | - |
21% August - 2017 |
Work order issued. Site not cleared (GGHS Kalpani). |
No Image |
1) Construction of 1 Cluster Hostel (Female) in Buner | |||||||||||||||||||
331 (OG) |
130339-Construction of 6 Cluster Hostels (Female) in Khyber Pakhtunkhwa on need basis (Phase-III). |
Buner |
- | 30-06-18 | - | 25-03-15 | - | 19.939 | 4.24 | 0 | 0 | 0 | 0 | 4.24 | 15.699 | - |
21% July - 2017 |
Work order issued. Site not cleared (GGHS Kalpani). |
No Image |
1) Construction of 1 Cluster Hostel (Female) in Buner | |||||||||||||||||||
331 (OG) |
130339-Construction of 6 Cluster Hostels (Female) in Khyber Pakhtunkhwa on need basis (Phase-III). |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 19.939 | 4.24 | 0 | 0 | 0 | 0 | 4.24 | 15.699 | - |
21% November - 2017 |
Work order issued. Site not cleared (GGHS Kalpani). |
No Image |
1) Construction of 1 Cluster Hostel (Female) in Buner | |||||||||||||||||||
331 (OG) |
130339-Construction of 6 Cluster Hostels (Female) in Khyber Pakhtunkhwa on need basis (Phase-III). |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 19.939 | 4.24 | 0 | 0 | 0 | 0 | 4.24 | 15.699 | - |
21% October - 2017 |
Work order issued. Site not cleared (GGHS Kalpani). |
No Image |
1) Construction of 1 Cluster Hostel (Female) in Buner | |||||||||||||||||||
331 (OG) |
130339-Construction of 6 Cluster Hostels (Female) in Khyber Pakhtunkhwa on need basis (Phase-III). |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 19.939 | 4.24 | 0 | 0 | 0 | 0 | 4.24 | 15.699 | - |
21% June - 2018 |
RW both side upto DPC level. |
No Image |
1) Construction of 1 Cluster Hostel (Female) in Buner PK-78 | |||||||||||||||||||
331 (OG) |
130339-Construction of 6 Cluster Hostels (Female) in Khyber Pakhtunkhwa on need basis (Phase-III). |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 19.939 | 4.24 | 0 | 0 | 0 | 0 | 4.24 | 15.699 | - |
21% May - 2018 |
RW foundation concrete laid. |
No Image |
1) Construction of 1 Cluster Hostel (Female) in Buner PK-78 | |||||||||||||||||||
331 (OG) |
130339-Construction of 6 Cluster Hostels (Female) in Khyber Pakhtunkhwa on need basis (Phase-III). |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 19.939 | 4.24 | 0 | 0 | 0 | 0 | 4.24 | 15.699 | - |
21% April - 2018 |
RW foundation concrete laid. |
No Image |
1) Construction of 1 Cluster Hostel (Female) in Buner PK-78 | |||||||||||||||||||
331 (OG) |
130339-Construction of 6 Cluster Hostels (Female) in Khyber Pakhtunkhwa on need basis (Phase-III). |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 19.939 | 4.24 | 0 | 0 | 0 | 0 | 4.24 | 15.699 | - |
21% March - 2018 |
Layout given. |
No Image |
1) Construction of 1 Cluster Hostel (Female) in Buner PK-78 | |||||||||||||||||||
331 (OG) |
130339-Construction of 6 Cluster Hostels (Female) in Khyber Pakhtunkhwa on need basis (Phase-III). |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 19.939 | 4.24 | 0 | 0 | 0 | 0 | 4.24 | 15.699 | - |
21% February - 2018 |
Work order issued. Site not cleared (GGHS Kalpani). |
No Image |
1) Construction of 1 Cluster Hostel (Female) in Buner PK-78 | |||||||||||||||||||
331 (OG) |
130339-Construction of 6 Cluster Hostels (Female) in Khyber Pakhtunkhwa on need basis (Phase-III). |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 19.939 | 4.24 | 0 | 0 | 0 | 0 | 4.24 | 15.699 | - |
21% January - 2018 |
Work order issued. Site not cleared (GGHS Kalpani). |
No Image |
1) Construction of 1 Cluster Hostel (Female) in Buner | |||||||||||||||||||
331 (OG) |
130339-Construction of 6 Cluster Hostels (Female) in Khyber Pakhtunkhwa on need basis (Phase-III). |
Chitral |
07-12-15 | 30-06-18 | - | 25-03-15 | - | 23.156 | 18.977 | 2 | 2 | 2 | 2 | 20.977 | 2.179 | 91% |
91% December - 2017 |
Completed. |
No Image |
Cluster Hostel Chitral (40 person female) | |||||||||||||||||||
331 (OG) |
130339-Construction of 6 Cluster Hostels (Female) in Khyber Pakhtunkhwa on need basis (Phase-III). |
Chitral |
- | 30-06-18 | - | 25-03-15 | - | 23.156 | 18.977 | 2 | 2 | 2 | 0.704 | 19.681 | 2.179 | 91% |
85% September - 2017 |
Completed. |
No Image |
Cluster Hostel Chitral (40 person female) | |||||||||||||||||||
331 (OG) |
130339-Construction of 6 Cluster Hostels (Female) in Khyber Pakhtunkhwa on need basis (Phase-III). |
Chitral |
- | 30-06-18 | - | 25-03-15 | - | 23.156 | 18.977 | 0 | 0 | 0 | 0 | 18.977 | 4.179 | - |
82% August - 2017 |
Completed. |
No Image |
Cluster Hostel Chitral (40 person female) | |||||||||||||||||||
331 (OG) |
130339-Construction of 6 Cluster Hostels (Female) in Khyber Pakhtunkhwa on need basis (Phase-III). |
Chitral |
- | 30-06-18 | - | 25-03-15 | - | 23.156 | 18.977 | 0 | 0 | 0 | 0 | 18.977 | 4.179 | - |
82% July - 2017 |
Completed. |
No Image |
Cluster Hostel Chitral (40 person female) | |||||||||||||||||||
331 (OG) |
130339-Construction of 6 Cluster Hostels (Female) in Khyber Pakhtunkhwa on need basis (Phase-III). |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 23.156 | 18.977 | 2 | 2 | 2 | 0.704 | 19.681 | 2.179 | 91% |
85% November - 2017 |
Completed. |
No Image |
Cluster Hostel Chitral (40 person female) | |||||||||||||||||||
331 (OG) |
130339-Construction of 6 Cluster Hostels (Female) in Khyber Pakhtunkhwa on need basis (Phase-III). |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 23.156 | 18.977 | 2 | 2 | 2 | 0.704 | 19.681 | 2.179 | 91% |
85% October - 2017 |
Completed. |
No Image |
Cluster Hostel Chitral (40 person female) | |||||||||||||||||||
331 (OG) |
130339-Construction of 6 Cluster Hostels (Female) in Khyber Pakhtunkhwa on need basis (Phase-III). |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 23.156 | 18.977 | 7.744 | 7.744 | 7.744 | 3.122 | 22.099 | 0 | 100% |
95% June - 2018 |
Completed. |
No Image |
Cluster Hostel at Chitral (construction of 40 person female) | |||||||||||||||||||
331 (OG) |
130339-Construction of 6 Cluster Hostels (Female) in Khyber Pakhtunkhwa on need basis (Phase-III). |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 23.156 | 18.977 | 3.25 | 3.25 | 3.25 | 2.614 | 21.591 | 0.929 | 96% |
93% May - 2018 |
Completed. |
No Image |
Cluster Hostel at Chitral (construction of 40 person female) | |||||||||||||||||||
331 (OG) |
130339-Construction of 6 Cluster Hostels (Female) in Khyber Pakhtunkhwa on need basis (Phase-III). |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 23.156 | 18.977 | 3.25 | 3.25 | 3.25 | 2.614 | 21.591 | 0.929 | 96% |
93% April - 2018 |
Completed. |
No Image |
Cluster Hostel at Chitral (construction of 40 person female) | |||||||||||||||||||
331 (OG) |
130339-Construction of 6 Cluster Hostels (Female) in Khyber Pakhtunkhwa on need basis (Phase-III). |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 23.156 | 18.977 | 3.25 | 3.25 | 3.25 | 2.614 | 21.591 | 0.929 | 96% |
93% March - 2018 |
Completed. |
No Image |
Cluster Hostel at Chitral (construction of 40 person female) | |||||||||||||||||||
331 (OG) |
130339-Construction of 6 Cluster Hostels (Female) in Khyber Pakhtunkhwa on need basis (Phase-III). |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 23.156 | 18.977 | 2 | 2 | 2 | 2 | 20.977 | 2.179 | 91% |
91% February - 2018 |
Completed. |
ADP's Images |
Cluster Hostel Chitral (40 person female) | |||||||||||||||||||
331 (OG) |
130339-Construction of 6 Cluster Hostels (Female) in Khyber Pakhtunkhwa on need basis (Phase-III). |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 23.156 | 18.977 | 2 | 2 | 2 | 2 | 20.977 | 2.179 | 91% |
91% January - 2018 |
Completed. |
No Image |
Cluster Hostel Chitral (40 person female) | |||||||||||||||||||
331 (OG) |
130339-Construction of 6 Cluster Hostels (Female) in Khyber Pakhtunkhwa on need basis (Phase-III). |
D.I.Khan |
14-06-15 | 30-06-18 | - | 25-03-15 | - | 23.164 | 24.752 | 0 | 0 | 0 | 0 | 24.752 | 0 | - |
100% December - 2017 |
Completed & H/O (1 unit). |
No Image |
GGHSS Paharpur PK-68 | |||||||||||||||||||
331 (OG) |
130339-Construction of 6 Cluster Hostels (Female) in Khyber Pakhtunkhwa on need basis (Phase-III). |
D.I.Khan |
14-06-15 | 30-06-18 | - | 25-03-15 | - | 23.164 | 24.752 | 0 | 0 | 0 | 0 | 24.752 | 0 | - |
100% September - 2017 |
Completed & H/O (1 unit). |
No Image |
GGHSS Paharpur PK-68 | |||||||||||||||||||
331 (OG) |
130339-Construction of 6 Cluster Hostels (Female) in Khyber Pakhtunkhwa on need basis (Phase-III). |
D.I.Khan |
14-06-15 | 30-06-18 | - | 25-03-15 | - | 23.164 | 24.752 | 0 | 0 | 0 | 0 | 24.752 | 0 | - |
100% August - 2017 |
Completed & H/O (1 unit). |
No Image |
GGHSS Paharpur PK-68 | |||||||||||||||||||
331 (OG) |
130339-Construction of 6 Cluster Hostels (Female) in Khyber Pakhtunkhwa on need basis (Phase-III). |
D.I.Khan |
14-06-15 | 30-06-18 | - | 25-03-15 | - | 23.164 | 24.752 | 0 | 0 | 0 | 0 | 24.752 | 0 | - |
100% July - 2017 |
Completed & H/O (1 unit). |
No Image |
GGHSS Paharpur PK-68 | |||||||||||||||||||
331 (OG) |
130339-Construction of 6 Cluster Hostels (Female) in Khyber Pakhtunkhwa on need basis (Phase-III). |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 23.164 | 24.752 | 0 | 0 | 0 | 0 | 24.752 | 0 | - |
100% November - 2017 |
Completed & H/O (1 unit). |
No Image |
GGHSS Paharpur PK-68 | |||||||||||||||||||
331 (OG) |
130339-Construction of 6 Cluster Hostels (Female) in Khyber Pakhtunkhwa on need basis (Phase-III). |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 23.164 | 24.752 | 0 | 0 | 0 | 0 | 24.752 | 0 | - |
100% October - 2017 |
Completed & H/O (1 unit). |
No Image |
GGHSS Paharpur PK-68 | |||||||||||||||||||
331 (OG) |
130339-Construction of 6 Cluster Hostels (Female) in Khyber Pakhtunkhwa on need basis (Phase-III). |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 23.164 | 24.752 | 0 | 0 | 0 | 0 | 24.752 | 0 | - |
100% June - 2018 |
Completed & H/O (1 unit). |
No Image |
GGHSS Paharpur PK-68 | |||||||||||||||||||
331 (OG) |
130339-Construction of 6 Cluster Hostels (Female) in Khyber Pakhtunkhwa on need basis (Phase-III). |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 23.164 | 24.752 | 0 | 0 | 0 | 0 | 24.752 | 0 | - |
100% May - 2018 |
Completed & H/O (1 unit). |
No Image |
GGHSS Paharpur PK-68 | |||||||||||||||||||
331 (OG) |
130339-Construction of 6 Cluster Hostels (Female) in Khyber Pakhtunkhwa on need basis (Phase-III). |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 23.164 | 24.752 | 0 | 0 | 0 | 0 | 24.752 | 0 | - |
100% April - 2018 |
Completed & H/O (1 unit). |
No Image |
GGHSS Paharpur PK-68 | |||||||||||||||||||
331 (OG) |
130339-Construction of 6 Cluster Hostels (Female) in Khyber Pakhtunkhwa on need basis (Phase-III). |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 23.164 | 24.752 | 0 | 0 | 0 | 0 | 24.752 | 0 | - |
100% March - 2018 |
Completed & H/O (1 unit). |
No Image |
GGHSS Paharpur PK-68 | |||||||||||||||||||
331 (OG) |
130339-Construction of 6 Cluster Hostels (Female) in Khyber Pakhtunkhwa on need basis (Phase-III). |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 23.164 | 24.752 | 0 | 0 | 0 | 0 | 24.752 | 0 | - |
100% February - 2018 |
Completed & H/O (1 unit). |
No Image |
GGHSS Paharpur PK-68 | |||||||||||||||||||
331 (OG) |
130339-Construction of 6 Cluster Hostels (Female) in Khyber Pakhtunkhwa on need basis (Phase-III). |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 23.164 | 24.752 | 0 | 0 | 0 | 0 | 24.752 | 0 | - |
100% January - 2018 |
Completed & H/O (1 unit). |
No Image |
GGHSS Paharpur PK-68 | |||||||||||||||||||
331 (OG) |
130339-Construction of 6 Cluster Hostels (Female) in Khyber Pakhtunkhwa on need basis (Phase-III). |
Haripur |
08-12-14 | 30-06-18 | - | 25-03-15 | - | 23.241 | 16.45 | 5 | 5 | 5 | 0 | 16.45 | 1.791 | 92% |
71% December - 2017 |
GF, FF - finishing in progress (1 unit). |
No Image |
331 (OG) |
130339-Construction of 6 Cluster Hostels (Female) in Khyber Pakhtunkhwa on need basis (Phase-III). |
Haripur |
08-12-14 | 30-06-18 | - | 25-03-15 | - | 23.241 | 16.45 | 0 | 0 | 0 | 0 | 16.45 | 6.791 | - |
71% September - 2017 |
GF, FF - finishing in progress (1 unit). |
No Image |
331 (OG) |
130339-Construction of 6 Cluster Hostels (Female) in Khyber Pakhtunkhwa on need basis (Phase-III). |
Haripur |
08-12-14 | 30-06-18 | - | 25-03-15 | - | 23.241 | 16.45 | 0 | 0 | 0 | 0 | 16.45 | 6.791 | - |
71% August - 2017 |
GF, FF - finishing in progress (1 unit). |
No Image |
331 (OG) |
130339-Construction of 6 Cluster Hostels (Female) in Khyber Pakhtunkhwa on need basis (Phase-III). |
Haripur |
08-12-14 | 30-06-18 | - | 25-03-15 | - | 23.241 | 16.45 | 0 | 0 | 0 | 0 | 16.45 | 6.791 | - |
71% July - 2017 |
GF, FF - finishing in progress (1 unit). |
No Image |
331 (OG) |
130339-Construction of 6 Cluster Hostels (Female) in Khyber Pakhtunkhwa on need basis (Phase-III). |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 23.241 | 16.45 | 5 | 5 | 5 | 0 | 16.45 | 1.791 | 92% |
71% November - 2017 |
GF, FF - finishing in progress (1 unit). |
No Image |
331 (OG) |
130339-Construction of 6 Cluster Hostels (Female) in Khyber Pakhtunkhwa on need basis (Phase-III). |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 23.241 | 16.45 | 5 | 5 | 5 | 0 | 16.45 | 1.791 | 92% |
71% October - 2017 |
GF, FF - finishing in progress (1 unit). |
No Image |
331 (OG) |
130339-Construction of 6 Cluster Hostels (Female) in Khyber Pakhtunkhwa on need basis (Phase-III). |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 23.241 | 16.449 | 2.905 | 2.905 | 2.905 | 2.905 | 19.354 | 3.887 | 83% |
83% June - 2018 |
Completed (1 unit). |
No Image |
GGSMHS Haripur PK-50 | |||||||||||||||||||
331 (OG) |
130339-Construction of 6 Cluster Hostels (Female) in Khyber Pakhtunkhwa on need basis (Phase-III). |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 23.241 | 16.449 | 5 | 5 | 5 | 0 | 16.449 | 1.792 | 92% |
71% May - 2018 |
GF, FF - finishing in progress (1 unit). |
No Image |
GGSMHS Haripur PK-50 | |||||||||||||||||||
331 (OG) |
130339-Construction of 6 Cluster Hostels (Female) in Khyber Pakhtunkhwa on need basis (Phase-III). |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 23.241 | 16.449 | 5 | 5 | 5 | 0 | 16.449 | 1.792 | 92% |
71% April - 2018 |
GF, FF - finishing in progress (1 unit). |
No Image |
GGSMHS Haripur PK-50 | |||||||||||||||||||
331 (OG) |
130339-Construction of 6 Cluster Hostels (Female) in Khyber Pakhtunkhwa on need basis (Phase-III). |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 23.241 | 16.449 | 5 | 5 | 5 | 0 | 16.449 | 1.792 | 92% |
71% March - 2018 |
GF, FF - finishing in progress (1 unit). |
No Image |
GGSMHS Haripur PK-50 | |||||||||||||||||||
331 (OG) |
130339-Construction of 6 Cluster Hostels (Female) in Khyber Pakhtunkhwa on need basis (Phase-III). |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 23.241 | 16.45 | 5 | 5 | 5 | 0 | 16.45 | 1.791 | 92% |
71% February - 2018 |
GF, FF - finishing in progress (1 unit). |
ADP's Images |
GGSMHS Haripur PK-50 | |||||||||||||||||||
331 (OG) |
130339-Construction of 6 Cluster Hostels (Female) in Khyber Pakhtunkhwa on need basis (Phase-III). |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 23.241 | 16.45 | 5 | 5 | 5 | 0 | 16.45 | 1.791 | 92% |
71% January - 2018 |
GF, FF - finishing in progress (1 unit). |
No Image |
GGSMHS Haripur PK-50 | |||||||||||||||||||
331 (OG) |
130339-Construction of 6 Cluster Hostels (Female) in Khyber Pakhtunkhwa on need basis (Phase-III). |
Kohat |
- | 30-06-18 | - | 25-03-15 | - | 29.333 | 0 | 0 | 0 | 0 | 0 | 0 | 29.333 | - |
- December - 2017 |
Work order issued but site not yet H/O. |
No Image |
GGCMHS Kohat | |||||||||||||||||||
331 (OG) |
130339-Construction of 6 Cluster Hostels (Female) in Khyber Pakhtunkhwa on need basis (Phase-III). |
Kohat |
- | 30-06-18 | - | 25-03-15 | - | 29.333 | 0 | 0 | 0 | 0 | 0 | 0 | 29.333 | - |
- September - 2017 |
Work order issued but site not yet H/O. |
No Image |
GGCMHS Kohat | |||||||||||||||||||
Pages : 1 2 |