429 (OG) |
150521-Establishment of Timergara Medical College Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 500 | 0 | 40 | 40 | 26.25 | 8.835 | 8.835 | 460 | 8% |
2% December - 2018 |
Academic block - work in progress. |
No Image |
Dir Lower | |||||||||||||||||||
429 (OG) |
150521-Establishment of Timergara Medical College Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 500 | 0 | 40 | 40 | 12.5 | 0 | 0 | 460 | 8% |
- November - 2018 |
Academic block - work in progress. |
No Image |
Dir Lower | |||||||||||||||||||
429 (OG) |
150521-Establishment of Timergara Medical College Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 500 | 0 | 40 | 40 | 12.5 | 0 | 0 | 460 | 8% |
- November - 2018 |
Academic block - work in progress. |
No Image |
Dir Lower | |||||||||||||||||||
429 (OG) |
150521-Establishment of Timergara Medical College Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 500 | 0 | 40 | 40 | 26.25 | 23.085 | 23.085 | 460 | 8% |
5% April - 2019 |
Academic block - work in progress. Demand Rs.30 m. |
No Image |
Dir Lower | |||||||||||||||||||
429 (OG) |
150521-Establishment of Timergara Medical College Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 500 | 0 | 40 | 40 | 26.25 | 23.085 | 23.085 | 460 | 8% |
5% March - 2019 |
Academic block - work in progress. Demand Rs.30 m. |
No Image |
Dir Lower | |||||||||||||||||||
429 (OG) |
150521-Establishment of Timergara Medical College Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 500 | 0 | 40 | 40 | 26.25 | 23.085 | 23.085 | 460 | 8% |
5% March - 2019 |
Academic block - work in progress. Demand Rs.30 m. |
No Image |
Dir Lower | |||||||||||||||||||
429 (OG) |
150521-Establishment of Timergara Medical College Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 500 | 0 | 40 | 40 | 26.25 | 23.085 | 23.085 | 460 | 8% |
5% February - 2019 |
Academic block - work in progress. Demand Rs.30 m. |
No Image |
Dir Lower | |||||||||||||||||||
429 (OG) |
150521-Establishment of Timergara Medical College Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 500 | 0 | 40 | 40 | 26.25 | 8.835 | 8.835 | 460 | 8% |
2% January - 2019 |
Academic block - work in progress. |
No Image |
Dir Lower | |||||||||||||||||||
429 (New) |
200067-Peshawar Schools Development Plan. |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1000 | 0 | 100 | 100 | 0 | 0 | 0 | 900 | 10% |
- December - 2020 |
Approved. |
No Image |
429 (New) |
200067-Peshawar Schools Development Plan. |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1000 | 0 | 100 | 100 | 0 | 0 | 0 | 900 | 10% |
- December - 2020 |
Approved. |
No Image |
429 (New) |
200067-Peshawar Schools Development Plan. |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 1000 | 0 | 100 | 100 | 0 | 0 | 0 | 0 | - |
- October - 2020 |
No Image | |
429 (New) |
200067-Peshawar Schools Development Plan. |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 1000 | 0 | 100 | 100 | 0 | 0 | 0 | 0 | - |
- September - 2020 |
No Image | |
429 (New) |
200067-Peshawar Schools Development Plan. |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 1000 | 0 | 100 | 100 | 0 | 0 | 0 | 0 | - |
- August - 2020 |
No Image | |
429 (New) |
200067-Peshawar Schools Development Plan. |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 1000 | 0 | 100 | 0 | 0 | 0 | 0 | 0 |
- July - 2020 |
No Image | ||
429 (New) |
200067-Peshawar Schools Development Plan. |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1000 | 0 | 0 | 0 | 0 | 0 | 0 | 1000 | - |
- May - 2021 |
27- Units
Finanical Bid sent to S.E C&W Circle Peshawar on 03-06-21 |
No Image |
429 (New) |
200067-Peshawar Schools Development Plan. |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1000 | 0 | 100 | 100 | 0 | 0 | 0 | 900 | 10% |
- April - 2021 |
Approved. |
No Image |
429 (New) |
200067-Peshawar Schools Development Plan. |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1000 | 0 | 100 | 100 | 0 | 0 | 0 | 900 | 10% |
- March - 2021 |
Approved. |
No Image |
429 (New) |
200067-Peshawar Schools Development Plan. |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1000 | 0 | 100 | 100 | 0 | 0 | 0 | 900 | 10% |
- February - 2021 |
Approved. |
No Image |
429 (New) |
200067-Peshawar Schools Development Plan. |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1000 | 0 | 100 | 100 | 0 | 0 | 0 | 900 | 10% |
- January - 2021 |
Approved. |
No Image |
429 (OG) |
20602-Construction of Central Police Office in Peshawar. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 658.831 | 418.79 | 25 | 25 | 12.5 | 12.5 | 431.29 | 215.041 | 67% |
65% September - 2018 |
Pack-II completed except remaining portion. OHT in progress. Mosque completed. Work started on balance work of Pack-I & II. |
No Image |
Peshawar (Package-III (a) Main Building (b) Tube Well (c) Overhead Tank (d) Consultancy) | |||||||||||||||||||
429 (OG) |
20602-Construction of Central Police Office in Peshawar. |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 658.831 | 418.79 | 25 | 25 | 0 | 0 | 418.79 | 215.041 | 67% |
64% July - 2018 |
Pack-II completed except remaining portion. OHT in progress. Mosque completed. Work started on balance work of Pack-I & II. |
No Image |
Peshawar (Package-III (a) Main Building (b) Tube Well (c) Overhead Tank (d) Consultancy) | |||||||||||||||||||
Pages : 1 |