Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2018, January - 2020, January - 2021, February - 2018, February - 2020, February - 2021, March - 2018, March - 2020, March - 2021, April - 2018, April - 2020, April - 2021, May - 2018, May - 2020, May - 2021, June - 2018, July - 2018, July - 2020, July - 2017, August - 2019, August - 2020, August - 2017, September - 2018, September - 2019, September - 2020, September - 2017, October - 2019, October - 2020, October - 2017, November - 2019, November - 2017, December - 2019, December - 2020, December - 2017,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
50
(OG)
150289-Construction of 100 No Patwar Khanas in Khyber Pakhtunkhwa (Phase-II).
Battagram
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
September - 2018
2 Nos Patwar Khanas identified. PC-I/DCE for Rs.10.286 m on MRS-2017 submitted to DC on 26/03/2018.
No Image
1) Tikri Mera
2) Shamlai
50
(OG)
150289-Construction of 100 No Patwar Khanas in Khyber Pakhtunkhwa (Phase-II).
Battagram
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
July - 2018
2 Nos Patwar Khanas identified. PC-I/DCE for Rs.10.286 m on MRS-2017 submitted to DC on 26/03/2018.
No Image
1) Tikri Mera
2) Shamlai
50
(OG)
150289-Construction of 100 No Patwar Khanas in Khyber Pakhtunkhwa (Phase-II).
Charsadda
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
September - 2018
PC-I/DCE submitted to SPO BOR on 21/03/2016.
No Image
1) Shabqadar PK-22
2) Maira Nisatta PK-17
3) Charsadda PK-17
4) Prang Safar Khel PK-17
5) Bari Band PK-20
50
(OG)
150289-Construction of 100 No Patwar Khanas in Khyber Pakhtunkhwa (Phase-II).
Charsadda
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
July - 2018
PC-I/DCE submitted to SPO BOR on 21/03/2016.
No Image
1) Shabqadar PK-22
2) Maira Nisatta PK-17
3) Charsadda PK-17
4) Prang Safar Khel PK-17
5) Bari Band PK-20
50
(OG)
150289-Construction of 100 No Patwar Khanas in Khyber Pakhtunkhwa (Phase-II).
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
September - 2018
PC-I/DCE based on MRS-2016 submitted to DC DI.Khan on 29/07/2016.
No Image
1) Ismail Baloch Naivela Paroa
2) Adil Sepra Paroa
3) Kotla Saidan
4) Thoya Fazil
5) Said Alian Paharpur
6) Rangpur Paharpur
7) Mithapur Paharpur
8) Bastian Paroa
9) Makar Paroa
10) Sikandar Janubi Paroa
11) Hammu Nala Paroa
12) Mahra Paroa
50
(OG)
150289-Construction of 100 No Patwar Khanas in Khyber Pakhtunkhwa (Phase-II).
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
July - 2018
PC-I/DCE based on MRS-2016 submitted to DC DI.Khan on 29/07/2016.
No Image
1) Ismail Baloch Naivela Paroa
2) Adil Sepra Paroa
3) Kotla Saidan
4) Thoya Fazil
5) Said Alian Paharpur
6) Rangpur Paharpur
7) Mithapur Paharpur
8) Bastian Paroa
9) Makar Paroa
10) Sikandar Janubi Paroa
11) Hammu Nala Paroa
12) Mahra Paroa
50
(OG)
150289-Construction of 100 No Patwar Khanas in Khyber Pakhtunkhwa (Phase-II).
Karak
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
September - 2018
PC-I/DCE for Rs.41.712 m re-submitted to DS-I BOR as per MRS-2017.
No Image
10 Nos in Karak
50
(OG)
150289-Construction of 100 No Patwar Khanas in Khyber Pakhtunkhwa (Phase-II).
Karak
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
July - 2018
PC-I/DCE for Rs.41.712 m re-submitted to DS-I BOR as per MRS-2017.
No Image
10 Nos in Karak
50
(OG)
191012-180071 - Agriculture Development in Sub-Division Lakki. [MA]
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 12.7 2.153 0 0 0 0 2.153 0 - -
December - 2020
No Image
50
(OG)
191012-180071 - Agriculture Development in Sub-Division Lakki. [MA]
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 12.7 2.153 0 0 0 0 2.153 0 - -
December - 2020
No Image
50
(OG)
191012-180071 - Agriculture Development in Sub-Division Lakki. [MA]
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 12.7 2.153 0 0 0 0 2.153 0 - -
October - 2020
No Image
50
(OG)
191012-180071 - Agriculture Development in Sub-Division Lakki. [MA]
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 12.7 2.153 0 0 0 0 2.153 0 - -
September - 2020
No Image
50
(OG)
191012-180071 - Agriculture Development in Sub-Division Lakki. [MA]
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 12.7 2.153 0 0 0 0 2.153 0 - -
August - 2020
No Image
50
(OG)
191012-180071 - Agriculture Development in Sub-Division Lakki. [MA]
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 12.7 2.153 0 0 0 0 2.153 0 -
July - 2020
No Image
50
(OG)
191012-180071 - Agriculture Development in Sub-Division Lakki. [MA]
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 12.7 2.153 0 0 0 0 2.153 0 - -
May - 2021
No Image
50
(OG)
191012-180071 - Agriculture Development in Sub-Division Lakki. [MA]
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 12.7 2.153 0 0 0 0 2.153 0 - -
April - 2021
No Image
50
(OG)
191012-180071 - Agriculture Development in Sub-Division Lakki. [MA]
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 12.7 2.153 0 0 0 0 2.153 0 - -
March - 2021
No Image
50
(OG)
191012-180071 - Agriculture Development in Sub-Division Lakki. [MA]
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 12.7 2.153 0 0 0 0 2.153 0 - -
February - 2021
No Image
50
(OG)
191012-180071 - Agriculture Development in Sub-Division Lakki. [MA]
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 12.7 2.153 0 0 0 0 2.153 0 - -
January - 2021
No Image
50
(OG)
160607-Construction and rehabilitation of Darul Uloom Haqannia, Akora Khattak.
Nowshera
- 30-06-18 - 28-03-17 - 300 25.938 275 275 133.5 46.235 72.173 0 100% 24%
December - 2017
Academic block - Basemnet Roof Laiid . Blaock B - Basement roffing in progress. Block C - Basement Columns in progress.
No Image
50
(OG)
160607-Construction and rehabilitation of Darul Uloom Haqannia, Akora Khattak.
Nowshera
- 30-06-18 - 28-03-17 - 300 25.938 275 275 0 0 25.938 0 100% 9%
September - 2017
Academic block - excavation completed. Foundation upto joint A in progress.
No Image
50
(OG)
160607-Construction and rehabilitation of Darul Uloom Haqannia, Akora Khattak.
Nowshera
- 30-06-18 - 28-03-17 - 300 25.938 275 275 0 0 25.938 0 100% 9%
August - 2017
Academic block - excavation completed. Foundation upto joint A in progress.
No Image
50
(OG)
160607-Construction and rehabilitation of Darul Uloom Haqannia, Akora Khattak.
Nowshera
- 30-06-18 - 28-03-17 - 300 25.938 275 275 0 0 25.938 0 100% 9%
July - 2017
Academic block - excavation completed. Foundation upto joint A in progress.
No Image
50
(OG)
160607-Construction and rehabilitation of Darul Uloom Haqannia, Akora Khattak.
Nowshera
30-11--1 30-11--1 - 30-11--1 - 300 25.938 275 275 133.5 36.658 62.596 0 100% 21%
November - 2017
Academic block - excavation completed. Foundation upto joint A in progress.
No Image
50
(OG)
160607-Construction and rehabilitation of Darul Uloom Haqannia, Akora Khattak.
Nowshera
30-11--1 30-11--1 - 30-11--1 - 300 25.938 275 275 133 23.151 49.089 0 100% 16%
October - 2017
Academic block - excavation completed. Foundation upto joint A in progress.
No Image
50
(OG)
160607-Construction and rehabilitation of Darul Uloom Haqannia, Akora Khattak.
Nowshera
30-11--1 30-11--1 - 30-11--1 - 300 25.938 275 275 133.5 106.899 132.837 0 100% 44%
June - 2018
Academic block - basement roof laid. Block-B - basement roofing in progress. Block-C - basement columns in progress.
No Image
Akora Khattak Nowshera
50
(OG)
160607-Construction and rehabilitation of Darul Uloom Haqannia, Akora Khattak.
Nowshera
30-11--1 30-11--1 - 30-11--1 - 300 25.938 275 275 133.5 98.757 124.695 0 100% 42%
May - 2018
Academic block - basement roof laid. Block-B - basement roofing in progress. Block-C - basement columns in progress.
No Image
Akora Khattak Nowshera
50
(OG)
160607-Construction and rehabilitation of Darul Uloom Haqannia, Akora Khattak.
Nowshera
30-11--1 30-11--1 - 30-11--1 - 300 25.938 275 275 133.5 98.757 124.695 0 100% 42%
April - 2018
Academic block - basement roof laid. Block-B - basement roofing in progress. Block-C - basement columns in progress.
No Image
Akora Khattak Nowshera
50
(OG)
160607-Construction and rehabilitation of Darul Uloom Haqannia, Akora Khattak.
Nowshera
30-11--1 30-11--1 - 30-11--1 - 300 25.938 275 275 133.5 89.168 115.106 0 100% 38%
March - 2018
Academic block - basement roof laid. Block-B - basement roofing in progress. Block-C - basement columns in progress.
No Image
Akora Khattak Nowshera
50
(OG)
160607-Construction and rehabilitation of Darul Uloom Haqannia, Akora Khattak.
Nowshera
30-11--1 30-11--1 - 30-11--1 - 300 25.938 275 275 133.5 73.915 99.853 0 100% 33%
February - 2018
Academic block - Basemnet Roof Laiid . Blaock B - Basement roffing in progress. Block C - Basement Columns in progress.
No Image
Akora Khattak Nowshera
50
(OG)
160607-Construction and rehabilitation of Darul Uloom Haqannia, Akora Khattak.
Nowshera
30-11--1 30-11--1 - 30-11--1 - 300 25.938 275 275 133.5 56.166 82.104 0 100% 27%
January - 2018
Academic block - Basemnet Roof Laiid . Blaock B - Basement roffing in progress. Block C - Basement Columns in progress.
No Image
50
(New)
190074-Construction of Community Based School for Sikh Community in Peshawar.
Peshawar
30-11--1 30-11--1 - 30-11--1 Line Deptt 20 0 5 5 0 0 0 0 - -
August - 2019
No Image
50
(New)
190074-Construction of Community Based School for Sikh Community in Peshawar.
Peshawar
BD-2
30-11--1 30-11--1 - 30-11--1 Line Deptt 20 0 5 0 0 0 0 0 - -
December - 2019
DDWP held on 26.09.19. Deferred due to issue of land.
No Image
50
(New)
190074-Construction of Community Based School for Sikh Community in Peshawar.
Peshawar
BD-2
30-11--1 30-11--1 - 30-11--1 Line Deptt 20 0 5 5 0 0 0 0 - -
November - 2019
DDWP held on 26.09.19. Deferred due to issue of land.
No Image
50
(New)
190074-Construction of Community Based School for Sikh Community in Peshawar.
Peshawar
BD-2
30-11--1 30-11--1 - 30-11--1 Line Deptt 20 0 5 5 0 0 0 0 - -
October - 2019
DDWP held on 26.09.19. Deferred due to issue of land.
No Image
50
(New)
190074-Construction of Community Based School for Sikh Community in Peshawar.
Peshawar
BD-2
30-11--1 30-11--1 - 30-11--1 Line Deptt 20 0 5 5 0 0 0 0 - -
September - 2019
DDWP held on 26.09.19. Deferred due to issue of land.
No Image
50
(New)
190074-Construction of Community Based School for Sikh Community in Peshawar.
Peshawar
BD-2
30-11--1 30-11--1 - 30-11--1 Line Deptt 20 0 5 0 0 0 0 0 - -
May - 2020
DDWP held on 26.09.19. Deferred due to issue of land. NIT called.
No Image
50
(New)
190074-Construction of Community Based School for Sikh Community in Peshawar.
Peshawar
BD-2
30-11--1 30-11--1 - 30-11--1 Line Deptt 20 0 5 0 0 0 0 0 - -
April - 2020
DDWP held on 26.09.19. Deferred due to issue of land. NIT called.
No Image
50
(New)
190074-Construction of Community Based School for Sikh Community in Peshawar.
Peshawar
BD-2
30-11--1 30-11--1 - 30-11--1 Line Deptt 20 0 5 0 0 0 0 0 - -
March - 2020
DDWP held on 26.09.19. Deferred due to issue of land. NIT called.
No Image
50
(New)
190074-Construction of Community Based School for Sikh Community in Peshawar.
Peshawar
BD-2
30-11--1 30-11--1 - 30-11--1 Line Deptt 20 0 5 0 0 0 0 0 - -
February - 2020
DDWP held on 26.09.19. Deferred due to issue of land. NIT called.
No Image
50
(New)
190074-Construction of Community Based School for Sikh Community in Peshawar.
Peshawar
BD-2
30-11--1 30-11--1 - 30-11--1 Line Deptt 20 0 5 0 0 0 0 0 - -
January - 2020
DDWP held on 26.09.19. Deferred due to issue of land. NIT called.
No Image
50
(OG)
150289-Construction of 100 No Patwar Khanas in Khyber Pakhtunkhwa (Phase-II).
Provincial
30-11--1 30-11--1 - 30-11--1 - 453.37 0 0.001 0.001 0 0 0 0 - -
September - 2018
PC-I/DCE submitted.
No Image
50
(OG)
150289-Construction of 100 No Patwar Khanas in Khyber Pakhtunkhwa (Phase-II).
Provincial
30-11--1 30-11--1 - 30-11--1 - 453.37 0 0.001 0.001 0 0 0 0 - -
July - 2018
PC-I/DCE submitted.
No Image
50
(OG)
150289-Construction of 100 No Patwar Khanas in Khyber Pakhtunkhwa (Phase-II).
Swat
30-11--1 30-11--1 - 30-11--1 - 86.482 0 0 0 0 0 0 86.482 - -
September - 2018
PC-I/DCE submitted.
No Image
1) Khwaza Khela
2) Shin
3) Kanju
4) Kota
5) Takhta Band
6) Totano Banda
7) Balogram
8) Kal Kalay
9) UC Shawar
10) UC Arkot
11) UC Pir Kilay
50
(OG)
150289-Construction of 100 No Patwar Khanas in Khyber Pakhtunkhwa (Phase-II).
Swat
30-11--1 30-11--1 - 30-11--1 - 86.482 0 0 0 0 0 0 86.482 - -
July - 2018
PC-I/DCE submitted.
No Image
1) Khwaza Khela
2) Shin
3) Kanju
4) Kota
5) Takhta Band
6) Totano Banda
7) Balogram
8) Kal Kalay
9) UC Shawar
10) UC Arkot
11) UC Pir Kilay
50
(OG)
150289-Construction of 100 No Patwar Khanas in Khyber Pakhtunkhwa (Phase-II).
Tank
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
September - 2018
PC-I/DCE for Rs.59.235 m submitted to DC Tank on 07/03/2016.
No Image
1) Gul Imam
2) Sheikh Sultan
3) Gara Baloch
4) Umer Adda
5) Pai
6) Gomal Bazar
7) Tajori
8) Mulazai Kakakhel
9) Manjhi Khel
10) Chesan Kach
11) Waraspon
12) Ama Khel
50
(OG)
150289-Construction of 100 No Patwar Khanas in Khyber Pakhtunkhwa (Phase-II).
Tank
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
July - 2018
PC-I/DCE for Rs.59.235 m submitted to DC Tank on 07/03/2016.
No Image
1) Gul Imam
2) Sheikh Sultan
3) Gara Baloch
4) Umer Adda
5) Pai
6) Gomal Bazar
7) Tajori
8) Mulazai Kakakhel
9) Manjhi Khel
10) Chesan Kach
11) Waraspon
12) Ama Khel
Pages : 1